ODOT contract 250360 bid tabulation

LAW-SR 522-00.00 (CHIP SEAL). Let by Ohio DOT on July 31, 2025, LAW. 2 bids received; low bid $656,919 by Shelly Company, -3.7% against the engineer's estimate of $682,000.

Owner
Ohio DOT
Letting
31 JUL 2025
Pay items
23
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly Company$656,919Low-4.0%
2Strawser Construction Inc$867,958+32%+27%
ODOT contract 250360: bids by rank

Engineer's estimate: $682,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly Company2. Strawser Construction Inc
1Linear grading (209E60500)MI1.66$3,400.00$3,600.00
2Compacted aggregate (617E10100)CY162$160.00$170.00
3Partial depth pavement repair (441), as per plan (251E01001)SY1,000$60.50$80.00
4Aggregate, single chip seal, type A (422E11000)SY127,186$1.03$1.45
5Emulsion, chip seal (422E25000)GAL47,059$3.00$3.50
6Fog seal (886E11000)GAL19,078$3.10$4.00
7RPM (621E00100)EACH756$36.50$40.00
8Raised pavement marker removed (621E54000)EACH740$15.25$30.00
9Edge line, 6", type 1 (642E00104)MI16.54$745.00$45.00
10Center line, type 1 (642E00300)MI8.27$1,232.00$1,300.00
11Stop line, type 1 (642E00500)FT19$8.50$9.00
12Edge line, 6" (646E10010)MI0.04$38,910$38,910
13Center line (646E10200)MI0.02$59,650$59,650
14Work zone marking sign (614E12460)EACH31$88.00$148.00
15Work zone center line, class III, 642 paint (614E21550)MI16.54$865.00$915.00
16Work zone edge line, class III, 6", 642 paint (614E22360)MI33.08$580.00$615.00
17Work zone stop line, class III, 642 paint (614E26610)FT19$5.00$5.25
18Premium for contract performance bond and for payment bond (103E05000)LS1$3,500.00$6,500.00
19Maintaining traffic (614E11000)LS1$72,000$82,400
20Construction layout stakes and surveying (623E10000)LS1$2,500.00$2,000.00
21Mobilization (624E10000)LS1$23,000$97,285
100Removal of pavement marking (644E30000)FT19$15.00$16.00
101Removal of pavement marking (644E30030)MI24.81$1,275.00$1,350.00
ODOT contract 250360: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy