ODOT contract 250371 bid tabulation
FRA-US 33-28.61 (INTERSECTION). Let by Ohio DOT on July 31, 2025, FRA. 5 bids received; low bid $255,800 by Shelly & Sands Inc, +1.9% against the engineer's estimate of $251,000.
- Owner
- Ohio DOT
- Letting
- 31 JUL 2025
- Pay items
- 51
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $255,800 | Low | +2.0% |
| 2 | Shelly Company | $255,964 | 0.0% | +2.0% |
| 3 | Axis Civil Construction LLC | $274,478 | +7.0% | +9.0% |
| 4 | Strawser Paving Co Inc | $278,564 | +9.0% | +11% |
| 5 | Complete General Construction Company | $283,991 | +11% | +13% |
Engineer's estimate: $251,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Shelly Company | 3. Axis Civil Construction LLC | 4. Strawser Paving Co Inc | 5. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $9,283.00 | $6,500.00 | $5,000.00 | $500.00 | $10,400 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $775.00 | $345.00 | $750.00 | $800.00 | $1,400.00 |
| 3 | Pavement removed, as per plan (202E23001) | SY | 740 | $21.00 | $26.00 | $19.50 | $15.00 | $16.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 40 | $34.00 | $35.00 | $24.00 | $40.00 | $30.00 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 81 | $34.00 | $34.35 | $39.00 | $20.00 | $30.00 |
| 6 | Excavation (203E10000) | CY | 440 | $34.00 | $53.00 | $36.00 | $42.00 | $60.00 |
| 7 | Embankment (203E20000) | CY | 170 | $17.00 | $35.00 | $36.00 | $15.00 | $14.00 |
| 8 | Subgrade compaction (204E10000) | SY | 982 | $6.00 | $2.60 | $4.00 | $5.00 | $6.00 |
| 9 | Excavation of subgrade (204E13000) | CY | 110 | $41.00 | $41.00 | $40.00 | $125.00 | $37.00 |
| 10 | Proof rolling (204E45000) | HR | 1 | $250.00 | $240.00 | $250.00 | $160.00 | $400.00 |
| 11 | Fence, type 47RA (607E15100) | FT | 135 | $35.00 | $35.00 | $35.00 | $40.00 | $40.00 |
| 12 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $250.00 | $250.00 | $800.00 | $500.00 | $215.00 |
| 13 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $3,000.00 | $10,000 | $4,500.00 | $5,000.00 | $3,000.00 |
| 14 | Topsoil (659E00300) | CY | 178 | $33.00 | $65.00 | $49.00 | $45.00 | $65.00 |
| 15 | Seeding and mulching (659E10000) | SY | 1,596 | $3.50 | $3.29 | $2.00 | $2.00 | $2.00 |
| 16 | Repair seeding and mulching (659E14000) | SY | 80 | $3.00 | $3.10 | $2.00 | $2.00 | $2.00 |
| 17 | Inter-seeding (659E15000) | SY | 80 | $3.00 | $3.10 | $2.00 | $2.00 | $2.00 |
| 18 | Commercial fertilizer (659E20000) | TON | 0.14 | $892.00 | $891.36 | $1,250.00 | $1,250.00 | $1,250.00 |
| 19 | Lime (659E31000) | ACRE | 0.33 | $155.00 | $155.48 | $150.00 | $150.00 | $150.00 |
| 20 | Water (659E35000) | MGAL | 9 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | Erosion control (832E30000) | EACH | 3,200 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | 18" conduit, type D (611E07900) | FT | 55 | $108.00 | $75.00 | $135.00 | $135.00 | $140.00 |
| 23 | Full depth pavement sawing (252E01500) | FT | 107 | $4.00 | $7.00 | $7.00 | $5.00 | $9.00 |
| 24 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 157 | $200.00 | $211.00 | $270.00 | $260.00 | $211.00 |
| 25 | Aggregate base (304E20000) | CY | 159 | $95.00 | $72.00 | $119.00 | $100.00 | $130.00 |
| 26 | Non-tracking tack coat (407E20000) | GAL | 104 | $3.50 | $3.90 | $7.00 | $4.00 | $3.90 |
| 27 | Traffic compacted surface, type C (410E13000) | CY | 10 | $130.00 | $140.00 | $140.00 | $385.00 | $100.00 |
| 28 | Stabilized crushed aggregate (411E10000) | CY | 11 | $160.00 | $210.00 | $140.00 | $300.00 | $160.00 |
| 29 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 39 | $300.00 | $291.00 | $395.00 | $330.00 | $291.00 |
| 30 | Asphalt concrete intermediate course, type 1, (449) (441E70200) | CY | 45 | $275.00 | $291.00 | $355.00 | $310.00 | $291.00 |
| 31 | Aggregate drains, as per plan (605E31101) | FT | 29 | $17.00 | $50.00 | $40.00 | $115.00 | $20.00 |
| 32 | Compacted aggregate (617E10100) | CY | 2 | $250.00 | $800.00 | $300.00 | $1,450.00 | $250.00 |
| 33 | Rumble stripes, edge line (asphalt concrete) (618E40800) | FT | 1,070 | $10.00 | $3.20 | $3.20 | $3.20 | $3.20 |
| 34 | Maintaining traffic, misc.:maintaining traffic, MI (614E18000) | EACH | 8 | $465.00 | $465.00 | $465.00 | $465.00 | $276.00 |
| 35 | Maintaining traffic, misc.:maintaining traffic, MI (614E18000) | EACH | 26 | $53.00 | $53.00 | $53.00 | $53.00 | $55.50 |
| 36 | Ground mounted support, no. 2 post (630E02100) | FT | 30 | $17.00 | $17.00 | $15.00 | $17.00 | $23.84 |
| 37 | Ground mounted support, no. 3 post (630E03100) | FT | 60 | $19.00 | $19.00 | $30.00 | $19.00 | $26.25 |
| 38 | Sign post reflector (630E08600) | EACH | 3 | $60.00 | $60.00 | $55.00 | $60.00 | $74.32 |
| 39 | Sign, flat sheet (630E80100) | SF | 64 | $30.00 | $30.00 | $28.00 | $30.00 | $28.66 |
| 40 | Removal of ground mounted sign and disposal (630E84900) | EACH | 21 | $25.00 | $25.00 | $35.00 | $25.00 | $15.51 |
| 41 | Edge line, 6" (644E00104) | MI | 0.22 | $5,350.00 | $5,350.00 | $5,350.00 | $5,350.00 | $5,350.00 |
| 42 | Transverse/diagonal line (644E00700) | FT | 663 | $6.00 | $5.80 | $5.80 | $5.80 | $5.80 |
| 43 | Removal of pavement marking (644E30000) | FT | 271 | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 |
| 44 | Removal of pavement marking (644E30020) | EACH | 2 | $110.00 | $110.00 | $110.00 | $110.00 | $110.00 |
| 45 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $113.00 | $80.00 | $85.00 | $85.00 | $125.00 |
| 46 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,000.00 | $650.00 | $750.00 | $650.00 | $1,225.00 |
| 47 | Water (616E10000) | MGAL | 1 | $250.00 | $5.00 | $1.00 | $100.00 | $175.00 |
| 48 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,500.00 | $4,000.00 | $4,500.00 | $5,000.00 | $3,835.00 |
| 49 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $22,000 | $20,000 | $35,000 | $35,000 |
| 50 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,349.47 | $4,000.00 | $9,500.00 | $10,000 | $6,000.00 |
| 51 | Mobilization (624E10000) | LS | 1 | $13,000 | $11,250 | $20,000 | $10,000 | $14,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.