ODOT contract 250369 bid tabulation
CLA-/MOT CR/BH FY26 (CULVERT REPLACEMENT). Let by Ohio DOT on July 31, 2025, CLA. 3 bids received; low bid $365,504 by Sunesis Construction Co, +43% against the engineer's estimate of $255,000.
- Owner
- Ohio DOT
- Letting
- 31 JUL 2025
- Pay items
- 46
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sunesis Construction Co | $365,504 | Low | +43% |
| 2 | Complete General Construction Company | $656,797 | +80% | +158% |
| 3 | John R Jurgensen Company | $679,713 | +86% | +167% |
Engineer's estimate: $255,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sunesis Construction Co | 2. Complete General Construction Company | 3. John R Jurgensen Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,203 | $25,000 | $13,271 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $323.43 | $5,000.00 | $1,390.45 |
| 3 | Pavement removed (202E23000) | SY | 124 | $22.80 | $30.00 | $16.18 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 8 | $24.45 | $125.00 | $120.86 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 25 | $93.16 | $160.00 | $86.98 |
| 6 | Special - fill and plug existing conduit (202E70000) | FT | 40 | $130.13 | $600.00 | $128.69 |
| 7 | Excavation (203E10000) | CY | 313 | $31.04 | $35.00 | $60.00 |
| 8 | Embankment (203E20000) | CY | 313 | $26.60 | $40.00 | $60.00 |
| 9 | Subgrade compaction (204E10000) | SY | 124 | $5.75 | $5.00 | $7.35 |
| 10 | Rock channel protection, type C with geotextile fabric, as per plan (601E32205) | CY | 6 | $751.73 | $200.00 | $621.81 |
| 11 | Soil analysis test (659E00100) | EACH | 2 | $50.00 | $400.00 | $75.00 |
| 12 | Topsoil (659E00300) | CY | 13 | $154.71 | $60.00 | $100.00 |
| 13 | Seeding and mulching (659E10000) | SY | 115 | $30.14 | $26.50 | $25.65 |
| 14 | Commercial fertilizer (659E20000) | TON | 0.02 | $900.00 | $1,150.00 | $1,750.00 |
| 15 | Lime (659E31000) | ACRE | 0.02 | $10.00 | $175.00 | $100.00 |
| 16 | Water (659E35000) | MGAL | 1 | $10.00 | $1.00 | $1.00 |
| 17 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 |
| 18 | Concrete masonry (602E20000) | CY | 1 | $5,847.06 | $5,000.00 | $5,992.19 |
| 19 | 29" X 45" conduit, type A, 706.04 (611E52700) | FT | 70 | $587.70 | $1,900.00 | $820.73 |
| 20 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 21 | $1,059.12 | $1,050.00 | $1,050.00 |
| 21 | Aggregate base (304E20000) | CY | 21 | $151.42 | $160.00 | $253.95 |
| 22 | Non-tracking tack coat (407E20000) | GAL | 14 | $10.00 | $10.00 | $10.00 |
| 23 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 10 | $1,835.00 | $1,835.00 | $1,835.00 |
| 24 | Edge line, 6", type 1 (642E00104) | MI | 0.01 | $79,900 | $105,100 | $79,900 |
| 25 | Center line, type 1 (642E00300) | MI | 0.01 | $159,800 | $140,135 | $159,800 |
| 26 | Detour signing (614E12420) | LS | 1 | $4,670.00 | $5,500.00 | $4,670.00 |
| 27 | Portions of structure removed (202E11200) | LS | 1 | $1,623.81 | $50,000 | $9,222.91 |
| 28 | Aggregate base (304E20000) | CY | 30 | $493.17 | $160.00 | $4,281.98 |
| 29 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $12,444 | $25,000 | $19,954 |
| 30 | Unclassified excavation (503E21300) | LS | 1 | $11,096 | $4,000.00 | $69,519 |
| 31 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 17 | $45.06 | $15.00 | $29.04 |
| 32 | Class QC1 concrete, abutment (511E45710) | CY | 1 | $2,524.58 | $5,000.00 | $4,024.57 |
| 33 | Concrete repair by epoxy injection (512E10600) | FT | 50 | $185.00 | $100.00 | $208.67 |
| 34 | Patching concrete structure, as per plan (519E11101) | SF | 35 | $250.79 | $350.00 | $537.86 |
| 35 | Riprap, type D, as per plan (601E11001) | SY | 35 | $565.94 | $925.00 | $1,822.20 |
| 36 | Rock channel protection, type B with geotextile fabric, as per plan (601E32105) | CY | 28 | $269.76 | $190.00 | $347.35 |
| 37 | Masonry, misc.:repoint existing stone abutments (602E97000) | SF | 416 | $69.98 | $70.00 | $40.27 |
| 38 | Patching concrete structures with trowelable mortar (843E50000) | SF | 19 | $190.73 | $275.00 | $1,365.75 |
| 39 | Galvanic anode protection, as per plan (844E20001) | EACH | 16 | $67.02 | $60.00 | $820.27 |
| 40 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $10,924 | $25,000 | $5,125.25 |
| 41 | Patching concrete structure, as per plan (519E11101) | SF | 35 | $254.06 | $350.00 | $537.86 |
| 42 | Galvanic anode protection, as per plan (844E20001) | EACH | 12 | $72.69 | $60.00 | $1,008.97 |
| 43 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,631.64 | $8,000.00 | $3,804.47 |
| 44 | Maintaining traffic (614E11000) | LS | 1 | $12,710 | $45,000 | $23,427 |
| 45 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,200.00 | $23,000 | $3,292.24 |
| 46 | Mobilization (624E10000) | LS | 1 | $53,585 | $75,000 | $32,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.