ODOT contract 250359 bid tabulation
JAC-SR 93-04.67 (TWO LANE RESURFACING). Let by Ohio DOT on July 31, 2025, JAC. 3 bids received; low bid $946,580 by Fillmore Construction, -8.5% against the engineer's estimate of $1,034,000.
- Owner
- Ohio DOT
- Letting
- 31 JUL 2025
- Pay items
- 21
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fillmore Construction | $946,580 | Low | -8.0% |
| 2 | Shelly & Sands Inc | $1,018,109 | +8.0% | -2.0% |
| 3 | Shelly Company | $1,152,729 | +22% | +11% |
Engineer's estimate: $1,034,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fillmore Construction | 2. Shelly & Sands Inc | 3. Shelly Company |
|---|---|---|---|---|---|---|
| 1 | Linear grading (209E60500) | MI | 0.78 | $7,000.00 | $10,500 | $3,635.00 |
| 2 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 1,500 | $32.00 | $45.00 | $91.00 |
| 3 | Pavement planing, asphalt concrete 1.25" (254E01000) | SY | 73,000 | $1.00 | $2.15 | $1.90 |
| 4 | Patching planed surface (254E01600) | SY | 14,788 | $3.00 | $3.00 | $3.00 |
| 5 | Non-tracking tack coat (407E20000) | GAL | 6,570 | $3.00 | $3.50 | $4.10 |
| 6 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 2,534 | $215.00 | $210.00 | $228.00 |
| 7 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 6.33 | $1,200.00 | $735.00 | $735.00 |
| 8 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 3.17 | $1,200.00 | $735.00 | $735.00 |
| 9 | Longitudinal joint preparation (874E21000) | MI | 3.12 | $7,000.00 | $1,750.00 | $4,750.00 |
| 10 | RPM (621E00100) | EACH | 294 | $43.00 | $37.50 | $37.50 |
| 11 | Raised pavement marker removed (621E54000) | EACH | 294 | $10.00 | $13.00 | $25.00 |
| 12 | Edge line, 6" (644E00104) | MI | 7.84 | $3,981.00 | $3,825.00 | $3,825.00 |
| 13 | Center line (644E00300) | MI | 3.92 | $5,468.00 | $4,630.00 | $4,630.00 |
| 14 | School symbol marking, 96" (644E01110) | EACH | 2 | $1,120.00 | $920.00 | $920.00 |
| 15 | Work zone marking sign (614E12460) | EACH | 18 | $140.00 | $90.00 | $90.00 |
| 16 | Work zone center line, class III, 642 paint (614E21550) | MI | 7.84 | $1,721.00 | $825.00 | $825.00 |
| 17 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 15.68 | $862.00 | $695.00 | $695.00 |
| 18 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $3,217.14 | $5,000.00 |
| 19 | Maintaining traffic (614E11000) | LS | 1 | $50,000 | $47,250 | $70,000 |
| 20 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,000.00 | $3,000.00 | $1,500.00 |
| 21 | Mobilization (624E10000) | LS | 1 | $20,000 | $36,250 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.