ODOT contract 250084 bid tabulation
CUY-IR 90-19.77/VAR Ramps (MINOR RECONSTRUCTION). Let by Ohio DOT on February 13, 2025, CUY. 6 bids received; low bid $2,587,098 by Anthony Allega Cement Contractor Inc, -20% against the engineer's estimate of $3,244,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 105
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Anthony Allega Cement Contractor Inc | $2,587,098 | Low | -20% |
| 2 | Karvo Companies Inc | $2,762,220 | +7.0% | -15% |
| 3 | Perk Company Inc | $2,995,494 | +16% | -8.0% |
| 4 | Great Lakes Construction Co | $3,500,807 | +35% | +8.0% |
| 5 | Ruhlin Company | $3,878,727 | +50% | +20% |
| 6 | Fabrizi Trucking & Paving Co Inc | $3,886,351 | +50% | +20% |
Engineer's estimate: $3,244,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Anthony Allega Cement Contractor Inc | 2. Karvo Companies Inc | 3. Perk Company Inc | 4. Great Lakes Construction Co | 5. Ruhlin Company | 6. Fabrizi Trucking & Paving Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $51,120 | $20,000 | $15,185 | $4,500.00 | $55,000 | $46,000 |
| 2 | Pavement removed (202E23000) | SY | 13,399 | $8.00 | $17.50 | $20.00 | $22.00 | $21.50 | $40.00 |
| 3 | Walk removed (202E30000) | SF | 362 | $2.30 | $1.50 | $4.65 | $3.50 | $1.75 | $2.00 |
| 4 | Traffic island removed (202E30800) | SY | 176 | $11.83 | $10.00 | $37.80 | $17.00 | $48.00 | $18.00 |
| 5 | Curb removed (202E32000) | FT | 1,734 | $2.40 | $10.00 | $2.75 | $3.50 | $4.50 | $4.00 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 350 | $5.42 | $18.00 | $15.00 | $31.00 | $20.00 | $8.00 |
| 7 | Pipe removed, over 24" diameter (202E35200) | FT | 16 | $39.30 | $39.00 | $82.00 | $140.00 | $109.00 | $15.00 |
| 8 | Guardrail removed (202E38000) | FT | 465.70 | $5.60 | $5.00 | $6.00 | $5.00 | $5.00 | $5.00 |
| 9 | Anchor assembly removed (202E42206) | EACH | 2 | $280.00 | $250.00 | $835.00 | $250.00 | $250.00 | $250.00 |
| 10 | Impact attenuator removed (202E47800) | EACH | 1 | $532.00 | $475.00 | $835.00 | $475.00 | $475.00 | $475.00 |
| 11 | Catch basin removed (202E58100) | EACH | 8 | $860.50 | $900.00 | $755.00 | $1,350.00 | $1,400.00 | $385.00 |
| 12 | Special - pipe cleanout, 24" and under (202E70110) | FT | 1,332 | $14.00 | $6.75 | $29.50 | $22.00 | $24.00 | $42.00 |
| 13 | Special - pipe cleanout, 27" to 48" (202E70120) | FT | 345 | $28.00 | $42.50 | $25.50 | $30.00 | $39.00 | $65.00 |
| 14 | Special - pipe cleanout over 48" (202E70130) | FT | 111 | $56.00 | $42.50 | $40.00 | $37.00 | $73.00 | $130.00 |
| 15 | Excavation (203E10000) | CY | 833 | $37.37 | $35.00 | $40.00 | $55.00 | $74.00 | $32.00 |
| 16 | Embankment (203E20000) | CY | 572 | $23.31 | $40.00 | $35.50 | $16.00 | $74.00 | $14.00 |
| 17 | Subgrade compaction (204E10000) | SY | 13,377 | $0.31 | $0.95 | $1.25 | $2.00 | $2.00 | $3.30 |
| 18 | Excavation of subgrade (204E13000) | CY | 2,189 | $29.06 | $30.25 | $40.00 | $60.00 | $60.00 | $22.00 |
| 19 | Granular material, type B (204E30010) | CY | 2,189 | $64.65 | $68.50 | $62.00 | $70.00 | $70.00 | $68.00 |
| 20 | Proof rolling (204E45000) | HR | 7 | $267.33 | $400.00 | $300.00 | $350.00 | $750.00 | $115.00 |
| 21 | Reshaping under guardrail, as per plan (209E15001) | STA | 5 | $832.58 | $110.00 | $2,450.00 | $110.00 | $650.00 | $225.00 |
| 22 | Linear grading, as per plan (209E60201) | STA | 29 | $861.29 | $1,000.00 | $560.00 | $755.00 | $1,050.00 | $286.00 |
| 23 | Guardrail, type MGS (606E15050) | FT | 437.50 | $23.52 | $21.00 | $21.00 | $21.00 | $21.00 | $21.00 |
| 24 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 1 | $3,192.00 | $2,850.00 | $2,850.00 | $2,850.00 | $2,850.00 | $2,850.00 |
| 25 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,176.00 | $1,050.00 | $1,050.00 | $1,050.00 | $1,050.00 | $2,100.00 |
| 26 | Impact attenuator, type 2 (unidirectional), 45 MPH (606E60022) | EACH | 1 | $24,360 | $21,750 | $21,750 | $21,750 | $21,750 | $21,750 |
| 27 | 6" concrete walk (608E13000) | SF | 163 | $18.32 | $9.55 | $18.85 | $20.00 | $30.00 | $11.00 |
| 28 | Curb ramp (608E52000) | SF | 144 | $19.34 | $9.55 | $37.50 | $22.00 | $37.00 | $32.00 |
| 29 | Detectable warning (608E53020) | SF | 20 | $20.36 | $35.00 | $40.50 | $80.00 | $78.00 | $41.00 |
| 30 | Soil analysis test (659E00100) | EACH | 2 | $448.00 | $400.00 | $500.00 | $400.00 | $400.00 | $225.00 |
| 31 | Topsoil (659E00300) | CY | 455 | $61.60 | $45.00 | $60.00 | $55.00 | $55.00 | $75.00 |
| 32 | Seeding and mulching, class 2 (659E00510) | SY | 4,155 | $1.04 | $0.93 | $2.60 | $0.93 | $0.93 | $7.00 |
| 33 | Repair seeding and mulching (659E14000) | SY | 205 | $2.24 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 34 | Inter-seeding (659E15000) | SY | 205 | $2.24 | $0.01 | $2.00 | $0.10 | $0.60 | $2.00 |
| 35 | Commercial fertilizer (659E20000) | TON | 0.66 | $1,680.00 | $1,500.00 | $1,000.00 | $1,500.00 | $1,500.00 | $850.00 |
| 36 | Lime (659E31000) | ACRE | 0.85 | $1,680.00 | $0.01 | $1,000.00 | $0.11 | $135.00 | $1,050.00 |
| 37 | Water (659E35000) | MGAL | 23 | $112.00 | $0.01 | $50.00 | $0.10 | $5.00 | $10.00 |
| 38 | Ditch erosion protection (670E00700) | SY | 297 | $3.92 | $3.50 | $4.50 | $3.50 | $3.50 | $4.00 |
| 39 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,660.00 | $2,700.00 | $4,500.00 | $4,000.00 | $5,500.00 | $2,600.00 |
| 40 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $13,709 | $8,500.00 | $2,450.00 | $10,500 | $10,200 | $14,000 |
| 41 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,881 | $10,150 | $9,715.00 | $11,000 | $9,713.00 | $7,500.00 |
| 42 | Erosion control (832E30000) | EACH | 54,277 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 43 | 6" shallow pipe underdrains with geotextile fabric (605E11110) | FT | 2,144 | $14.81 | $13.70 | $14.00 | $22.00 | $20.00 | $14.00 |
| 44 | 6" unclassified pipe underdrains with geotextile fabric (605E13410) | FT | 259 | $20.72 | $15.00 | $17.85 | $22.00 | $26.00 | $28.00 |
| 45 | 6" rock cut underdrains with geotextile fabric (605E13510) | FT | 2,349 | $15.88 | $14.65 | $27.20 | $42.00 | $44.00 | $24.00 |
| 46 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 1,321 | $13.84 | $14.30 | $17.85 | $25.00 | $13.50 | $15.00 |
| 47 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 251 | $29.56 | $21.00 | $17.85 | $22.00 | $42.00 | $18.00 |
| 48 | 10" conduit, type C (611E03300) | FT | 8 | $519.02 | $102.00 | $110.00 | $150.00 | $278.00 | $100.00 |
| 49 | 12" conduit, type B (611E04400) | FT | 20 | $612.80 | $131.00 | $122.00 | $150.00 | $387.00 | $190.00 |
| 50 | 12" conduit, type C (611E04600) | FT | 42 | $206.50 | $122.00 | $115.00 | $145.00 | $114.00 | $180.00 |
| 51 | 15" conduit, type B (611E05900) | FT | 250 | $188.34 | $132.00 | $105.00 | $120.00 | $183.00 | $215.00 |
| 52 | 15" conduit, type C (611E06100) | FT | 8 | $528.82 | $155.00 | $120.00 | $170.00 | $257.00 | $200.00 |
| 53 | 18" conduit, type C (611E07600) | FT | 16 | $521.26 | $112.00 | $120.00 | $110.00 | $129.00 | $250.00 |
| 54 | 24" conduit, type C (611E10600) | FT | 8 | $600.92 | $153.00 | $205.00 | $195.00 | $313.00 | $900.00 |
| 55 | 48" conduit, type C (611E21100) | FT | 8 | $885.69 | $466.00 | $425.00 | $1,350.00 | $1,445.00 | $1,170.00 |
| 56 | 38" X 60" conduit, type C, 706.04 (611E53004) | FT | 8 | $1,016.21 | $714.00 | $715.00 | $1,600.00 | $3,190.00 | $1,315.00 |
| 57 | Catch basin, no. 3A (611E98180) | EACH | 1 | $9,450.84 | $3,400.00 | $4,940.00 | $3,900.00 | $7,540.00 | $4,595.00 |
| 58 | Catch basin, no. 5 (611E98300) | EACH | 4 | $7,963.84 | $5,200.00 | $5,915.00 | $5,500.00 | $9,000.00 | $6,590.00 |
| 59 | Catch basin, no. 5A (611E98344) | EACH | 1 | $15,783 | $10,000 | $17,800 | $22,000 | $14,500 | $22,045 |
| 60 | Catch basin, no. 6 (611E98370) | EACH | 1 | $7,187.25 | $3,700.00 | $7,030.00 | $3,900.00 | $12,250 | $6,750.00 |
| 61 | Catch basin grate (611E98644) | EACH | 1 | $1,692.53 | $550.00 | $1,180.00 | $850.00 | $1,650.00 | $950.00 |
| 62 | Catch basin, misc.: city of cleveland CB-1 catch B (611E98690) | EACH | 1 | $5,597.93 | $5,500.00 | $6,295.00 | $5,300.00 | $8,750.00 | $4,735.00 |
| 63 | Inlet, no. 2-6, as per plan (611E98711) | EACH | 4 | $4,023.75 | $4,800.00 | $5,360.00 | $8,500.00 | $13,000 | $7,865.00 |
| 64 | Full depth pavement sawing (255E20000) | FT | 1,201 | $3.36 | $3.50 | $1.80 | $2.00 | $1.80 | $4.00 |
| 65 | Aggregate base (304E20000) | CY | 2,209 | $71.99 | $76.00 | $74.00 | $90.00 | $82.00 | $72.00 |
| 66 | Asphalt concrete intermediate course, type 1, (449), (under guardrail), as per plan (441E70801) | CY | 21 | $661.63 | $420.00 | $850.00 | $750.00 | $907.00 | $825.00 |
| 67 | 6" reinforced concrete pavement, class QC 1P (451E10010) | SY | 5 | $563.51 | $230.00 | $1,095.00 | $565.00 | $865.00 | $160.00 |
| 68 | 10.5" non-reinforced concrete pavement, class QC 1P with QC/QA (452E14022) | SY | 2,125 | $105.31 | $88.50 | $110.60 | $127.00 | $138.00 | $136.00 |
| 69 | 11" non-reinforced concrete pavement, class QC 1P with QC/QA (452E14120) | SY | 9,497 | $83.53 | $92.00 | $100.35 | $132.00 | $152.00 | $128.00 |
| 70 | Curb, type 2-A (609E14000) | FT | 1,728 | $7.24 | $2.75 | $7.65 | $7.00 | $8.50 | $6.00 |
| 71 | 6" concrete traffic island (609E54000) | SY | 176 | $82.46 | $68.50 | $82.50 | $63.00 | $21.00 | $119.00 |
| 72 | RPM (621E00100) | EACH | 193 | $89.45 | $83.76 | $65.00 | $80.00 | $86.60 | $125.00 |
| 73 | Barrier reflector, type 2, one-way (626E00110) | EACH | 6 | $12.32 | $11.00 | $11.00 | $11.00 | $11.00 | $15.00 |
| 74 | Ground mounted support, no. 3 post (630E03100) | FT | 651.50 | $13.44 | $12.50 | $12.00 | $7.50 | $12.50 | $16.50 |
| 75 | One way support, no. 3 post (630E08004) | FT | 88.20 | $15.68 | $15.00 | $14.00 | $12.15 | $15.00 | $16.50 |
| 76 | Sign post reflector (630E08600) | EACH | 44 | $61.60 | $35.00 | $55.00 | $22.00 | $35.00 | $61.00 |
| 77 | Sign support assembly, pole mounted (630E79500) | EACH | 2 | $140.00 | $100.00 | $125.00 | $76.00 | $100.00 | $116.00 |
| 78 | Sign, flat sheet (630E80100) | SF | 379.50 | $15.68 | $25.00 | $14.00 | $13.80 | $25.00 | $20.00 |
| 79 | Ramp reference marker (630E81010) | EACH | 1 | $100.80 | $150.00 | $90.00 | $58.00 | $150.00 | $200.00 |
| 80 | Removal of ground mounted sign and disposal (630E84900) | EACH | 56 | $22.40 | $15.00 | $20.00 | $22.40 | $15.00 | $18.00 |
| 81 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $95.20 | $15.00 | $85.00 | $47.00 | $15.00 | $65.00 |
| 82 | Removal of ground mounted post support and disposal (630E86002) | EACH | 52 | $33.60 | $15.00 | $30.00 | $24.00 | $15.00 | $22.10 |
| 83 | Removal of pole mounted sign and disposal (630E87500) | EACH | 2 | $22.40 | $50.00 | $20.00 | $64.00 | $50.00 | $20.00 |
| 84 | Edge line, 6" (646E10010) | MI | 1.14 | $5,432.00 | $5,500.00 | $4,850.00 | $5,455.00 | $5,500.00 | $5,500.00 |
| 85 | Channelizing line, 12" (646E10310) | FT | 3,273 | $2.80 | $3.50 | $2.50 | $2.65 | $3.50 | $2.75 |
| 86 | Stop line (646E10400) | FT | 145 | $13.44 | $15.00 | $12.00 | $17.05 | $15.00 | $18.00 |
| 87 | Crosswalk line, 12" (646E10510) | FT | 363 | $6.72 | $12.50 | $6.00 | $8.10 | $12.50 | $8.50 |
| 88 | Lane arrow (646E20300) | EACH | 64 | $173.60 | $200.00 | $185.00 | $225.00 | $200.00 | $225.00 |
| 89 | Wrong way arrow (646E20320) | EACH | 4 | $207.20 | $350.00 | $185.00 | $500.00 | $350.00 | $500.00 |
| 90 | Dotted line, 8" (646E20506) | FT | 143 | $5.60 | $2.50 | $5.00 | $2.50 | $2.50 | $2.50 |
| 91 | Pull box, misc.:pull box adjusted to grade (625E31600) | EACH | 5 | $336.00 | $385.00 | $30.00 | $385.00 | $850.00 | $450.00 |
| 92 | Detector loop, as per plan (632E26501) | EACH | 3 | $1,680.00 | $1,850.00 | $1,500.00 | $1,850.00 | $1,075.86 | $1,950.00 |
| 93 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $112.00 | $100.00 | $100.00 | $100.00 | $102.00 | $85.00 |
| 94 | Detour signing (614E12420) | LS | 1 | $20,423 | $15,000 | $15,000 | $20,000 | $15,000 | $26,500 |
| 95 | Portable changeable message sign, as per plan (614E18601) | SNMT | 18 | $896.00 | $800.00 | $1,200.00 | $735.00 | $800.00 | $1,025.00 |
| 96 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.39 | $15,264 | $32,500 | $15,000 | $12,000 | $32,500 | $34,500 |
| 97 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 1,440 | $1.70 | $1.00 | $5.00 | $1.30 | $1.00 | $1.55 |
| 98 | Water (616E10000) | MGAL | 6 | $102.46 | $50.00 | $50.00 | $50.00 | $115.00 | $10.00 |
| 99 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,082 | $15,000 | $35,000 | $20,000 | $20,000 | $18,500 |
| 100 | Maintaining traffic (614E11000) | LS | 1 | $75,000 | $38,000 | $160,000 | $55,000 | $45,000 | $83,600 |
| 101 | Field office, type B, as per plan (619E16011) | MNTH | 12 | $1,445.47 | $3,000.00 | $2,230.00 | $3,750.00 | $3,125.00 | $4,850.00 |
| 102 | Construction layout stakes and surveying (623E10000) | LS | 1 | $50,000 | $31,785 | $30,000 | $34,000 | $21,250 | $52,300 |
| 103 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $7,257.60 | $3,240.00 | $6,500.00 | $1,000.00 | $4,500.00 | $3,200.00 |
| 104 | Post construction survey monument verification and report (623E51000) | LS | 1 | $7,257.60 | $3,000.00 | $6,500.00 | $1,000.00 | $4,500.00 | $3,800.00 |
| 105 | Mobilization (624E10000) | LS | 1 | $100,000 | $249,300 | $90,000 | $175,000 | $174,831 | $298,985 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.