ODOT contract 250365 bid tabulation
TUS-IR 77-01.21 (CULVERT REPLACEMENT). Let by Ohio DOT on July 31, 2025, TUS. 4 bids received; low bid $298,236 by Geotech Services Inc, -12% against the engineer's estimate of $339,000.
- Owner
- Ohio DOT
- Letting
- 31 JUL 2025
- Pay items
- 27
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Geotech Services Inc | $298,236 | Low | -12% |
| 2 | Eclipse Co LLC | $395,573 | +33% | +17% |
| 3 | Stanley Miller Construction Company | $448,559 | +50% | +32% |
| 4 | Proshot Concrete Inc | $691,116 | +132% | +104% |
Engineer's estimate: $339,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Geotech Services Inc | 2. Eclipse Co LLC | 3. Stanley Miller Construction Company | 4. Proshot Concrete Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $28,000 | $16,806 | $80,000 | $50,000 |
| 2 | Special - pipe cleanout over 48" (202E70130) | FT | 398 | $12.00 | $76.50 | $60.00 | $25.00 |
| 3 | Fence removed (202E75000) | FT | 36 | $56.00 | $11.00 | $15.00 | $14.85 |
| 4 | Fence, type 47 (607E15000) | FT | 36 | $87.00 | $124.00 | $140.00 | $167.50 |
| 5 | Riprap, type D (601E11000) | SY | 14 | $825.00 | $410.00 | $1,000.00 | $2,200.00 |
| 6 | Rock channel protection, type A with aggregate filter (601E32010) | CY | 83 | $250.00 | $183.50 | $260.00 | $800.00 |
| 7 | Soil analysis test (659E00100) | EACH | 2 | $75.00 | $125.00 | $150.00 | $1,500.00 |
| 8 | Topsoil (659E00300) | CY | 597 | $55.00 | $94.00 | $90.00 | $30.00 |
| 9 | Seeding and mulching (659E10000) | SY | 5,376 | $2.88 | $0.80 | $3.10 | $4.00 |
| 10 | Repair seeding and mulching (659E14000) | SY | 269 | $0.84 | $0.80 | $1.00 | $1.22 |
| 11 | Inter-seeding (659E15000) | SY | 269 | $0.15 | $1.00 | $1.00 | $0.15 |
| 12 | Commercial fertilizer (659E20000) | TON | 0.75 | $476.00 | $891.51 | $800.00 | $607.51 |
| 13 | Lime (659E31000) | ACRE | 1.11 | $1.17 | $155.50 | $50.00 | $40.50 |
| 14 | Water (659E35000) | MGAL | 30 | $0.32 | $1.00 | $1.00 | $0.95 |
| 15 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | Special - work zone guardrail (614E12200) | FT | 50 | $75.00 | $92.00 | $125.00 | $125.00 |
| 17 | Removal misc.: oepa notification of demolition (202E98000) | LS | 1 | $5,000.00 | $680.00 | $2,000.00 | $1,000.00 |
| 18 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $2,000.00 | $104,459 | $15,000 | $25,000 |
| 19 | Unclassified excavation (503E21300) | LS | 1 | $11,000 | $1,709.00 | $10,000 | $10,000 |
| 20 | Patching concrete structure, as per plan (519E11101) | SF | 28 | $150.00 | $254.00 | $350.00 | $500.00 |
| 21 | Field paving of existing pipe, as per plan (144" C (611E96551) | FT | 398 | $205.00 | $205.00 | $225.00 | $880.00 |
| 22 | Conduit, misc.: weep holes (611E97200) | EACH | 10 | $237.00 | $229.50 | $300.00 | $200.00 |
| 23 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,500.00 | $5,696.00 | $10,000 | $9,400.00 |
| 24 | Maintaining traffic (614E11000) | LS | 1 | $20,000 | $7,741.50 | $8,000.00 | $25,000 |
| 25 | Field office, type A (619E16000) | MNTH | 4 | $2,500.00 | $850.00 | $1,000.00 | $2,800.00 |
| 26 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,500.00 | $3,514.00 | $14,000 | $5,000.00 |
| 27 | Mobilization (624E10000) | LS | 1 | $22,000 | $27,670 | $50,000 | $15,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way