ODOT contract 250084 bid tabulation

CUY-IR 90-19.77/VAR Ramps (MINOR RECONSTRUCTION). Let by Ohio DOT on February 13, 2025, CUY. 6 bids received; low bid $2,587,098 by Anthony Allega Cement Contractor Inc, -20% against the engineer's estimate of $3,244,000.

Owner
Ohio DOT
Letting
13 FEB 2025
Pay items
105
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Anthony Allega Cement Contractor Inc$2,587,098Low-20%
2Karvo Companies Inc$2,762,220+7.0%-15%
3Perk Company Inc$2,995,494+16%-8.0%
4Great Lakes Construction Co$3,500,807+35%+8.0%
5Ruhlin Company$3,878,727+50%+20%
6Fabrizi Trucking & Paving Co Inc$3,886,351+50%+20%
ODOT contract 250084: bids by rank

Engineer's estimate: $3,244,000.

Bid tabulation

LinePay itemUnitQuantity1. Anthony Allega Cement Contractor Inc2. Karvo Companies Inc3. Perk Company Inc4. Great Lakes Construction Co5. Ruhlin Company6. Fabrizi Trucking & Paving Co Inc
1Clearing and grubbing (201E11000)LS1$51,120$20,000$15,185$4,500.00$55,000$46,000
2Pavement removed (202E23000)SY13,399$8.00$17.50$20.00$22.00$21.50$40.00
3Walk removed (202E30000)SF362$2.30$1.50$4.65$3.50$1.75$2.00
4Traffic island removed (202E30800)SY176$11.83$10.00$37.80$17.00$48.00$18.00
5Curb removed (202E32000)FT1,734$2.40$10.00$2.75$3.50$4.50$4.00
6Pipe removed, 24" and under (202E35100)FT350$5.42$18.00$15.00$31.00$20.00$8.00
7Pipe removed, over 24" diameter (202E35200)FT16$39.30$39.00$82.00$140.00$109.00$15.00
8Guardrail removed (202E38000)FT465.70$5.60$5.00$6.00$5.00$5.00$5.00
9Anchor assembly removed (202E42206)EACH2$280.00$250.00$835.00$250.00$250.00$250.00
10Impact attenuator removed (202E47800)EACH1$532.00$475.00$835.00$475.00$475.00$475.00
11Catch basin removed (202E58100)EACH8$860.50$900.00$755.00$1,350.00$1,400.00$385.00
12Special - pipe cleanout, 24" and under (202E70110)FT1,332$14.00$6.75$29.50$22.00$24.00$42.00
13Special - pipe cleanout, 27" to 48" (202E70120)FT345$28.00$42.50$25.50$30.00$39.00$65.00
14Special - pipe cleanout over 48" (202E70130)FT111$56.00$42.50$40.00$37.00$73.00$130.00
15Excavation (203E10000)CY833$37.37$35.00$40.00$55.00$74.00$32.00
16Embankment (203E20000)CY572$23.31$40.00$35.50$16.00$74.00$14.00
17Subgrade compaction (204E10000)SY13,377$0.31$0.95$1.25$2.00$2.00$3.30
18Excavation of subgrade (204E13000)CY2,189$29.06$30.25$40.00$60.00$60.00$22.00
19Granular material, type B (204E30010)CY2,189$64.65$68.50$62.00$70.00$70.00$68.00
20Proof rolling (204E45000)HR7$267.33$400.00$300.00$350.00$750.00$115.00
21Reshaping under guardrail, as per plan (209E15001)STA5$832.58$110.00$2,450.00$110.00$650.00$225.00
22Linear grading, as per plan (209E60201)STA29$861.29$1,000.00$560.00$755.00$1,050.00$286.00
23Guardrail, type MGS (606E15050)FT437.50$23.52$21.00$21.00$21.00$21.00$21.00
24Anchor assembly, MGS type E, MASH 2016 (606E26150)EACH1$3,192.00$2,850.00$2,850.00$2,850.00$2,850.00$2,850.00
25Anchor assembly, MGS type T (606E26550)EACH2$1,176.00$1,050.00$1,050.00$1,050.00$1,050.00$2,100.00
26Impact attenuator, type 2 (unidirectional), 45 MPH (606E60022)EACH1$24,360$21,750$21,750$21,750$21,750$21,750
276" concrete walk (608E13000)SF163$18.32$9.55$18.85$20.00$30.00$11.00
28Curb ramp (608E52000)SF144$19.34$9.55$37.50$22.00$37.00$32.00
29Detectable warning (608E53020)SF20$20.36$35.00$40.50$80.00$78.00$41.00
30Soil analysis test (659E00100)EACH2$448.00$400.00$500.00$400.00$400.00$225.00
31Topsoil (659E00300)CY455$61.60$45.00$60.00$55.00$55.00$75.00
32Seeding and mulching, class 2 (659E00510)SY4,155$1.04$0.93$2.60$0.93$0.93$7.00
33Repair seeding and mulching (659E14000)SY205$2.24$2.00$2.00$2.00$2.00$2.00
34Inter-seeding (659E15000)SY205$2.24$0.01$2.00$0.10$0.60$2.00
35Commercial fertilizer (659E20000)TON0.66$1,680.00$1,500.00$1,000.00$1,500.00$1,500.00$850.00
36Lime (659E31000)ACRE0.85$1,680.00$0.01$1,000.00$0.11$135.00$1,050.00
37Water (659E35000)MGAL23$112.00$0.01$50.00$0.10$5.00$10.00
38Ditch erosion protection (670E00700)SY297$3.92$3.50$4.50$3.50$3.50$4.00
39Storm water pollution prevention plan (832E15000)LS1$2,660.00$2,700.00$4,500.00$4,000.00$5,500.00$2,600.00
40Storm water pollution prevention inspections (832E15002)LS1$13,709$8,500.00$2,450.00$10,500$10,200$14,000
41Storm water pollution prevention inspection software (832E15010)LS1$10,881$10,150$9,715.00$11,000$9,713.00$7,500.00
42Erosion control (832E30000)EACH54,277$1.00$1.00$1.00$1.00$1.00$1.00
436" shallow pipe underdrains with geotextile fabric (605E11110)FT2,144$14.81$13.70$14.00$22.00$20.00$14.00
446" unclassified pipe underdrains with geotextile fabric (605E13410)FT259$20.72$15.00$17.85$22.00$26.00$28.00
456" rock cut underdrains with geotextile fabric (605E13510)FT2,349$15.88$14.65$27.20$42.00$44.00$24.00
466" base pipe underdrains with geotextile fabric (605E14020)FT1,321$13.84$14.30$17.85$25.00$13.50$15.00
476" conduit, type F for underdrain outlets (611E00510)FT251$29.56$21.00$17.85$22.00$42.00$18.00
4810" conduit, type C (611E03300)FT8$519.02$102.00$110.00$150.00$278.00$100.00
4912" conduit, type B (611E04400)FT20$612.80$131.00$122.00$150.00$387.00$190.00
5012" conduit, type C (611E04600)FT42$206.50$122.00$115.00$145.00$114.00$180.00
5115" conduit, type B (611E05900)FT250$188.34$132.00$105.00$120.00$183.00$215.00
5215" conduit, type C (611E06100)FT8$528.82$155.00$120.00$170.00$257.00$200.00
5318" conduit, type C (611E07600)FT16$521.26$112.00$120.00$110.00$129.00$250.00
5424" conduit, type C (611E10600)FT8$600.92$153.00$205.00$195.00$313.00$900.00
5548" conduit, type C (611E21100)FT8$885.69$466.00$425.00$1,350.00$1,445.00$1,170.00
5638" X 60" conduit, type C, 706.04 (611E53004)FT8$1,016.21$714.00$715.00$1,600.00$3,190.00$1,315.00
57Catch basin, no. 3A (611E98180)EACH1$9,450.84$3,400.00$4,940.00$3,900.00$7,540.00$4,595.00
58Catch basin, no. 5 (611E98300)EACH4$7,963.84$5,200.00$5,915.00$5,500.00$9,000.00$6,590.00
59Catch basin, no. 5A (611E98344)EACH1$15,783$10,000$17,800$22,000$14,500$22,045
60Catch basin, no. 6 (611E98370)EACH1$7,187.25$3,700.00$7,030.00$3,900.00$12,250$6,750.00
61Catch basin grate (611E98644)EACH1$1,692.53$550.00$1,180.00$850.00$1,650.00$950.00
62Catch basin, misc.: city of cleveland CB-1 catch B (611E98690)EACH1$5,597.93$5,500.00$6,295.00$5,300.00$8,750.00$4,735.00
63Inlet, no. 2-6, as per plan (611E98711)EACH4$4,023.75$4,800.00$5,360.00$8,500.00$13,000$7,865.00
64Full depth pavement sawing (255E20000)FT1,201$3.36$3.50$1.80$2.00$1.80$4.00
65Aggregate base (304E20000)CY2,209$71.99$76.00$74.00$90.00$82.00$72.00
66Asphalt concrete intermediate course, type 1, (449), (under guardrail), as per plan (441E70801)CY21$661.63$420.00$850.00$750.00$907.00$825.00
676" reinforced concrete pavement, class QC 1P (451E10010)SY5$563.51$230.00$1,095.00$565.00$865.00$160.00
6810.5" non-reinforced concrete pavement, class QC 1P with QC/QA (452E14022)SY2,125$105.31$88.50$110.60$127.00$138.00$136.00
6911" non-reinforced concrete pavement, class QC 1P with QC/QA (452E14120)SY9,497$83.53$92.00$100.35$132.00$152.00$128.00
70Curb, type 2-A (609E14000)FT1,728$7.24$2.75$7.65$7.00$8.50$6.00
716" concrete traffic island (609E54000)SY176$82.46$68.50$82.50$63.00$21.00$119.00
72RPM (621E00100)EACH193$89.45$83.76$65.00$80.00$86.60$125.00
73Barrier reflector, type 2, one-way (626E00110)EACH6$12.32$11.00$11.00$11.00$11.00$15.00
74Ground mounted support, no. 3 post (630E03100)FT651.50$13.44$12.50$12.00$7.50$12.50$16.50
75One way support, no. 3 post (630E08004)FT88.20$15.68$15.00$14.00$12.15$15.00$16.50
76Sign post reflector (630E08600)EACH44$61.60$35.00$55.00$22.00$35.00$61.00
77Sign support assembly, pole mounted (630E79500)EACH2$140.00$100.00$125.00$76.00$100.00$116.00
78Sign, flat sheet (630E80100)SF379.50$15.68$25.00$14.00$13.80$25.00$20.00
79Ramp reference marker (630E81010)EACH1$100.80$150.00$90.00$58.00$150.00$200.00
80Removal of ground mounted sign and disposal (630E84900)EACH56$22.40$15.00$20.00$22.40$15.00$18.00
81Removal of ground mounted sign and reerection (630E85100)EACH1$95.20$15.00$85.00$47.00$15.00$65.00
82Removal of ground mounted post support and disposal (630E86002)EACH52$33.60$15.00$30.00$24.00$15.00$22.10
83Removal of pole mounted sign and disposal (630E87500)EACH2$22.40$50.00$20.00$64.00$50.00$20.00
84Edge line, 6" (646E10010)MI1.14$5,432.00$5,500.00$4,850.00$5,455.00$5,500.00$5,500.00
85Channelizing line, 12" (646E10310)FT3,273$2.80$3.50$2.50$2.65$3.50$2.75
86Stop line (646E10400)FT145$13.44$15.00$12.00$17.05$15.00$18.00
87Crosswalk line, 12" (646E10510)FT363$6.72$12.50$6.00$8.10$12.50$8.50
88Lane arrow (646E20300)EACH64$173.60$200.00$185.00$225.00$200.00$225.00
89Wrong way arrow (646E20320)EACH4$207.20$350.00$185.00$500.00$350.00$500.00
90Dotted line, 8" (646E20506)FT143$5.60$2.50$5.00$2.50$2.50$2.50
91Pull box, misc.:pull box adjusted to grade (625E31600)EACH5$336.00$385.00$30.00$385.00$850.00$450.00
92Detector loop, as per plan (632E26501)EACH3$1,680.00$1,850.00$1,500.00$1,850.00$1,075.86$1,950.00
93Law enforcement officer with patrol car for assistance (614E11110)HR100$112.00$100.00$100.00$100.00$102.00$85.00
94Detour signing (614E12420)LS1$20,423$15,000$15,000$20,000$15,000$26,500
95Portable changeable message sign, as per plan (614E18601)SNMT18$896.00$800.00$1,200.00$735.00$800.00$1,025.00
96Work zone edge line, class I, 6", 740.06, type I (614E22210)MI0.39$15,264$32,500$15,000$12,000$32,500$34,500
97Work zone dotted line, class I, 6", 740.06, type I (614E24402)FT1,440$1.70$1.00$5.00$1.30$1.00$1.55
98Water (616E10000)MGAL6$102.46$50.00$50.00$50.00$115.00$10.00
99Premium for contract performance bond and for payment bond (103E05000)LS1$12,082$15,000$35,000$20,000$20,000$18,500
100Maintaining traffic (614E11000)LS1$75,000$38,000$160,000$55,000$45,000$83,600
101Field office, type B, as per plan (619E16011)MNTH12$1,445.47$3,000.00$2,230.00$3,750.00$3,125.00$4,850.00
102Construction layout stakes and surveying (623E10000)LS1$50,000$31,785$30,000$34,000$21,250$52,300
103Preconstruction survey monument verification and report (623E50000)LS1$7,257.60$3,240.00$6,500.00$1,000.00$4,500.00$3,200.00
104Post construction survey monument verification and report (623E51000)LS1$7,257.60$3,000.00$6,500.00$1,000.00$4,500.00$3,800.00
105Mobilization (624E10000)LS1$100,000$249,300$90,000$175,000$174,831$298,985
ODOT contract 250084: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way