ODOT contract 254007 bid tabulation

ERI-/HUR-SR 113/SR 13-20.18/04.13 (CULVERT REPLACEMENT). Let by Ohio DOT on February 13, 2025, ERI. 2 bids received; low bid $528,983 by Great Lakes Demolition Company, +1.1% against the engineer's estimate of $523,000.

Owner
Ohio DOT
Letting
13 FEB 2025
Pay items
54
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Great Lakes Demolition Company$528,983Low+1.0%
2Crawford Construction Company Inc$583,898+10%+12%
ODOT contract 254007: bids by rank

Engineer's estimate: $523,000.

Bid tabulation

LinePay itemUnitQuantity1. Great Lakes Demolition Company2. Crawford Construction Company Inc
1Clearing and grubbing (201E11000)LS1$31,500$4,700.00
2Headwall removed (202E20010)EACH4$2,500.00$620.00
3Pavement removed (202E23000)SY623$20.00$10.30
4Guardrail removed (202E38000)FT462.50$2.00$13.00
5Anchor assembly removed, type A (202E42000)EACH1$375.00$375.00
6Anchor assembly removed, type T (202E42040)EACH5$100.00$500.00
7Excavation (203E10000)CY71$20.00$84.00
8Embankment (203E20000)CY708$35.00$27.00
9Subgrade compaction (204E10000)SY690$3.00$2.20
10Guardrail, type MGS (606E15050)FT631.25$22.00$21.00
11Anchor assembly, MGS type E, MASH 2016 (606E26150)EACH3$2,650.00$2,600.00
12Anchor assembly, MGS type T (606E26550)EACH5$1,500.00$1,470.00
13Monument assembly, type C (623E38500)EACH4$2,000.00$1,800.00
14Preconstruction survey monument verification and report (623E50000)LS1$3,000.00$855.00
15Post construction survey monument verification and report (623E51000)LS1$3,000.00$855.00
16Riprap, type D (601E11000)SY30$200.00$286.00
17Rock channel protection, type B with filter (601E32100)CY81$130.00$140.00
18Soil analysis test (659E00100)EACH4$200.00$88.00
19Topsoil (659E00300)CY204$50.00$32.00
20Seeding and mulching (659E10000)SY1,833$3.00$4.40
21Repair seeding and mulching (659E14000)SY92$1.00$1.00
22Inter-seeding (659E15000)SY92$1.00$1.00
23Commercial fertilizer (659E20000)TON0.24$1,000.00$715.00
24Lime (659E31000)ACRE0.38$800.00$55.00
25Water (659E35000)MGAL10.15$1.00$1.10
26Slope erosion protection mat, type B (670E00520)SY894$4.00$3.60
27Erosion control (832E30000)EACH4,000$1.00$1.00
28Aggregate drains (605E31100)FT96$15.00$26.00
2954" conduit, type A (611E22200)FT94$325.00$600.00
3058" X 91" conduit, type A, 706.04 (611E53400)FT88$555.00$1,400.00
31Pavement planing, asphalt concrete (3.0") (254E01000)SY314$25.00$53.00
32Asphalt concrete base, PG64-22, (449) (301E56000)CY163$250.00$300.00
33Aggregate base (304E20000)CY185$65.00$134.00
34Tack coat (407E10000)GAL106$4.00$4.40
35Asphalt concrete surface course, 9.5 MM, type A (4 (442E22001)CY80$335.00$388.00
36RPM (621E00100)EACH6$165.00$710.00
37Raised pavement marker removed (621E54000)EACH6$60.00$60.00
38Barrier reflector, type 2, bidirectional (626E00110)EACH13$11.00$11.00
39Edge line, 6", type 1 (642E00104)MI0.18$5,000.00$19,722
40Center line, type 1 (642E00300)MI0.09$10,000$45,560
41Detour signing (614E12420)LS1$10,500$10,450
42Portable changeable message sign, as per plan (614E18601)SNMT4$1,000.00$1,320.00
43Structure removed, as per plan (202E11001)LS1$16,500$15,000
44Cofferdams and excavation bracing (503E11100)LS1$8,500.00$8,000.00
45Concrete masonry (602E20000)CY4$3,200.00$1,500.00
46Special - temporary support of utility duct (690E98400)LS1$8,500.00$3,000.00
47Structure removed, as per plan (202E11001)LS1$16,500$17,200
48Cofferdams and excavation bracing (503E11100)LS1$8,500.00$5,500.00
49Concrete masonry (602E20000)CY3$2,500.00$2,000.00
50Premium for contract performance bond and for payment bond (103E05000)LS1$8,500.00$7,000.00
51Maintaining traffic (614E11000)LS1$12,500$5,500.00
52Field office, type B (619E16010)MNTH3$1,500.00$1,650.00
53Construction layout stakes and surveying (623E10000)LS1$9,500.00$8,300.00
54Mobilization (624E10000)LS1$60,000$36,500
ODOT contract 254007: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy