ODOT contract 250083 bid tabulation
CLA-US 68-04.43 (FOUR LANE RESURFACING). Let by Ohio DOT on February 13, 2025, CLA. 3 bids received; low bid $7,086,327 by Shelly Company, -14% against the engineer's estimate of $8,229,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 57
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $7,086,327 | Low | -14% |
| 2 | John R Jurgensen Company | $7,316,379 | +3.0% | -11% |
| 3 | Barrett Paving Materials Inc | $9,279,281 | +31% | +13% |
Engineer's estimate: $8,229,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. John R Jurgensen Company | 3. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|
| 1 | Excavation, as per plan (203E10001) | CY | 950 | $29.50 | $28.45 | $65.00 |
| 2 | Special - tension meter (690E98000) | EACH | 2 | $3,600.00 | $3,750.00 | $3,750.00 |
| 3 | Special - training (690E98000) | EACH | 2 | $850.00 | $2,100.00 | $2,100.00 |
| 4 | Special - no mow strip (690E98300) | SY | 8,420 | $52.75 | $45.33 | $50.00 |
| 7 | Special - cable barrier with concrete line post foundation (606E55010) | FT | 18,020 | $19.50 | $19.50 | $20.50 |
| 8 | Special - cable barrier, anchor assembly (606E55150) | EACH | 18 | $3,875.00 | $3,875.00 | $4,100.00 |
| 11 | Soil analysis test (659E00100) | EACH | 2 | $500.00 | $500.00 | $500.00 |
| 12 | Topsoil (659E00300) | CY | 1,886 | $85.00 | $5.62 | $45.00 |
| 13 | Seeding and mulching (659E10000) | SY | 16,991 | $0.78 | $0.78 | $1.00 |
| 14 | Repair seeding and mulching (659E14000) | SY | 849 | $0.50 | $0.50 | $1.00 |
| 15 | Inter-seeding (659E15000) | SY | 849 | $0.01 | $0.01 | $1.00 |
| 16 | Commercial fertilizer (659E20000) | TON | 2.30 | $1,500.00 | $1,500.00 | $1,500.00 |
| 17 | Lime (659E31000) | ACRE | 3.49 | $200.00 | $200.00 | $200.00 |
| 18 | Water (659E35000) | MGAL | 96 | $1.00 | $1.00 | $1.00 |
| 19 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01041) | SY | 600 | $145.00 | $110.69 | $70.00 |
| 20 | Full depth rigid pavement removal and flexible replacement (252E01000) | SY | 1,312 | $250.00 | $197.04 | $260.00 |
| 21 | Full depth pavement sawing (252E01500) | FT | 5,712 | $2.35 | $2.22 | $3.50 |
| 22 | Non-tracking tack coat (407E20000) | GAL | 47,037 | $3.00 | $4.00 | $3.50 |
| 23 | Fine graded polymer asphalt concrete, type B, (448) (424E14000) | CY | 15,374 | $230.00 | $256.19 | $315.00 |
| 24 | Compacted aggregate (617E10100) | CY | 968 | $98.00 | $130.06 | $150.00 |
| 25 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 41.12 | $675.00 | $675.00 | $1,550.00 |
| 26 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 74.13 | $1,300.00 | $1,900.00 | $1,900.00 |
| 27 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 12,766 | $1.00 | $0.85 | $0.85 |
| 28 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 19,210 | $1.50 | $1.40 | $1.40 |
| 29 | Pavement planing, asphalt concrete, class A, 1" DE (897E01010) | SY | 553,290 | $0.75 | $0.85 | $2.05 |
| 30 | Patching planed surface, as per plan (897E02001) | SY | 400 | $14.00 | $3.87 | $10.00 |
| 31 | RPM (621E00100) | EACH | 1,522 | $34.00 | $34.00 | $35.00 |
| 32 | Raised pavement marker removed (621E54000) | EACH | 1,522 | $4.50 | $8.41 | $15.00 |
| 33 | Stop line (644E00500) | FT | 241 | $7.00 | $8.00 | $8.00 |
| 34 | Transverse/diagonal line (644E00700) | FT | 413 | $6.00 | $8.00 | $8.00 |
| 35 | Lane arrow (644E01300) | EACH | 23 | $100.00 | $125.00 | $125.00 |
| 36 | Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010) | MI | 53.09 | $4,200.00 | $4,600.00 | $4,600.00 |
| 37 | Wet reflective thermoplastic pavement marking, lane line, 6" (807E14110) | MI | 20.83 | $2,100.00 | $1,950.00 | $1,950.00 |
| 38 | Wet reflective thermoplastic pavement marking, center line (807E14200) | MI | 0.21 | $6,000.00 | $5,400.00 | $5,400.00 |
| 39 | Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310) | FT | 18,167 | $2.00 | $2.50 | $2.50 |
| 40 | Wet reflective thermoplastic pavement marking, dotted line, 6" (807E14410) | FT | 12,766 | $1.50 | $1.00 | $1.00 |
| 41 | Wet reflective thermoplastic pavement marking, dotted line, 12" (807E14430) | FT | 1,043 | $2.00 | $1.40 | $1.40 |
| 42 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 500 | $90.00 | $89.02 | $85.00 |
| 43 | Replacement drum (614E12600) | EACH | 25 | $45.00 | $100.00 | $45.00 |
| 44 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $800.00 | $800.00 | $800.00 |
| 45 | Work zone stop line, class III, 642 paint (614E26610) | FT | 116 | $3.00 | $8.00 | $8.00 |
| 46 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 23 | $35.00 | $70.00 | $70.00 |
| 47 | Work zone pavement marking, misc.: center line, CL (614E98000) | MI | 0.21 | $4,000.00 | $3,400.00 | $3,400.00 |
| 48 | Work zone pavement marking, misc.: edge line, clas (614E98000) | MI | 53.09 | $2,000.00 | $1,700.00 | $1,700.00 |
| 49 | Work zone pavement marking, misc.: lane line, clas (614E98000) | MI | 20.83 | $1,300.00 | $1,100.00 | $1,100.00 |
| 50 | Work zone pavement marking, misc.: channelizing LI (614E98100) | FT | 18,167 | $2.00 | $2.10 | $2.10 |
| 51 | Work zone pavement marking, misc.: dotted line, CL (614E98100) | FT | 1,043 | $2.00 | $2.00 | $2.00 |
| 52 | Work zone pavement marking, misc.: dotted line, CL (614E98100) | FT | 12,766 | $1.00 | $1.40 | $1.40 |
| 53 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 48 | $700.00 | $500.00 | $700.00 |
| 54 | Patching concrete bridge deck - type B (519E12300) | SY | 10 | $1,200.00 | $1,200.00 | $1,200.00 |
| 55 | Patching concrete bridge deck - type B (519E12300) | SY | 140 | $650.00 | $650.00 | $650.00 |
| 56 | Patching concrete bridge deck - type B (519E12300) | SY | 25 | $1,200.00 | $1,200.00 | $1,200.00 |
| 57 | Patching concrete bridge deck - type B (519E12300) | SY | 1 | $1,500.00 | $1,500.00 | $1,500.00 |
| 58 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $2,500.00 | $5,000.00 | $13,650 |
| 59 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,000 | $30,366 | $52,250 |
| 60 | Maintaining traffic (614E11000) | LS | 1 | $283,000 | $136,720 | $283,125 |
| 61 | Mobilization (624E10000) | LS | 1 | $110,000 | $200,000 | $125,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.