ODOT contract 250358 bid tabulation
HAS-SR 149-01.17 (CULVERT REPLACEMENT). Let by Ohio DOT on July 31, 2025, HAS. 5 bids received; low bid $711,194 by Tucson Inc, -12% against the engineer's estimate of $810,000.
- Owner
- Ohio DOT
- Letting
- 31 JUL 2025
- Pay items
- 76
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Tucson Inc | $711,194 | Low | -12% |
| 2 | Advanced Excavating & Demolition LLC | $712,356 | 0.0% | -12% |
| 3 | Eclipse Co LLC | $1,001,321 | +41% | +24% |
| 4 | Ohio-West Virginia Excavating Co | $1,047,010 | +47% | +29% |
| 5 | Shelly & Sands Inc | $1,161,995 | +63% | +43% |
Engineer's estimate: $810,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Tucson Inc | 2. Advanced Excavating & Demolition LLC | 3. Eclipse Co LLC | 4. Ohio-West Virginia Excavating Co | 5. Shelly & Sands Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,775.00 | $10,000 | $10,000 | $8,000.00 | $11,000 |
| 2 | Pavement removed (202E23000) | SY | 275 | $14.75 | $26.00 | $71.50 | $22.00 | $45.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 217 | $6.25 | $13.00 | $16.00 | $15.00 | $15.00 |
| 4 | Guardrail removed (202E38000) | FT | 300 | $2.60 | $2.40 | $2.50 | $10.00 | $2.50 |
| 5 | Catch basin removed (202E58100) | EACH | 1 | $450.00 | $450.00 | $462.50 | $2,000.00 | $250.00 |
| 6 | Regulated underground storage tank removed (202E67000) | EACH | 1 | $2,750.00 | $23,500 | $13,356 | $35,000 | $13,000 |
| 7 | Fence removed (202E75000) | FT | 201 | $1.85 | $8.50 | $2.50 | $5.00 | $8.50 |
| 8 | Removal misc.: septic tank removed or abandoned (202E98000) | LS | 1 | $1,580.00 | $1,500.00 | $2,977.00 | $8,000.00 | $2,500.00 |
| 9 | Excavation (203E10000) | CY | 455 | $43.00 | $21.00 | $33.00 | $40.00 | $60.00 |
| 10 | Embankment (203E20000) | CY | 229 | $40.00 | $26.50 | $52.50 | $65.00 | $30.00 |
| 11 | Subgrade compaction (204E10000) | SY | 643 | $2.25 | $1.50 | $1.00 | $3.00 | $20.00 |
| 12 | Guardrail, type MGS (606E15050) | FT | 50 | $42.50 | $40.00 | $44.50 | $35.00 | $39.20 |
| 13 | Guardrail, type MGS, long-span (606E17360) | FT | 43.75 | $48.50 | $45.00 | $47.00 | $35.00 | $44.80 |
| 14 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 2 | $3,154.00 | $2,950.00 | $2,490.00 | $1,800.00 | $2,920.00 |
| 15 | Rock channel protection, type B with aggregate filter (601E32110) | CY | 79 | $124.00 | $85.00 | $180.00 | $105.00 | $150.00 |
| 16 | Soil analysis test (659E00100) | EACH | 2 | $75.00 | $75.00 | $125.00 | $175.00 | $150.00 |
| 17 | Topsoil (659E00300) | CY | 250 | $57.00 | $40.00 | $68.00 | $100.00 | $50.00 |
| 18 | Seeding and mulching (659E10000) | SY | 2,249 | $3.00 | $2.50 | $1.50 | $1.50 | $1.50 |
| 19 | Repair seeding and mulching (659E14000) | SY | 112 | $0.75 | $1.50 | $2.00 | $1.50 | $1.50 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.30 | $2,640.00 | $590.00 | $891.50 | $1,500.00 | $1,250.00 |
| 21 | Lime (659E31000) | ACRE | 0.46 | $690.00 | $50.00 | $155.50 | $175.00 | $150.00 |
| 22 | Water (659E35000) | MGAL | 12 | $10.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 93 | $7.75 | $7.50 | $15.00 | $7.00 | $6.00 |
| 25 | Concrete masonry (602E20000) | CY | 0.20 | $5,225.00 | $7,000.00 | $3,680.00 | $10,500 | $6,000.00 |
| 26 | Aggregate drains (605E31100) | FT | 62 | $24.25 | $33.50 | $24.00 | $90.00 | $25.00 |
| 27 | 12" conduit, type C (611E04600) | FT | 199 | $88.00 | $78.00 | $129.00 | $130.00 | $130.00 |
| 28 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $2,925.00 | $2,600.00 | $4,484.00 | $5,500.00 | $4,000.00 |
| 29 | Catch basin, no. 2-2C (611E98504) | EACH | 1 | $3,200.00 | $2,300.00 | $4,438.50 | $6,500.00 | $5,000.00 |
| 30 | Pavement planing, asphalt concrete (3") (254E01000) | SY | 578 | $5.70 | $15.00 | $33.00 | $10.00 | $20.00 |
| 31 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 104 | $435.00 | $375.00 | $356.00 | $310.00 | $340.00 |
| 32 | Aggregate base (304E20000) | CY | 172 | $121.00 | $90.00 | $115.50 | $175.00 | $175.00 |
| 33 | Tack coat (407E10000) | GAL | 124 | $4.35 | $3.50 | $4.00 | $12.00 | $3.30 |
| 34 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 37 | $435.00 | $525.00 | $522.00 | $460.00 | $425.00 |
| 35 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 49 | $380.00 | $425.00 | $374.00 | $380.00 | $375.00 |
| 36 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 2 | $1,625.00 | $1,000.00 | $522.00 | $2,000.00 | $1,875.00 |
| 37 | RPM (621E00100) | EACH | 8 | $341.00 | $315.00 | $315.00 | $370.00 | $315.00 |
| 38 | Raised pavement marker removed (621E54000) | EACH | 8 | $9.00 | $50.00 | $26.50 | $20.00 | $35.00 |
| 39 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 5 | $27.05 | $13.00 | $12.00 | $12.00 | $13.00 |
| 40 | Ground mounted support, no. 2 post (630E02100) | FT | 59.60 | $16.25 | $15.00 | $12.00 | $9.00 | $15.00 |
| 41 | Ground mounted support, no. 3 post (630E03100) | FT | 51.80 | $21.65 | $20.00 | $13.00 | $9.00 | $20.00 |
| 42 | Sign post reflector (630E08600) | EACH | 8 | $50.00 | $45.00 | $30.00 | $100.00 | $45.00 |
| 43 | Sign, flat sheet (630E80100) | SF | 18 | $27.25 | $25.00 | $25.00 | $35.00 | $25.00 |
| 44 | Removal of ground mounted sign and reerection (630E85100) | EACH | 7 | $54.25 | $50.00 | $50.00 | $100.00 | $50.00 |
| 45 | Removal of ground mounted post support and disposal (630E86002) | EACH | 5 | $22.00 | $20.00 | $10.00 | $30.00 | $20.00 |
| 46 | Edge line, 6" (646E10010) | MI | 0.10 | $21,600 | $19,990 | $19,990 | $23,000 | $19,900 |
| 47 | Center line (646E10200) | MI | 0.05 | $32,425 | $30,000 | $30,000 | $35,000 | $30,000 |
| 48 | Detour signing (614E12420) | LS | 1 | $6,000.00 | $5,500.00 | $5,500.00 | $15,000 | $5,500.00 |
| 49 | Asphalt concrete for maintaining traffic (614E13000) | CY | 98 | $190.00 | $200.00 | $250.00 | $300.00 | $500.00 |
| 50 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.05 | $9,775.00 | $9,050.00 | $28,995 | $11,000 | $9,050.00 |
| 51 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.10 | $4,925.00 | $4,550.00 | $14,578 | $5,000.00 | $4,550.00 |
| 52 | Water (616E10000) | MGAL | 10 | $1.00 | $1.00 | $97.00 | $1.00 | $50.00 |
| 53 | Removal misc.: oepa notification of demolition (202E98100) | EACH | 1 | $2,345.00 | $500.00 | $668.00 | $12,000 | $1,500.00 |
| 54 | Special - work involving non-regulated materials (690E65000) | TON | 68 | $81.25 | $40.00 | $120.00 | $175.00 | $55.00 |
| 55 | Special - work involving petroleum contaminated soil (690E65016) | TON | 68 | $162.25 | $80.00 | $153.50 | $340.00 | $160.00 |
| 56 | Special - work involving non-regulated water (690E65022) | GAL | 2,272 | $1.65 | $1.50 | $46.50 | $12.00 | $4.50 |
| 57 | Special - work involving regulated water (690E65024) | GAL | 2,272 | $3.25 | $2.50 | $6.50 | $15.00 | $6.50 |
| 58 | Pipe removed, over 24" diameter (202E35200) | FT | 50 | $72.00 | $125.00 | $146.00 | $265.00 | $250.00 |
| 59 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $13,000 | $15,000 | $34,000 | $30,000 | $35,000 |
| 60 | Unclassified excavation, including rock (503E21104) | CY | 194 | $40.50 | $60.00 | $159.50 | $85.00 | $180.00 |
| 61 | Epoxy coated steel reinforcement (509E10000) | LB | 6,605 | $2.25 | $2.85 | $3.50 | $2.00 | $5.00 |
| 62 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 15 | $2,100.00 | $955.00 | $2,611.00 | $2,500.00 | $5,200.00 |
| 63 | Class QC1 concrete, footing (511E46510) | CY | 43 | $803.00 | $600.00 | $1,025.50 | $850.00 | $1,800.00 |
| 64 | Class QC1 concrete, headwall (511E46610) | CY | 2 | $4,025.00 | $1,500.00 | $2,458.50 | $2,000.00 | $5,000.00 |
| 65 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 80 | $29.00 | $40.00 | $161.00 | $50.00 | $38.00 |
| 66 | Type 2 waterproofing (512E33000) | SY | 151 | $39.00 | $36.00 | $35.00 | $35.00 | $27.00 |
| 67 | Type 3 waterproofing (512E33010) | SY | 148 | $46.00 | $51.00 | $56.50 | $60.00 | $45.00 |
| 68 | 1" preformed expansion joint filler (516E13600) | SF | 38 | $18.50 | $18.00 | $6.50 | $15.00 | $10.00 |
| 69 | Porous backfill with geotextile fabric (518E21200) | CY | 17 | $198.00 | $150.00 | $183.50 | $415.00 | $225.00 |
| 70 | 12' X 6' conduit, type A, 706.05, as per plan (611E95801) | FT | 85 | $1,700.00 | $1,525.00 | $1,717.00 | $2,100.00 | $2,200.00 |
| 71 | Low strength mortar backfill (613E41200) | CY | 302 | $206.00 | $165.00 | $248.50 | $250.00 | $335.00 |
| 72 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,850 | $14,000 | $15,000 | $20,000 | $7,400.24 |
| 73 | Maintaining traffic (614E11000) | LS | 1 | $11,650 | $35,000 | $23,206 | $10,000 | $40,300 |
| 74 | Field office, type B (619E16010) | MNTH | 6 | $1,955.00 | $1,500.00 | $868.00 | $2,500.00 | $5,500.00 |
| 75 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,650.00 | $17,000 | $7,974.00 | $15,000 | $15,000 |
| 76 | Mobilization (624E10000) | LS | 1 | $27,500 | $50,000 | $41,796 | $75,000 | $75,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.