ODOT contract 250100 bid tabulation
PIK-SR 220-05.50SR (CULVERT REPLACEMENT). Let by Ohio DOT on February 13, 2025, PIK. 6 bids received; low bid $554,331 by D G M Inc, -8.4% against the engineer's estimate of $605,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 74
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | D G M Inc | $554,331 | Low | -8.0% |
| 2 | Axis Civil Construction LLC | $662,411 | +19% | +9.0% |
| 3 | Fillmore Construction | $688,714 | +24% | +14% |
| 4 | Double Z Construction Company | $692,391 | +25% | +14% |
| 5 | Sunesis Construction Co | $816,517 | +47% | +35% |
| 6 | Alan Stone Co Inc | $836,973 | +51% | +38% |
Engineer's estimate: $605,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D G M Inc | 2. Axis Civil Construction LLC | 3. Fillmore Construction | 4. Double Z Construction Company | 5. Sunesis Construction Co | 6. Alan Stone Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $14,000 | $6,000.00 | $3,500.00 | $18,000 | $3,500.00 | $3,200.00 |
| 2 | Pavement removed (202E23000) | SY | 139 | $6.00 | $12.00 | $20.00 | $25.00 | $22.00 | $70.00 |
| 3 | Guardrail removed (202E38000) | FT | 262.50 | $1.00 | $5.00 | $3.50 | $6.00 | $4.00 | $4.00 |
| 4 | Anchor assembly removed, type A (202E42000) | EACH | 4 | $250.00 | $300.00 | $250.00 | $250.00 | $928.00 | $240.00 |
| 5 | Excavation (203E10000) | CY | 415 | $22.50 | $30.00 | $30.00 | $50.00 | $55.90 | $60.00 |
| 6 | Embankment (203E20000) | CY | 52 | $35.00 | $30.00 | $100.00 | $20.00 | $90.40 | $50.00 |
| 7 | Subgrade compaction (204E10000) | SY | 312 | $10.00 | $3.00 | $10.00 | $9.00 | $6.75 | $8.50 |
| 8 | Guardrail, type MGS (606E15050) | FT | 200 | $45.00 | $35.00 | $35.00 | $35.00 | $42.56 | $40.00 |
| 9 | Anchor assembly, MGS type E, (MASH 2016) (606E26150) | EACH | 3 | $2,300.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,240.00 | $2,900.00 |
| 10 | Anchor assembly, MGS type T (606E26550) | EACH | 3 | $1,100.00 | $1,250.00 | $1,250.00 | $1,250.00 | $990.00 | $1,500.00 |
| 11 | Monument assembly, type C (623E38500) | EACH | 4 | $1,000.00 | $2,295.00 | $1,000.00 | $1,600.00 | $1,461.69 | $1,600.00 |
| 12 | Seeding and mulching (659E10000) | SY | 1,342 | $2.75 | $2.50 | $1.75 | $6.00 | $3.87 | $3.00 |
| 13 | Repair seeding and mulching (659E14000) | SY | 67 | $0.05 | $2.50 | $2.00 | $2.50 | $2.35 | $3.00 |
| 14 | Commercial fertilizer (659E20000) | TON | 0.18 | $1,500.00 | $1,250.00 | $1,400.00 | $1,250.00 | $1,644.72 | $650.00 |
| 15 | Lime (659E31000) | ACRE | 0.28 | $300.00 | $150.00 | $450.00 | $150.00 | $528.64 | $930.00 |
| 16 | Water (659E35000) | MGAL | 7.20 | $1.00 | $1.00 | $100.00 | $1.00 | $1.00 | $120.00 |
| 17 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | Full depth pavement sawing (252E01500) | FT | 36 | $15.00 | $4.00 | $20.00 | $7.00 | $12.50 | $70.00 |
| 19 | Pavement planing, asphalt concrete, (1.25") (254E01000) | SY | 40 | $42.00 | $55.00 | $50.00 | $155.00 | $155.04 | $190.00 |
| 20 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 22 | $495.00 | $350.00 | $300.00 | $475.00 | $475.00 | $690.00 |
| 21 | Aggregate base (304E20000) | CY | 46 | $120.00 | $150.00 | $100.00 | $115.00 | $78.85 | $90.00 |
| 22 | Tack coat (407E10000) | GAL | 36 | $2.50 | $5.00 | $10.00 | $2.50 | $2.50 | $50.00 |
| 23 | Stabilized crushed aggregate (411E10000) | CY | 9 | $150.00 | $170.00 | $200.00 | $150.00 | $123.08 | $110.00 |
| 24 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 8 | $520.00 | $550.00 | $500.00 | $495.00 | $495.00 | $840.00 |
| 25 | Ground mounted support, no. 2 post (630E02100) | FT | 27.50 | $15.00 | $25.00 | $15.00 | $15.00 | $25.00 | $15.00 |
| 26 | Sign post reflector (630E08600) | EACH | 1 | $40.00 | $95.00 | $50.00 | $50.00 | $95.00 | $60.00 |
| 27 | Removal of ground mounted sign and reerection (630E85100) | EACH | 3 | $60.00 | $85.00 | $100.00 | $100.00 | $85.00 | $120.00 |
| 28 | Center line, type 1 (642E00300) | MI | 0.12 | $9,500.00 | $25,535 | $8,550.00 | $25,535 | $12,800 | $10,000 |
| 29 | Pavement repair (253E02000) | CY | 50 | $355.00 | $350.00 | $300.00 | $545.02 | $455.00 | $200.00 |
| 30 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 14 | $375.00 | $300.00 | $300.00 | $475.00 | $475.00 | $300.00 |
| 31 | Tack coat (407E10000) | GAL | 50 | $2.50 | $5.00 | $10.00 | $2.50 | $2.50 | $4.50 |
| 32 | Stabilized crushed aggregate (411E10000) | CY | 50 | $40.00 | $85.00 | $200.00 | $85.00 | $124.25 | $160.00 |
| 33 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 50 | $260.00 | $300.00 | $400.00 | $360.00 | $79.20 | $350.00 |
| 34 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 8 | $60.00 | $75.00 | $100.00 | $65.00 | $85.00 | $100.00 |
| 35 | Increased barrier delineation (614E11630) | FT | 240 | $2.50 | $2.40 | $2.30 | $4.69 | $2.91 | $2.50 |
| 36 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $2,200.00 | $2,000.00 | $2,400.00 | $2,400.00 | $2,351.21 | $2,800.00 |
| 37 | Detour signing (614E12420) | LS | 1 | $6,700.00 | $10,000 | $6,500.00 | $11,500 | $8,153.24 | $7,600.00 |
| 38 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $125.00 | $300.00 | $300.00 | $180.00 | $360.00 | $250.00 |
| 39 | Barrier reflector, type 1, (bidirectional) (614E13310) | EACH | 5 | $55.00 | $12.00 | $55.00 | $27.11 | $12.68 | $65.00 |
| 40 | Object marker, two way (614E13360) | EACH | 5 | $60.00 | $18.00 | $60.00 | $19.36 | $20.12 | $70.00 |
| 41 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.18 | $1,500.00 | $35,577 | $14,500 | $33,702 | $20,456 | $13,294 |
| 42 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.08 | $12,500 | $30,305 | $12,050 | $28,195 | $16,057 | $14,000 |
| 43 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 22 | $15.00 | $43.00 | $14.00 | $43.00 | $10.11 | $15.00 |
| 44 | Water (616E10000) | MGAL | 1 | $1.00 | $1.00 | $100.00 | $50.00 | $12.83 | $1.00 |
| 45 | Portable barrier, unanchored (622E41100) | FT | 240 | $25.00 | $25.00 | $30.00 | $50.00 | $67.14 | $35.00 |
| 46 | Portions of structure removed (202E11200) | LS | 1 | $29,500 | $8,000.00 | $25,000 | $35,000 | $14,875 | $16,000 |
| 47 | Wearing course removed (202E23500) | SY | 47 | $12.00 | $22.00 | $20.00 | $15.00 | $16.09 | $15.00 |
| 48 | Bridge railing removed (202E38500) | FT | 50 | $10.00 | $15.00 | $10.00 | $10.00 | $8.38 | $15.00 |
| 49 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $70,000 | $110,000 | $58,000 | $83,000 | $231,175 | $226,000 |
| 50 | Unclassified excavation (503E21300) | LS | 1 | $13,000 | $25,000 | $10,000 | $34,000 | $19,855 | $8,000.00 |
| 51 | Class QC1 concrete, footing (511E46510) | CY | 57 | $625.00 | $825.00 | $800.00 | $775.00 | $557.41 | $1,100.00 |
| 52 | Class QC1 concrete, headwall (511E46610) | CY | 2 | $1,500.00 | $1,200.00 | $1,200.00 | $2,000.00 | $2,083.21 | $2,300.00 |
| 53 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 60 | $40.00 | $43.00 | $30.00 | $75.00 | $60.00 | $50.00 |
| 54 | Type 2 waterproofing (512E33000) | SY | 88 | $22.00 | $20.00 | $35.00 | $30.00 | $26.50 | $35.00 |
| 55 | Type 3 waterproofing (512E33010) | SY | 139 | $35.00 | $40.00 | $80.00 | $45.00 | $40.00 | $55.00 |
| 56 | Rock channel protection, type B with aggregate filter (601E32110) | CY | 51 | $120.00 | $100.00 | $200.00 | $115.00 | $169.10 | $150.00 |
| 57 | 20' X 5' conduit, type A, 706.05, as per plan (611E96489) | FT | 52 | $2,800.00 | $3,020.00 | $4,000.00 | $2,450.00 | $2,605.18 | $2,300.00 |
| 58 | Epoxy coated steel reinforcement (509E10000) | LB | 6,957 | $1.75 | $2.00 | $2.80 | $2.50 | ||
| 59 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 19 | $1,200.00 | $1,800.00 | $2,028.09 | $2,000.00 | ||
| 60 | 1" preformed expansion joint filler (516E13600) | SF | 32 | $12.00 | $15.00 | $4.32 | $2.00 | ||
| 61 | Porous backfill with geotextile fabric (518E21200) | CY | 25 | $100.00 | $135.00 | $157.46 | $140.00 | ||
| 62 | Epoxy coated steel reinforcement (509E10000) | LB | 5,199 | $2.85 | $3.00 | ||||
| 63 | Precast gravity and semigravity retaining wall (851E10000) | SF | 514 | $75.00 | $100.00 | ||||
| 64 | Natural soil (851E11000) | CY | 13 | $45.00 | $100.00 | ||||
| 65 | On-site assistance (851E14000) | DAY | 2 | $500.00 | $1,000.00 | ||||
| 66 | Wall drainage system (851E15000) | LS | 1 | $4,500.00 | $1,500.00 | ||||
| 67 | PGSRW inspection and compaction testing (851E15500) | LS | 1 | $4,000.00 | $5,000.00 | ||||
| 68 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $4,500.00 | $5,000.00 | $5,000.00 | $5,195.26 | $5,200.00 |
| 69 | Maintaining traffic (614E11000) | LS | 1 | $28,500 | $25,000 | $25,000 | $35,000 | $18,537 | $31,000 |
| 70 | Field office, type A (619E16000) | MNTH | 2 | $750.00 | $2,200.00 | $1,000.00 | $1,200.00 | $1,660.00 | $800.00 |
| 71 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,000.00 | $4,500.00 | $3,500.00 | $8,000.00 | $7,200.00 | $10,000 |
| 72 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,000.00 | $750.00 | $3,500.00 | $1,000.00 | $1,500.00 | $1,700.00 |
| 73 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,000.00 | $750.00 | $3,500.00 | $1,000.00 | $1,500.00 | $1,700.00 |
| 74 | Mobilization (624E10000) | LS | 1 | $7,000.00 | $20,000 | $25,000 | $20,000 | $63,525 | $66,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.