ODOT contract 250360 bid tabulation
LAW-SR 522-00.00 (CHIP SEAL). Let by Ohio DOT on July 31, 2025, LAW. 2 bids received; low bid $656,919 by Shelly Company, -3.7% against the engineer's estimate of $682,000.
- Owner
- Ohio DOT
- Letting
- 31 JUL 2025
- Pay items
- 23
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $656,919 | Low | -4.0% |
| 2 | Strawser Construction Inc | $867,958 | +32% | +27% |
Engineer's estimate: $682,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Strawser Construction Inc |
|---|---|---|---|---|---|
| 1 | Linear grading (209E60500) | MI | 1.66 | $3,400.00 | $3,600.00 |
| 2 | Compacted aggregate (617E10100) | CY | 162 | $160.00 | $170.00 |
| 3 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 1,000 | $60.50 | $80.00 |
| 4 | Aggregate, single chip seal, type A (422E11000) | SY | 127,186 | $1.03 | $1.45 |
| 5 | Emulsion, chip seal (422E25000) | GAL | 47,059 | $3.00 | $3.50 |
| 6 | Fog seal (886E11000) | GAL | 19,078 | $3.10 | $4.00 |
| 7 | RPM (621E00100) | EACH | 756 | $36.50 | $40.00 |
| 8 | Raised pavement marker removed (621E54000) | EACH | 740 | $15.25 | $30.00 |
| 9 | Edge line, 6", type 1 (642E00104) | MI | 16.54 | $745.00 | $45.00 |
| 10 | Center line, type 1 (642E00300) | MI | 8.27 | $1,232.00 | $1,300.00 |
| 11 | Stop line, type 1 (642E00500) | FT | 19 | $8.50 | $9.00 |
| 12 | Edge line, 6" (646E10010) | MI | 0.04 | $38,910 | $38,910 |
| 13 | Center line (646E10200) | MI | 0.02 | $59,650 | $59,650 |
| 14 | Work zone marking sign (614E12460) | EACH | 31 | $88.00 | $148.00 |
| 15 | Work zone center line, class III, 642 paint (614E21550) | MI | 16.54 | $865.00 | $915.00 |
| 16 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 33.08 | $580.00 | $615.00 |
| 17 | Work zone stop line, class III, 642 paint (614E26610) | FT | 19 | $5.00 | $5.25 |
| 18 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,500.00 | $6,500.00 |
| 19 | Maintaining traffic (614E11000) | LS | 1 | $72,000 | $82,400 |
| 20 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,500.00 | $2,000.00 |
| 21 | Mobilization (624E10000) | LS | 1 | $23,000 | $97,285 |
| 100 | Removal of pavement marking (644E30000) | FT | 19 | $15.00 | $16.00 |
| 101 | Removal of pavement marking (644E30030) | MI | 24.81 | $1,275.00 | $1,350.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.