ODOT contract 250362 bid tabulation
MED-IR 271-05.64 (SLIDE REPAIR). Let by Ohio DOT on July 31, 2025, MED. 4 bids received; low bid $448,589 by Great Lakes Construction Co, +10% against the engineer's estimate of $407,000.
- Owner
- Ohio DOT
- Letting
- 31 JUL 2025
- Pay items
- 36
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Great Lakes Construction Co | $448,589 | Low | +10% |
| 2 | Alan Stone Co Inc | $515,639 | +15% | +27% |
| 3 | Ohio-West Virginia Excavating Co | $552,000 | +23% | +36% |
| 4 | Craig Edward Susany Inc | $824,461 | +84% | +103% |
Engineer's estimate: $407,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Great Lakes Construction Co | 2. Alan Stone Co Inc | 3. Ohio-West Virginia Excavating Co | 4. Craig Edward Susany Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,500.00 | $10,000 | $6,000.00 | $1,000.00 |
| 2 | Guardrail removed for reuse (202E38200) | FT | 175 | $10.00 | $10.00 | $11.00 | $10.00 |
| 3 | Embankment (203E20000) | CY | 9.10 | $120.00 | $40.00 | $298.00 | $300.00 |
| 4 | Guardrail rebuilt, type 5 (606E16500) | FT | 175 | $25.00 | $30.00 | $34.00 | $40.00 |
| 5 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,500.00 | $2,700.00 | $2,020.00 | $10,000 |
| 6 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,500.00 | $2,700.00 | $2,020.00 | $1,000.00 |
| 7 | Soil analysis test (659E00100) | EACH | 2 | $50.00 | $180.00 | $200.00 | $25.00 |
| 8 | Topsoil (659E00300) | CY | 12 | $120.00 | $90.00 | $225.00 | $100.00 |
| 9 | Seeding and mulching (659E10000) | SY | 110 | $28.00 | $25.00 | $40.00 | $31.00 |
| 10 | Repair seeding and mulching (659E14000) | SY | 6 | $8.00 | $320.00 | $40.00 | $120.00 |
| 11 | Inter-seeding (659E15000) | SY | 6 | $1.00 | $55.00 | $40.00 | $115.00 |
| 12 | Commercial fertilizer (659E20000) | TON | 0.01 | $1,000.00 | $660.00 | $1,700.00 | $1,200.00 |
| 13 | Lime (659E31000) | ACRE | 0.02 | $100.00 | $940.00 | $202.00 | $600.00 |
| 14 | Water (659E35000) | MGAL | 0.61 | $50.00 | $1.00 | $1.00 | $1.00 |
| 15 | Erosion control (832E30000) | EACH | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | Barrier reflector, type 2 (1WAY) (626E00110) | EACH | 4 | $15.00 | $15.00 | $15.00 | $20.00 |
| 17 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $47.00 | $150.00 | $175.00 | $200.00 |
| 18 | Removal of ground mounted post support and reerection (630E86010) | EACH | 1 | $48.00 | $320.00 | $370.00 | $400.00 |
| 19 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $100.00 | $100.00 | $200.00 | $100.00 |
| 20 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 1 | $2,100.00 | $2,400.00 | $2,727.00 | $3,000.00 |
| 21 | Work zone increased penalties sign (614E12484) | EACH | 4 | $150.00 | $290.00 | $336.00 | $300.00 |
| 22 | Barrier reflector, type 2 (1WAY) (614E13312) | EACH | 6 | $7.95 | $15.00 | $16.00 | $20.00 |
| 23 | Object marker, one way (614E13350) | EACH | 6 | $13.00 | $25.00 | $26.00 | $20.00 |
| 24 | Portable changeable message sign (614E18600) | SNMT | 4 | $750.00 | $1,200.00 | $1,500.00 | $1,200.00 |
| 25 | Portable barrier, unanchored (622E41100) | FT | 260 | $35.00 | $40.00 | $81.00 | $100.00 |
| 26 | Steel piles, misc.: W16X57 furnished (507E00400) | FT | 1,513 | $75.00 | $55.00 | $68.00 | $112.00 |
| 27 | Concrete, misc.: precast concrete lagging panel (511E81300) | EACH | 1 | $3,000.00 | $3,100.00 | $7,128.00 | $3,000.00 |
| 28 | Drilled shafts, 24" diameter, above bedrock, as per plan (524E94503) | FT | 1,074.60 | $95.00 | $90.00 | $97.00 | $289.00 |
| 29 | Drilled shafts, 24" diameter, into bedrock, as per plan (524E94505) | FT | 455.40 | $95.00 | $150.00 | $92.00 | $289.00 |
| 30 | Drilled shafts, misc.: plug pile, 24" diameter unr (524E95000) | FT | 576 | $100.00 | $90.00 | $97.00 | $90.00 |
| 31 | Special - inclinometer (690E98000) | EACH | 1 | $2,750.00 | $2,200.00 | $10,000 | $5,000.00 |
| 32 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,000.00 | $6,000.00 | $8,000.00 | $25,000 |
| 33 | Maintaining traffic (614E11000) | LS | 1 | $39,000 | $65,000 | $41,117 | $10,000 |
| 34 | Field office, type C (619E16020) | MNTH | 3 | $4,000.00 | $3,000.00 | $6,500.00 | $4,000.00 |
| 35 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,000.00 | $7,000.00 | $2,500.00 | $10,000 |
| 36 | Mobilization (624E10000) | LS | 1 | $22,400 | $64,000 | $79,750 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.