ODOT contract 250090 bid tabulation
JEF-SR 43-02.00 (TWO LANE RESURFACING). Let by Ohio DOT on February 13, 2025, JEF. 3 bids received; low bid $1,718,137 by NLS Paving, Inc, +7.1% against the engineer's estimate of $1,604,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 39
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | NLS Paving, Inc | $1,718,137 | Low | +7.0% |
| 2 | Shelly & Sands Inc | $1,745,551 | +2.0% | +9.0% |
| 3 | Cast & Baker Corporation | $2,103,272 | +22% | +31% |
Engineer's estimate: $1,604,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. NLS Paving, Inc | 2. Shelly & Sands Inc | 3. Cast & Baker Corporation |
|---|---|---|---|---|---|---|
| 1 | Wearing course removed (202E23500) | SY | 1,767 | $12.00 | $10.00 | $7.45 |
| 2 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 4 | $1,900.00 | $2,750.00 | $2,400.00 |
| 3 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 |
| 4 | Pavement planing, asphalt concrete, 2-1/4" (254E01000) | SY | 61,762 | $3.10 | $2.95 | $4.00 |
| 5 | Non-tracking tack coat (407E20000) | GAL | 9,624 | $3.50 | $3.50 | $3.15 |
| 6 | Asphalt concrete surface course, type 1, (446), PG70-22M (441E10100) | CY | 2,542 | $250.00 | $235.00 | $295.00 |
| 7 | Asphalt concrete intermediate course, type 1, (448) (441E50200) | CY | 1,716 | $225.00 | $235.00 | $290.00 |
| 8 | Asphalt concrete surface course, type 1, (449), (driveways), as per plan (441E70501) | CY | 62 | $550.00 | $500.00 | $800.00 |
| 9 | Pavement planing, asphalt concrete, class A, 1-1/4 (897E01010) | SY | 11,450 | $2.85 | $3.95 | $4.30 |
| 10 | Patching planed surface (897E02000) | SY | 343 | $10.00 | $25.00 | $56.00 |
| 11 | RPM (621E00100) | EACH | 170 | $45.00 | $45.00 | $47.00 |
| 12 | Raised pavement marker removed (621E54000) | EACH | 170 | $9.00 | $26.00 | $27.00 |
| 13 | Sign, flat sheet (630E80100) | SF | 304.70 | $30.00 | $31.00 | $21.00 |
| 14 | Sign, street name, as per plan (630E80511) | EACH | 32 | $275.00 | $275.00 | $525.00 |
| 15 | Sign erected, flat sheet (630E81100) | SF | 315.20 | $30.00 | $31.00 | $16.00 |
| 16 | Removal of ground mounted sign and disposal (630E84900) | EACH | 50 | $20.00 | $20.00 | $20.00 |
| 17 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 38 | $42.00 | $43.00 | $240.00 |
| 18 | Removal of pole mounted sign and disposal (630E87500) | EACH | 6 | $25.00 | $25.00 | $50.00 |
| 19 | Lane line, 6" (644E00204) | MI | 4.96 | $1,600.00 | $1,700.00 | $2,200.00 |
| 20 | Center line (644E00300) | MI | 2.74 | $4,250.00 | $4,500.00 | $6,700.00 |
| 21 | Channelizing line, 8" (644E00400) | FT | 1,326 | $1.50 | $1.55 | $2.50 |
| 22 | Stop line (644E00500) | FT | 548 | $6.15 | $6.50 | $8.00 |
| 23 | Crosswalk line, 24", as per plan (644E00631) | FT | 2,048 | $6.15 | $6.50 | $7.50 |
| 24 | Transverse/diagonal line (644E00700) | FT | 650 | $6.15 | $6.50 | $8.25 |
| 25 | Island marking (644E00900) | SF | 147 | $4.25 | $4.50 | $4.25 |
| 26 | Lane arrow (644E01300) | EACH | 23 | $100.00 | $100.00 | $105.00 |
| 27 | Dotted line, 6" (644E01510) | FT | 571 | $0.85 | $0.90 | $3.00 |
| 28 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 300 | $95.00 | $95.00 | $80.00 |
| 29 | Work zone marking sign (614E12460) | EACH | 12 | $100.00 | $105.00 | $105.00 |
| 30 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 7.09 | $1,750.00 | $1,000.00 | $3,750.00 |
| 31 | Work zone center line, class II, 642 paint (614E21500) | MI | 7.77 | $750.00 | $825.00 | $650.00 |
| 32 | Work zone center line, class III, 642 paint (614E21550) | MI | 7.77 | $2,050.00 | $1,500.00 | $3,850.00 |
| 33 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 3,314 | $1.20 | $1.00 | $1.50 |
| 34 | Work zone stop line, class III, 642 paint (614E26610) | FT | 2,305 | $4.65 | $4.75 | $5.25 |
| 35 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $9,100.00 | $7,500.00 | $16,500 |
| 36 | Maintaining traffic (614E11000) | LS | 1 | $115,000 | $191,601 | $85,000 |
| 37 | Field office, type B (619E16010) | MNTH | 3 | $1,500.00 | $1,175.00 | $5,500.00 |
| 38 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,000.00 | $2,500.00 | $6,000.00 |
| 39 | Mobilization (624E10000) | LS | 1 | $75,000 | $50,000 | $95,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.