ODOT contract 250094 bid tabulation
LIC-CR 327-00.00 (BIKEWAYS). Let by Ohio DOT on February 13, 2025, LIC. 8 bids received; low bid $938,829 by Law General Contracting Inc, -23% against the engineer's estimate of $1,216,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 57
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Law General Contracting Inc | $938,829 | Low | -23% |
| 2 | Layton Services | $961,702 | +2.0% | -21% |
| 3 | Boss Excavating & Grading Inc | $1,085,185 | +16% | -11% |
| 4 | Strawser Paving Co Inc | $1,096,723 | +17% | -10% |
| 5 | Park Enterprise Construction Co Inc | $1,117,135 | +19% | -8.0% |
| 6 | Axis Civil Construction LLC | $1,251,693 | +33% | +3.0% |
| 7 | Double Z Construction Company | $1,312,936 | +40% | +8.0% |
| 8 | Eclipse Co LLC | $1,427,647 | +52% | +17% |
Engineer's estimate: $1,216,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Law General Contracting Inc | 2. Layton Services | 3. Boss Excavating & Grading Inc | 4. Strawser Paving Co Inc | 5. Park Enterprise Construction Co Inc | 6. Axis Civil Construction LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $18,000 | $4,000.00 | $43,600 | $3,000.00 | $30,000 | $20,000 |
| 2 | Excavation (203E10000) | CY | 6,830 | $17.00 | $17.00 | $26.65 | $31.12 | $31.53 | $28.00 |
| 3 | Embankment (203E20000) | CY | 1,088 | $22.00 | $5.00 | $22.00 | $26.89 | $35.00 | $28.00 |
| 4 | Subgrade compaction (204E10000) | SY | 10,176 | $0.75 | $1.00 | $2.00 | $1.00 | $1.00 | $1.50 |
| 5 | Granular material, type C (204E30020) | CY | 3,508 | $55.50 | $86.00 | $55.00 | $72.75 | $65.00 | $90.00 |
| 6 | Proof rolling (204E45000) | HR | 6 | $158.72 | $240.00 | $720.00 | $148.32 | $250.00 | $200.00 |
| 7 | Geogrid (204E51000) | SY | 8,095 | $1.37 | $2.75 | $4.00 | $4.00 | $1.50 | $1.50 |
| 8 | 4" concrete walk (608E10000) | SF | 109 | $25.00 | $13.75 | $27.00 | $20.08 | $43.00 | $15.00 |
| 9 | Curb ramp (608E52000) | SF | 93 | $35.53 | $13.50 | $34.00 | $25.00 | $50.00 | $35.00 |
| 10 | Detectable warning (608E53020) | SF | 66 | $33.16 | $30.00 | $38.00 | $16.30 | $50.00 | $54.00 |
| 11 | Rock channel protection, type C with filter (601E32200) | CY | 8 | $156.39 | $170.00 | $345.00 | $200.00 | $130.00 | $125.00 |
| 12 | Soil analysis test (659E00100) | EACH | 1 | $148.15 | $150.00 | $170.00 | $150.00 | $150.00 | $150.00 |
| 13 | Topsoil (659E00300) | CY | 815 | $36.00 | $12.00 | $70.00 | $50.00 | $4.00 | $34.00 |
| 14 | Seeding and mulching, class 1 (659E00500) | SY | 7,340 | $1.14 | $1.00 | $3.00 | $1.00 | $1.20 | $1.00 |
| 15 | Repair seeding and mulching (659E14000) | SY | 367 | $0.95 | $1.00 | $3.00 | $1.00 | $1.00 | $1.00 |
| 16 | Inter-seeding (659E15000) | SY | 367 | $0.95 | $1.00 | $3.00 | $1.00 | $1.00 | $1.00 |
| 17 | Commercial fertilizer (659E20000) | TON | 1.02 | $1,056.45 | $1,250.00 | $1,755.00 | $1,250.00 | $1,000.00 | $1,250.00 |
| 18 | Lime (659E31000) | ACRE | 1.52 | $184.30 | $150.00 | $11.45 | $150.00 | $200.00 | $150.00 |
| 19 | Water (659E35000) | MGAL | 42 | $1.19 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 20 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,457.74 | $2,100.00 | $1,350.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 21 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $4,145.59 | $5,100.00 | $2,700.00 | $8,450.00 | $8,750.00 | $8,100.00 |
| 22 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $2,368.91 | $1,850.00 | $2,265.00 | $1,361.53 | $2,250.00 | $2,130.00 |
| 23 | Erosion control (832E30000) | EACH | 3,315 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Pipe removed, 24" and under (202E35100) | FT | 333 | $11.91 | $10.00 | $18.00 | $7.47 | $3.00 | $23.00 |
| 25 | Pipe removed, over 24" diameter (202E35200) | FT | 91 | $20.87 | $20.00 | $20.00 | $10.07 | $5.00 | $18.00 |
| 26 | 4" conduit, type E (611E00400) | FT | 50 | $15.00 | $10.00 | $37.50 | $7.00 | $20.00 | $39.00 |
| 27 | 6" conduit, type E (611E01400) | FT | 50 | $16.00 | $15.00 | $38.00 | $8.00 | $25.00 | $40.00 |
| 28 | 8" conduit, type E (611E02500) | FT | 50 | $20.00 | $20.00 | $54.00 | $10.00 | $30.00 | $43.00 |
| 29 | 12" conduit, type D (611E04900) | FT | 222 | $55.97 | $33.00 | $58.00 | $63.28 | $40.00 | $47.00 |
| 30 | 18" conduit, type D (611E07900) | FT | 111 | $60.00 | $43.00 | $74.00 | $74.71 | $60.00 | $63.00 |
| 31 | 24" conduit, type D (611E10900) | FT | 91 | $120.12 | $59.00 | $110.00 | $93.42 | $70.00 | $81.00 |
| 32 | Manhole adjusted to grade (611E99654) | EACH | 3 | $465.64 | $800.00 | $378.00 | $350.00 | $500.00 | $950.00 |
| 33 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 99 | $230.00 | $208.00 | $266.00 | $251.63 | $275.00 | $300.00 |
| 34 | Aggregate base (304E20000) | CY | 1,516 | $67.00 | $83.00 | $59.00 | $98.00 | $90.00 | $109.00 |
| 35 | Non-tracking tack coat (407E20000) | GAL | 477 | $5.75 | $4.00 | $4.50 | $4.00 | $5.00 | $3.50 |
| 36 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 48 | $300.00 | $329.00 | $305.00 | $357.36 | $395.00 | $335.00 |
| 37 | Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700) | CY | 44 | $280.00 | $301.00 | $289.00 | $331.00 | $386.00 | $325.00 |
| 38 | Curb, type 6 (609E26000) | FT | 20 | $88.83 | $50.00 | $74.00 | $57.24 | $66.00 | $84.00 |
| 39 | Asphalt concrete surface course, type 1, (448) (823E10000) | CY | 247 | $300.00 | $256.00 | $282.00 | $283.38 | $317.00 | $315.00 |
| 40 | Asphalt concrete intermediate course, type 2, (448) (823E20000) | CY | 344 | $220.00 | $237.00 | $262.50 | $264.66 | $293.00 | $305.00 |
| 41 | Ground mounted support, no. 2 post (630E02100) | FT | 198.50 | $11.43 | $16.00 | $18.00 | $15.66 | $16.00 | $15.00 |
| 42 | Ground mounted support, no. 3 post (630E03100) | FT | 96.40 | $13.80 | $17.75 | $20.00 | $17.64 | $18.00 | $18.00 |
| 43 | Sign, flat sheet (630E80100) | SF | 89.50 | $35.65 | $20.50 | $23.00 | $20.58 | $21.00 | $25.00 |
| 44 | Removal of ground mounted sign and disposal (630E84900) | EACH | 8 | $44.42 | $73.25 | $18.00 | $16.10 | $16.00 | $150.00 |
| 45 | Removal of ground mounted post support and disposal (630E86002) | EACH | 6 | $59.53 | $48.75 | $24.00 | $21.46 | $21.00 | $25.00 |
| 46 | Signing, misc.: solar-powered rectangular rapid FL (630E97700) | EACH | 4 | $9,000.00 | $6,700.00 | $7,600.00 | $6,700.00 | $7,000.00 | $10,000 |
| 47 | Channelizing line, 8" (644E00400) | FT | 28 | $2.90 | $2.45 | $3.50 | $3.04 | $6.00 | $2.45 |
| 48 | Stop line (644E00500) | FT | 15 | $11.79 | $9.95 | $11.00 | $12.35 | $10.00 | $9.95 |
| 49 | Crosswalk line, 12" (644E00620) | FT | 457 | $4.32 | $3.65 | $5.00 | $4.53 | $10.00 | $3.65 |
| 50 | Crosswalk line, 24" (644E00630) | FT | 220 | $8.88 | $7.50 | $10.50 | $9.31 | $10.00 | $7.50 |
| 51 | Lane arrow (644E01300) | EACH | 4 | $118.45 | $100.00 | $140.00 | $124.14 | $200.00 | $100.00 |
| 52 | Portable changeable message sign, as per plan (614E18601) | SNMT | 14 | $1,125.23 | $900.00 | $1,000.00 | $900.00 | $900.00 | $1,500.00 |
| 53 | Water (616E10000) | MGAL | 5 | $118.45 | $250.00 | $108.00 | $10.00 | $1.00 | $1.00 |
| 54 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $14,500 | $15,000 | $16,000 | $6,351.56 | $11,000 | $7,500.00 |
| 55 | Maintaining traffic (614E11000) | LS | 1 | $2,500.00 | $10,000 | $5,400.00 | $5,000.00 | $12,000 | $25,000 |
| 56 | Construction layout stakes and surveying (623E10000) | LS | 1 | $13,000 | $15,000 | $12,850 | $6,500.00 | $7,500.00 | $12,500 |
| 57 | Mobilization (624E10000) | LS | 1 | $65,000 | $20,000 | $35,650 | $5,000.00 | $40,000 | $30,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.