ODOT contract 250363 bid tabulation
PAU-US 127-10.23 (BRIDGE REPAIR). Let by Ohio DOT on July 31, 2025, PAU. 6 bids received; low bid $328,707 by Catts Construction Inc, -32% against the engineer's estimate of $480,000.
- Owner
- Ohio DOT
- Letting
- 31 JUL 2025
- Pay items
- 24
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Catts Construction Inc | $328,707 | Low | -32% |
| 2 | Vernon Nagel Inc | $331,187 | +1.0% | -31% |
| 3 | Ohio Concrete Maintenance LLC | $372,523 | +13% | -22% |
| 4 | Miller Bros Const Inc | $383,021 | +17% | -20% |
| 5 | Eagle Bridge Co | $400,213 | +22% | -17% |
| 6 | Perk Company Inc | $444,091 | +35% | -7.0% |
Engineer's estimate: $480,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Catts Construction Inc | 2. Vernon Nagel Inc | 3. Ohio Concrete Maintenance LLC | 4. Miller Bros Const Inc | 5. Eagle Bridge Co | 6. Perk Company Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,200.00 | $1,000.00 | $2,000.00 | $1,198.35 | $500.00 | $2,000.00 |
| 2 | Walk removed (202E30000) | SF | 333 | $3.25 | $8.00 | $13.00 | $7.92 | $6.00 | $9.70 |
| 3 | 4" concrete walk (608E10000) | SF | 333 | $8.50 | $10.00 | $17.00 | $21.44 | $16.00 | $19.16 |
| 4 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 5 | Partial depth pavement repair (441) (251E01000) | SY | 42 | $91.00 | $500.00 | $170.00 | $153.66 | $415.00 | $150.00 |
| 6 | Pavement repair (253E02000) | CY | 5 | $591.00 | $1,200.00 | $1,000.00 | $1,337.98 | $1,200.00 | $900.00 |
| 7 | Pavement repair (253E02000) | CY | 20 | $591.00 | $525.00 | $900.00 | $842.11 | $525.00 | $400.00 |
| 8 | Non-tracking tack coat (407E20000) | GAL | 20 | $3.00 | $2.75 | $2.50 | $2.11 | $2.75 | $2.00 |
| 9 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 10 | $774.00 | $525.00 | $800.00 | $777.78 | $525.00 | $350.00 |
| 10 | Compacted aggregate (617E10100) | CY | 50 | $58.50 | $100.00 | $50.00 | $64.18 | $150.00 | $71.42 |
| 11 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 516 | $12.00 | $16.00 | $11.00 | $13.96 | $14.00 | $13.39 |
| 12 | Structural joint or joint sealer, misc.: neoprene (516E14600) | FT | 57 | $109.00 | $130.00 | $150.00 | $151.39 | $250.00 | $157.69 |
| 13 | Joint sealer, as per plan (516E31001) | FT | 89 | $29.00 | $25.00 | $25.00 | $30.84 | $22.50 | $25.02 |
| 14 | Patching concrete structure, as per plan (519E11101) | SF | 16 | $250.00 | $130.00 | $200.00 | $374.30 | $400.00 | $443.72 |
| 15 | Patching concrete structures with trowelable mortar (843E50000) | SF | 10 | $240.00 | $130.00 | $200.00 | $366.97 | $325.00 | $460.38 |
| 16 | Latex modified concrete overlay using hydrodemolition (848E10100) | SY | 1,136 | $97.00 | $79.00 | $114.00 | $99.42 | $100.00 | $101.56 |
| 17 | Surface preparation using hydrodemolition, as per plan (848E20001) | SY | 1,136 | $45.00 | $73.00 | $48.00 | $77.86 | $100.00 | $82.33 |
| 18 | Latex modified concrete overlay (variable thickness), material only (848E30100) | CY | 39 | $824.00 | $1,000.00 | $1,100.00 | $1,183.34 | $825.00 | $1,141.56 |
| 19 | Hand chipping (848E50000) | SY | 69 | $202.00 | $105.00 | $140.00 | $156.60 | $100.00 | $150.00 |
| 20 | Test slab (848E50100) | LS | 1 | $650.00 | $8,500.00 | $5,500.00 | $9,726.64 | $3,250.00 | $10,867 |
| 21 | Full-depth repair (848E50200) | CY | 1 | $750.00 | $700.00 | $100.00 | $4,442.89 | $1,500.00 | $3,246.10 |
| 22 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,800.00 | $5,000.00 | $12,000 | $1,883.17 | $8,000.00 | $4,500.00 |
| 23 | Maintaining traffic (614E11000) | LS | 1 | $7,000.00 | $5,000.00 | $10,000 | $8,245.88 | $15,000 | $31,776 |
| 24 | Mobilization (624E10000) | LS | 1 | $52,300 | $16,000 | $33,000 | $19,151 | $17,500 | $61,583 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.