ODOT contract 250112 bid tabulation

WOO-IR 75-08.58 Weigh Station (PARKING AREAS). Let by Ohio DOT on February 13, 2025, WOO. 4 bids received; low bid $693,840 by Geddis Paving & Excavating Inc, -28% against the engineer's estimate of $963,000.

Owner
Ohio DOT
Letting
13 FEB 2025
Pay items
77
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Geddis Paving & Excavating Inc$693,840Low-28%
2Great Lakes Demolition Company$694,9810.0%-28%
3Advanced Excavating & Demolition LLC$742,651+7.0%-23%
4Ebony Construction Co$769,385+11%-20%
ODOT contract 250112: bids by rank

Engineer's estimate: $963,000.

Bid tabulation

LinePay itemUnitQuantity1. Geddis Paving & Excavating Inc2. Great Lakes Demolition Company3. Advanced Excavating & Demolition LLC4. Ebony Construction Co
1Clearing and grubbing, as per plan (201E11001)LS1$1,000.00$100.00$5,000.00$21,000
2Pavement removed (202E23000)SY483$30.00$20.00$17.00$26.00
3Pipe removed, 24" and under (202E35100)FT72$60.00$20.00$12.00$44.00
4Catch basin removed (202E58100)EACH1$500.00$450.00$650.00$518.00
5Special - fill and plug existing conduit (202E70000)FT45$60.00$25.00$35.00$74.50
6Excavation, as per plan (203E10001)CY635$15.00$20.00$24.00$18.50
7Embankment (203E20000)CY14$15.00$20.00$25.00$25.00
8Granular material, type B (203E35110)CY555$52.00$60.00$64.00$58.00
9Granular material, type D (203E35130)CY443$45.50$60.00$60.00$57.00
10Excavation of subgrade, as per plan (204E13001)CY997$16.00$20.00$18.00$21.50
11Linear grading (209E60200)STA21$115.00$150.00$90.00$465.00
12Topsoil stockpiled (651E10000)CY220$5.00$15.00$27.00$25.35
13Placing stockpiled topsoil (652E10000)CY220$9.00$20.00$27.00$51.75
14Special - soil sterilant (203E01890)SY6,000$0.35$0.80$0.55$0.75
15Tied concrete block mat with type 1 underlayment (601E21050)SY2$755.00$80.00$180.00$143.00
16Soil analysis test (659E00100)EACH2$67.00$200.00$60.00$61.00
17Topsoil (659E00300)CY350$55.00$50.00$85.00$85.00
18Seeding and mulching (659E10000)SY5,115$0.95$2.50$0.92$0.95
19Commercial fertilizer (659E20000)TON0.70$950.00$800.00$850.00$852.50
20Lime (659E31000)ACRE1.10$39.00$50.00$35.00$35.11
21Water (659E35000)MGAL27.60$1.00$1.00$1.00$1.00
22Erosion control (832E30000)EACH32,000$1.00$1.00$1.00$1.00
236" unclassified pipe underdrains (605E13300)FT62$45.00$15.00$36.00$14.00
246" conduit, type F (611E01500)FT28$45.00$15.00$40.00$16.50
25Precast reinforced concrete outlet (611E99710)EACH1$1,300.00$250.00$800.00$597.00
26Pavement repair (253E01000)SY54$86.00$85.00$105.00$85.00
27Pavement planing, asphalt concrete, 3.25" (254E01000)SY2,123$6.00$7.00$7.00$3.50
28Aggregate base (304E20000)CY334$61.00$60.00$73.00$89.00
29Tack coat (407E10000)GAL298$3.00$4.00$3.00$2.75
30Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100)CY89$265.00$350.00$310.00$490.00
31Asphalt concrete intermediate course, 12.5 MM, type A (449) (442E22300)CY104$265.00$325.00$310.00$440.00
3212" non-reinforced concrete pavement, class QC 1P (452E15010)SY1,995$115.00$82.00$103.00$100.00
33Compacted aggregate (617E10100)CY38$76.50$75.00$90.00$130.00
34Connection, fused pull apart (625E00450)EACH12$188.00$125.00$164.00$195.00
35Connection, unfused pull apart (625E00460)EACH21$188.00$125.00$158.25$195.00
36Light pole, conventional, design A20B32.5 (625E10490)EACH6$2,924.00$3,000.00$3,397.00$3,000.00
37Light pole foundation, 24" X 6' deep (625E14000)EACH6$1,750.00$1,500.00$2,046.25$1,800.00
38No. 4 AWG 2400 volt distribution cable (625E23200)FT258$4.00$4.00$5.00$4.00
39No. 12 AWG pole and bracket cable (625E23410)FT990$1.50$2.00$2.25$1.55
401-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320)FT902$14.50$17.00$17.25$18.00
41Conduit, 3", 725.04 (625E25500)FT18$14.50$25.00$33.00$14.50
42Conduit, jacked or drilled, 725.04, 3" (625E25902)FT48$91.00$60.00$69.50$95.00
43Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH6$528.00$450.00$512.75$550.00
44Trench, 24" deep (625E29002)FT902$8.25$10.00$11.00$8.35
45Pull box, 725.08, 18" (625E30700)EACH3$1,550.00$950.00$1,325.00$1,600.00
46Ground rod (625E32000)EACH7$475.00$250.00$326.25$490.00
47Power service, as per plan (625E34001)EACH1$3,246.00$7,500.00$7,500.00$3,450.00
48Underground warning marking tape (625E36010)FT920$2.50$2.00$2.00$2.30
49Luminaire support removed (625E75520)EACH9$308.00$300.00$587.00$320.00
50Luminaire support foundation removed (625E75522)EACH9$617.00$450.00$807.50$650.00
51Distribution cable removed (625E75550)FT6$308.00$2.00$7.00$320.00
52RPM (621E00100)EACH12$360.00$370.00$400.00$78.00
53Raised pavement marker removed (621E54000)EACH12$42.00$60.00$40.00$20.00
54Ground mounted support, no. 3 post, as per plan (630E03101)FT388$17.00$15.00$15.00$30.00
55Ground mounted structural beam support, W6X9 (630E06500)FT84$53.00$48.00$47.50$31.00
56Ground mounted wooden box beam support, type M beam (630E08302)FT18$130.00$115.00$115.00$260.00
57Sign post reflector (630E08600)EACH4$50.50$45.00$45.00$26.00
58Breakaway structural beam connection (630E09000)EACH4$945.00$820.00$820.00$452.00
59Sign, flat sheet (630E80100)SF142$19.50$18.00$17.50$31.00
60Sign, ground mounted extrusheet (630E80200)SF180$26.50$24.00$23.50$21.00
61Ground mounted structural beam support foundation (630E84500)EACH4$1,550.00$1,500.00$1,120.00$925.00
62Removal of ground mounted sign and disposal (630E84900)EACH8$11.00$10.00$10.00$285.00
63Removal of ground mounted post support and disposal (630E86002)EACH13$22.50$20.00$20.00$290.00
64Edge line, 6" (646E10010)MI0.22$14,000$15,000$15,000$15,500
65Edge line, 6" (646E10010)MI0.24$14,000$15,000$15,000$15,500
66Channelizing line, 12" (646E10310)FT257$5.05$2.00$2.00$2.10
67Transverse/diagonal line (646E10600)FT278$13.50$10.00$10.00$10.50
68Parking lot stall marking (646E20200)FT1,846$4.95$3.00$3.00$3.10
69Wrong way arrow (646E20320)EACH2$280.00$500.00$500.00$510.00
70Removal of pavement marking (646E50000)EACH8$95.00$50.00$50.00$52.00
71Removal of pavement marking (646E50100)FT1,472$1.70$2.50$2.50$3.00
72Replacement sign (614E12500)EACH5$130.00$200.00$192.00$195.00
73Replacement drum (614E12600)EACH5$75.00$60.00$56.00$57.25
74Premium for contract performance bond and for payment bond (103E05000)LS1$7,000.00$8,500.00$16,000$10,500
75Maintaining traffic (614E11000)LS1$15,000$10,500$15,000$7,400.00
76Construction layout stakes and surveying (623E10000)LS1$10,000$6,500.00$15,000$5,200.00
77Mobilization (624E10000)LS1$20,000$70,000$25,000$20,000
ODOT contract 250112: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way