ODOT contract 250237 bid tabulation
DEL-SR 315 Drainage Improvements (CULVERT REPLACEMENT). Let by Ohio DOT on April 24, 2025, DEL. 5 bids received; low bid $235,828 by Layton Services, +11% against the engineer's estimate of $213,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 52
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Layton Services | $235,828 | Low | +11% |
| 2 | Strawser Paving Co Inc | $242,542 | +3.0% | +14% |
| 3 | Rietschlin Construction Inc | $256,443 | +9.0% | +20% |
| 4 | Danbert Incorporated | $263,388 | +12% | +24% |
| 5 | Eclipse Co LLC | $292,065 | +24% | +37% |
Engineer's estimate: $213,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Layton Services | 2. Strawser Paving Co Inc | 3. Rietschlin Construction Inc | 4. Danbert Incorporated | 5. Eclipse Co LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,648 | $1,500.00 | $10,000 | $3,500.00 | $3,522.75 |
| 2 | Pavement removed (202E23000) | SY | 52 | $35.00 | $45.00 | $40.00 | $31.00 | $31.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 115 | $30.00 | $10.00 | $36.00 | $31.00 | $31.50 |
| 4 | Fence removed (202E75000) | FT | 45 | $20.00 | $10.00 | $18.00 | $19.00 | $15.00 |
| 5 | Excavation (203E10000) | CY | 162 | $55.00 | $58.00 | $40.00 | $63.00 | $63.00 |
| 6 | Embankment (203E20000) | CY | 57 | $45.00 | $90.00 | $40.00 | $51.00 | $64.50 |
| 7 | Fence, misc.:temporary orange construction fence ( (607E98000) | FT | 85 | $15.00 | $25.00 | $19.00 | $11.00 | $19.00 |
| 8 | Special - mailbox removed and reset (690E50350) | EACH | 2 | $500.00 | $260.00 | $594.00 | $555.00 | $175.50 |
| 9 | Riprap, type D, as per plan (601E11001) | SY | 5 | $855.00 | $750.00 | $520.00 | $607.00 | $976.75 |
| 10 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 25.50 | $180.00 | $150.00 | $140.00 | $175.00 | $99.00 |
| 11 | Rock channel protection, type C with filter (601E32200) | CY | 4 | $530.00 | $750.00 | $690.00 | $476.00 | $374.25 |
| 12 | Seeding and mulching, as per plan (659E10001) | SY | 708 | $5.00 | $4.80 | $10.00 | $3.00 | $5.00 |
| 13 | Commercial fertilizer (659E20000) | TON | 0.10 | $1,250.00 | $1,250.00 | $1,300.00 | $500.00 | $1,500.00 |
| 14 | Lime (659E31000) | ACRE | 0.20 | $150.00 | $150.00 | $165.00 | $500.00 | $200.00 |
| 15 | Water (659E35000) | MGAL | 4 | $1.00 | $1.00 | $20.00 | $250.00 | $5.00 |
| 16 | Ditch erosion protection, as per plan (670E00701) | SY | 198 | $2.50 | $3.00 | $5.00 | $3.00 | $5.00 |
| 17 | Erosion control, as per plan (832E30001) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | Concrete masonry (602E20000) | CY | 1.40 | $3,000.00 | $3,300.00 | $2,000.00 | $3,888.00 | $2,408.75 |
| 19 | 6" unclassified pipe underdrains (605E13300) | FT | 40 | $40.00 | $90.00 | $29.00 | $77.00 | $30.75 |
| 20 | Aggregate drains (605E31100) | FT | 90 | $20.00 | $50.00 | $16.00 | $43.00 | $25.00 |
| 21 | 6" conduit, type B (611E00900) | FT | 50 | $30.00 | $40.00 | $39.00 | $30.00 | $56.50 |
| 22 | 6" conduit, type E (611E01400) | FT | 50 | $20.00 | $40.00 | $27.00 | $47.00 | $42.50 |
| 23 | 6" conduit, type F (611E01500) | FT | 65 | $20.00 | $40.00 | $24.00 | $44.00 | $42.50 |
| 24 | 15" conduit, type D (611E06400) | FT | 117 | $110.00 | $90.00 | $105.00 | $133.00 | $151.75 |
| 25 | 18" conduit, type C (611E07600) | FT | 195 | $140.00 | $110.00 | $125.00 | $127.00 | $177.00 |
| 26 | 36" conduit, type B (611E16400) | FT | 54 | $350.00 | $275.00 | $390.00 | $228.00 | $371.25 |
| 27 | 36" conduit, type C (611E16600) | FT | 16 | $260.00 | $325.00 | $250.00 | $297.00 | $290.75 |
| 28 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $2,980.00 | $3,000.00 | $2,400.00 | $3,218.00 | $4,719.00 |
| 29 | Catch basin, no. 2-4 (611E98540) | EACH | 1 | $4,900.00 | $4,000.00 | $4,400.00 | $4,909.00 | $5,938.00 |
| 30 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $500.00 | $650.00 | $256.00 | $759.00 | $529.25 |
| 31 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 13 | $499.00 | $900.00 | $803.00 | $730.00 | $730.00 |
| 32 | Aggregate base (304E20000) | CY | 55 | $132.00 | $160.00 | $120.00 | $101.00 | $123.75 |
| 33 | Non-tracking tack coat (407E20000) | GAL | 10 | $9.00 | $3.00 | $11.00 | $10.00 | $10.00 |
| 34 | Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100) | CY | 3 | $578.00 | $1,000.00 | $857.00 | $778.00 | $778.50 |
| 35 | Asphalt concrete surface course, 12.5 MM, type A (449) (driveways) (442E22120) | CY | 11 | $578.00 | $1,000.00 | $857.00 | $778.00 | $778.50 |
| 36 | Asphalt concrete intermediate course, 12.5 MM, type A (449) (442E22300) | CY | 3 | $542.00 | $1,000.00 | $857.00 | $778.00 | $778.50 |
| 37 | Asphalt concrete intermediate course, 12.5 MM, type A (449) (driveways) (442E22320) | CY | 8 | $542.00 | $1,000.00 | $857.00 | $778.00 | $778.50 |
| 38 | Special - 4" water main dip class 52 mechanical JO [alternate group AA1] (638E20000) | FT | 36 | $300.00 | $235.00 | $211.00 | $550.00 | $348.50 |
| 39 | Special - 10" steel pipe encasement, open cut (del [alternate group AA1] (638E20442) | FT | 12 | $360.00 | $425.00 | $350.00 | $274.00 | $206.50 |
| 42 | Edge line, 6" (644E00104) | MI | 0.02 | $43,500 | $13,500 | $61,900 | $13,500 | $150,000 |
| 43 | Center line (644E00300) | MI | 0.01 | $79,500 | $19,500 | $119,600 | $19,500 | $150,000 |
| 44 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 32 | $75.00 | $75.00 | $88.00 | $150.00 | $75.00 |
| 45 | Detour signing (614E12420) | LS | 1 | $9,175.00 | $11,263 | $10,100 | $18,137 | $11,263 |
| 46 | Asphalt concrete for maintaining traffic (614E13000) | CY | 35 | $300.00 | $100.00 | $500.00 | $460.00 | $350.00 |
| 47 | Portable changeable message sign, as per plan (614E18601) | SNMT | 5 | $750.00 | $1,302.30 | $825.00 | $1,070.00 | $1,302.25 |
| 48 | Water (617E25000) | MGAL | 1 | $300.00 | $100.00 | $20.00 | $622.00 | $190.00 |
| 49 | Center line, type 1 (642E00300) | MI | 0.25 | $6,900.00 | $1,300.00 | $4,600.00 | $1,300.00 | $6,000.00 |
| 50 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $3,400.00 | $10,000 | $2,507.00 | $4,437.25 |
| 51 | Maintaining traffic (614E11000) | LS | 1 | $2,815.00 | $7,500.00 | $3,500.00 | $2,500.00 | $4,961.75 |
| 52 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,250.00 | $5,000.00 | $3,900.00 | $5,250.00 | $6,265.75 |
| 53 | Mobilization (624E10000) | LS | 1 | $4,000.00 | $10,000 | $10,000 | $9,333.00 | $27,008 |
| 100 | Water work, misc.:EX. water main connection (by DE [alternate group AA1] (638E98000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.