ODOT contract 250047 bid tabulation
FAI-SR 204-02.28 (INTERSECTION). Let by Ohio DOT on January 30, 2025, FAI. 5 bids received; low bid $842,043 by Shelly Company, +0.7% against the engineer's estimate of $836,000.
- Owner
- Ohio DOT
- Letting
- 30 JAN 2025
- Pay items
- 100
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $842,043 | Low | +1.0% |
| 2 | Axis Civil Construction LLC | $863,880 | +3.0% | +3.0% |
| 3 | Strawser Paving Co Inc | $931,073 | +11% | +11% |
| 4 | Decker Construction Company | $979,852 | +16% | +17% |
| 5 | Double Z Construction Company | $1,044,233 | +24% | +25% |
Engineer's estimate: $836,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Axis Civil Construction LLC | 3. Strawser Paving Co Inc | 4. Decker Construction Company | 5. Double Z Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $13,750 | $10,000 | $14,500 | $10,000 | $40,000 |
| 2 | Pavement removed (202E23000) | SY | 781 | $16.35 | $12.00 | $23.00 | $21.34 | $34.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 113 | $52.75 | $22.00 | $31.00 | $67.31 | $15.00 |
| 4 | Mailbox removed (202E53100) | EACH | 7 | $69.75 | $150.00 | $60.00 | $116.85 | $80.00 |
| 5 | Valve box removed (202E75610) | EACH | 5 | $190.00 | $250.00 | $130.00 | $1,105.92 | $250.00 |
| 6 | Removal misc.: - (2) 2' X 2' brick pillars, stone (202E98000) | LS | 1 | $380.00 | $1,500.00 | $1,400.00 | $2,283.84 | $800.00 |
| 7 | Removal misc.: (2) signs (202E98000) | LS | 1 | $380.00 | $400.00 | $95.00 | $177.42 | $250.00 |
| 8 | Removal misc.: flower bed (202E98100) | EACH | 2 | $190.00 | $400.00 | $700.00 | $534.96 | $300.00 |
| 9 | Excavation (203E10000) | CY | 692 | $43.50 | $36.00 | $50.00 | $69.27 | $54.00 |
| 10 | Embankment (203E20000) | CY | 131 | $36.75 | $36.00 | $105.00 | $125.29 | $50.00 |
| 11 | Subgrade compaction (204E10000) | SY | 1,850 | $2.80 | $3.00 | $3.00 | $2.43 | $11.00 |
| 12 | Special - geocell, subgrade - 6" (204E60000) | SY | 1,558 | $2.15 | $4.20 | $7.00 | $6.00 | $12.00 |
| 13 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,750.00 | $1,500.00 | $550.00 | $2,000.00 | $1,500.00 |
| 14 | Post construction survey monument verification and report (623E51000) | LS | 1 | $9,000.00 | $1,500.00 | $550.00 | $2,000.00 | $1,500.00 |
| 15 | Special - reinforced mesh for transverse and/or longitudinal joints and cracks (690E12050) | SY | 886 | $27.50 | $15.00 | $18.00 | $15.00 | $27.50 |
| 16 | Special - mailbox support system, single (690E50100) | EACH | 3 | $195.00 | $200.00 | $200.00 | $293.88 | $285.00 |
| 17 | Special - mailbox support system, multiple (690E50300) | EACH | 1 | $420.00 | $250.00 | $250.00 | $743.88 | $495.00 |
| 18 | Rock channel protection, type C with filter (601E32200) | CY | 1 | $1,000.00 | $250.00 | $1,025.00 | $486.96 | $350.00 |
| 19 | Seeding and mulching, class 2 (659E00510) | SY | 2,446 | $2.01 | $1.50 | $1.50 | $3.65 | $3.50 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.30 | $888.40 | $1,250.00 | $1,250.00 | $787.50 | $750.00 |
| 21 | Lime (659E31000) | ACRE | 0.50 | $156.50 | $150.00 | $150.00 | $20.50 | $20.00 |
| 22 | Water (659E35000) | MGAL | 13.20 | $1.00 | $1.00 | $1.00 | $100.00 | $9.00 |
| 23 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Aggregate drains (605E31100) | FT | 180 | $11.00 | $15.00 | $40.00 | $34.93 | $24.00 |
| 25 | 6" conduit, type E (611E01400) | FT | 50 | $18.00 | $25.00 | $13.00 | $26.44 | $8.00 |
| 26 | 6" conduit, type F (611E01500) | FT | 50 | $18.00 | $25.00 | $13.00 | $23.08 | $8.00 |
| 27 | 12" conduit, type C (611E04600) | FT | 325 | $54.25 | $65.00 | $125.00 | $106.37 | $135.00 |
| 28 | 15" conduit, type A (611E05700) | FT | 112 | $106.00 | $125.00 | $160.00 | $142.20 | $175.00 |
| 29 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $2,800.00 | $3,600.00 | $5,000.00 | $3,289.92 | $4,000.00 |
| 30 | Full depth pavement sawing (252E01500) | FT | 1,594 | $2.45 | $2.60 | $2.00 | $3.60 | $3.50 |
| 31 | Pavement planing, asphalt concrete - variable dept (254E01000) | SY | 2,135 | $6.20 | $6.10 | $5.25 | $6.28 | $6.20 |
| 32 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 251 | $205.00 | $258.00 | $235.00 | $279.32 | $228.00 |
| 33 | Asphalt concrete base, PG64-22, (449), (driveways) (301E56100) | CY | 21 | $325.00 | $258.00 | $410.00 | $648.16 | $340.00 |
| 34 | Aggregate base (304E20000) | CY | 256 | $68.00 | $115.00 | $110.00 | $94.18 | $125.00 |
| 35 | Non-tracking tack coat (407E20000) | GAL | 446 | $3.90 | $6.00 | $4.40 | $4.90 | $3.90 |
| 36 | Prime coat, as per plan (408E10001) | GAL | 122 | $5.00 | $6.00 | $4.80 | $5.00 | $5.00 |
| 37 | Stabilized crushed aggregate (411E10000) | CY | 260 | $85.00 | $115.00 | $110.00 | $93.52 | $150.00 |
| 38 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 118 | $274.00 | $330.00 | $280.00 | $327.82 | $300.00 |
| 39 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 160 | $191.00 | $280.00 | $225.00 | $289.32 | $214.00 |
| 40 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 8 | $635.00 | $450.00 | $1,000.00 | $676.66 | $650.00 |
| 41 | Compacted aggregate, as per plan (617E10101) | CY | 34 | $170.00 | $145.00 | $225.00 | $228.20 | $170.00 |
| 42 | Valve box, as per plan (638E07609) | EACH | 5 | $1,700.00 | $750.00 | $425.00 | $3,468.96 | $750.00 |
| 43 | Fire hydrant extended and adjusted to grade, as per plan (638E10301) | EACH | 1 | $2,900.00 | $5,500.00 | $4,500.00 | $1,535.52 | $5,500.00 |
| 44 | Fire hydrant adjusted to grade, as per plan (638E10401) | EACH | 1 | $2,600.00 | $2,200.00 | $4,000.00 | $6,730.56 | $1,000.00 |
| 45 | RPM (621E00100) | EACH | 30 | $125.00 | $125.00 | $116.00 | $126.00 | $120.00 |
| 46 | Raised pavement marker removed (621E54000) | EACH | 27 | $6.25 | $40.00 | $2.00 | $10.48 | $20.00 |
| 47 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 110 | $21.40 | $20.00 | $19.36 | $40.30 | $21.40 |
| 48 | Sign post reflector (630E08600) | EACH | 3 | $45.00 | $50.00 | $68.46 | $194.25 | $45.00 |
| 49 | Sign, flat sheet (630E80100) | SF | 54.25 | $32.00 | $25.00 | $22.59 | $46.20 | $32.00 |
| 50 | Removal of ground mounted sign and disposal (630E84900) | EACH | 8 | $15.00 | $40.00 | $16.09 | $99.75 | $15.00 |
| 51 | Removal of ground mounted post support and disposal (630E86002) | EACH | 8 | $20.00 | $40.00 | $21.46 | $99.75 | $20.00 |
| 52 | Edge line, 6" (644E00104) | MI | 0.29 | $9,555.00 | $9,555.00 | $8,100.00 | $10,033 | $9,555.00 |
| 53 | Center line (644E00300) | MI | 0.20 | $12,650 | $12,650 | $8,100.00 | $13,283 | $12,650 |
| 54 | Channelizing line, 8" (644E00400) | FT | 118 | $2.50 | $2.50 | $1.50 | $2.60 | $2.50 |
| 55 | Stop line (644E00500) | FT | 72 | $9.00 | $9.00 | $6.00 | $9.45 | $9.00 |
| 56 | Transverse/diagonal line (644E00700) | FT | 210 | $8.30 | $8.30 | $6.00 | $8.70 | $8.30 |
| 57 | Island marking (644E00900) | SF | 57 | $3.50 | $3.50 | $9.00 | $3.65 | $3.50 |
| 58 | Lane arrow (644E01300) | EACH | 2 | $110.00 | $110.00 | $90.00 | $115.50 | $110.00 |
| 59 | Word on pavement, 72" (644E01400) | EACH | 1 | $150.00 | $150.00 | $275.00 | $157.50 | $150.00 |
| 60 | Conduit, 2", 725.05 (625E25402) | FT | 20 | $11.00 | $14.00 | $32.00 | $11.35 | $14.00 |
| 61 | Conduit, 4", 725.05 (625E25602) | FT | 10 | $27.00 | $24.00 | $64.00 | $27.85 | $24.00 |
| 62 | Trench, 24" deep (625E29002) | FT | 10 | $11.00 | $45.00 | $26.00 | $11.35 | $45.00 |
| 63 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $1,550.00 | $1,400.00 | $2,900.00 | $1,596.50 | $1,400.00 |
| 64 | Ground rod (625E32000) | EACH | 5 | $300.00 | $275.00 | $400.00 | $309.00 | $275.00 |
| 65 | Arc flash calculations and label - controller (625E76000) | EACH | 1 | $2,100.00 | $3,500.00 | $3,850.00 | $2,163.00 | $3,500.00 |
| 66 | Sign hanger assembly, span wire (630E79000) | EACH | 1 | $485.00 | $540.00 | $272.94 | $1,155.00 | $485.00 |
| 67 | Sign support assembly, pole mounted (630E79500) | EACH | 4 | $235.00 | $180.00 | $129.56 | $383.25 | $235.00 |
| 68 | Sign, flat sheet (630E80100) | SF | 14 | $32.50 | $32.00 | $22.59 | $69.30 | $32.50 |
| 69 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007) | EACH | 5 | $950.00 | $1,250.00 | $1,110.00 | $978.50 | $1,250.00 |
| 70 | Vehicular signal head, (LED), 4-section, 12" lens, 1-way, polycarbonate, as per plan (632E05065) | EACH | 2 | $1,425.00 | $1,750.00 | $1,670.00 | $1,467.75 | $1,750.00 |
| 71 | Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate, as per plan (632E05087) | EACH | 1 | $1,600.00 | $2,000.00 | $1,980.00 | $1,648.00 | $2,000.00 |
| 72 | Covering of vehicular signal head (632E25000) | EACH | 8 | $40.00 | $40.00 | $130.00 | $41.20 | $40.00 |
| 73 | Messenger wire, 7 strand, 7/16" diameter with accessories (632E30300) | FT | 307 | $27.00 | $25.00 | $21.50 | $27.85 | $25.00 |
| 74 | Tether wire, with accessories (632E30600) | FT | 307 | $33.00 | $20.00 | $32.00 | $34.00 | $20.00 |
| 75 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 588 | $3.25 | $3.25 | $5.00 | $3.35 | $3.25 |
| 76 | Strain pole foundation (632E64000) | EACH | 4 | $8,000.00 | $8,750.00 | $6,985.00 | $8,240.00 | $8,750.00 |
| 77 | Power cable, 3 conductor, no. 8 AWG (632E67300) | FT | 55 | $5.00 | $6.40 | $7.30 | $5.15 | $6.40 |
| 78 | Service cable, 3 conductor, no. 8 AWG (632E69700) | FT | 46 | $5.00 | $7.00 | $4.50 | $5.15 | $7.00 |
| 79 | Power service, as per plan (632E70001) | EACH | 1 | $4,100.00 | $1,250.00 | $2,300.00 | $4,223.00 | $1,250.00 |
| 80 | Strain pole, type TC-81.11, design 10 (632E86130) | EACH | 4 | $12,000 | $9,900.00 | $11,100 | $12,360 | $9,900.00 |
| 81 | Removal of traffic signal installation, as per plan (632E90101) | EACH | 1 | $3,500.00 | $1,600.00 | $5,300.00 | $3,605.00 | $1,600.00 |
| 82 | Cabinet, type 332, as per plan (633E65521) | EACH | 1 | $18,000 | $17,000 | $20,300 | $18,540 | $17,000 |
| 83 | Cabinet foundation, as per plan (633E67101) | EACH | 1 | $3,650.00 | $3,100.00 | $5,280.00 | $3,759.50 | $3,100.00 |
| 84 | Controller work pad, as per plan (633E67201) | EACH | 1 | $1,700.00 | $750.00 | $715.00 | $1,751.00 | $750.00 |
| 85 | Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001) | EACH | 1 | $8,200.00 | $7,700.00 | $7,900.00 | $8,446.00 | $7,700.00 |
| 86 | Advance radar detection, as per plan (809E69001) | EACH | 2 | $8,550.00 | $9,850.00 | $9,550.00 | $8,806.50 | $9,850.00 |
| 87 | Stop line radar detection, as per plan (809E69101) | EACH | 3 | $8,400.00 | $9,550.00 | $9,900.00 | $8,652.00 | $9,550.00 |
| 88 | Atc controller, as per plan (809E69123) | EACH | 1 | $811.68 | $935.00 | $1,850.00 | $836.05 | $935.00 |
| 89 | Traffic compacted surface, type A (410E10000) | CY | 50 | $89.00 | $65.00 | $75.00 | $60.00 | $45.00 |
| 90 | Traffic compacted surface, type B (410E11000) | CY | 50 | $89.00 | $65.00 | $75.00 | $60.00 | $45.00 |
| 91 | Detour signing (614E12420) | LS | 1 | $3,500.00 | $3,500.00 | $9,000.00 | $10,149 | $20,000 |
| 92 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $265.00 | $200.00 | $600.00 | $680.00 | $200.00 |
| 93 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,600.00 | $1,200.00 | $900.00 | $935.55 | $1,000.00 |
| 94 | Water (616E10000) | MGAL | 1 | $1.00 | $1.00 | $50.00 | $100.00 | $100.00 |
| 95 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $6,500.00 | $6,000.00 | $3,500.00 | $7,000.00 |
| 96 | Maintaining traffic (614E11000) | LS | 1 | $17,500 | $20,000 | $20,000 | $10,000 | $18,000 |
| 97 | Field office, type B (619E16010) | MNTH | 4 | $2,500.00 | $1,650.00 | $3,500.00 | $2,000.00 | $2,000.00 |
| 98 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $5,000.00 | $15,000 | $6,500.00 | $10,000 | $15,900 |
| 99 | Mobilization (624E10000) | LS | 1 | $37,250 | $20,000 | $20,000 | $17,000 | $45,000 |
| 100 | Special - calendar days of contract time for opening to traffic (unit price field should reflect number of days bid) (614E15000) | DLR | 3,500 | $40.00 | $45.00 | $45.00 | $46.00 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.