ODOT contract 250095 bid tabulation
MAH-US 422/SR 616-07.58/03.81 (FOUR LANE RESURFACING). Let by Ohio DOT on February 13, 2025, MAH. 3 bids received; low bid $2,069,999 by Shelly & Sands Inc, -12% against the engineer's estimate of $2,349,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 125
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $2,069,999 | Low | -12% |
| 2 | Karvo Companies Inc | $2,448,277 | +18% | +4.0% |
| 3 | Shelly Company | $2,740,888 | +32% | +17% |
Engineer's estimate: $2,349,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Karvo Companies Inc | 3. Shelly Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,000.00 | $7,000.00 | $7,000.00 |
| 2 | Pavement removed (202E23000) | SY | 587 | $15.00 | $31.75 | $31.75 |
| 3 | Wearing course removed (202E23500) | SY | 120 | $19.00 | $4.00 | $40.00 |
| 4 | Walk removed (202E30000) | SF | 524 | $12.50 | $15.00 | $6.75 |
| 5 | Curb removed (202E32000) | FT | 60 | $25.00 | $25.00 | $7.50 |
| 6 | Curb and gutter removed (202E32500) | FT | 2,000 | $9.00 | $12.00 | $12.75 |
| 7 | Gutter removed (202E32700) | SY | 190 | $22.63 | $12.00 | $31.33 |
| 8 | Pipe removed, 24" and under (202E35100) | FT | 24 | $20.00 | $15.00 | $15.00 |
| 9 | Guardrail removed (202E38000) | FT | 533 | $2.00 | $7.00 | $2.00 |
| 10 | Removal misc.: inspection well (202E98100) | EACH | 1 | $520.00 | $200.00 | $200.00 |
| 11 | Removal misc.: conduit (202E98200) | FT | 10 | $20.00 | $15.00 | $15.00 |
| 12 | Excavation (203E10000) | CY | 167 | $20.00 | $40.00 | $40.00 |
| 13 | Excavation (203E10000) | CY | 34 | $74.00 | $25.00 | $50.00 |
| 14 | Excavation (203E10000) | CY | 3 | $150.00 | $25.00 | $25.00 |
| 15 | Embankment (203E20000) | CY | 423 | $27.55 | $42.00 | $42.00 |
| 16 | Embankment, as per plan (203E20001) | CY | 3 | $95.25 | $50.00 | $50.00 |
| 17 | Subgrade compaction (204E10000) | SY | 813 | $4.00 | $3.75 | $3.75 |
| 18 | Linear grading (209E60200) | STA | 38 | $130.00 | $190.00 | $100.00 |
| 19 | Guardrail, type MGS (606E15050) | FT | 406.25 | $23.20 | $23.00 | $23.20 |
| 20 | Anchor assembly, MGS type B (606E26050) | EACH | 2 | $2,580.00 | $2,575.00 | $2,580.00 |
| 21 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 1 | $2,960.00 | $2,650.00 | $2,960.00 |
| 22 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,495.00 | $1,375.00 | $1,495.00 |
| 23 | 4" concrete walk (608E10000) | SF | 483 | $9.50 | $15.00 | $25.00 |
| 24 | Curb ramp (608E52000) | SF | 240 | $22.00 | $25.00 | $27.00 |
| 25 | Monument assembly adjusted to grade (623E39500) | EACH | 8 | $120.00 | $1,750.00 | $1,600.00 |
| 26 | Special - as-built construction plans (690E91000) | LS | 1 | $3,000.00 | $1,000.00 | $10,000 |
| 27 | Special - survey control verification (690E98400) | LS | 1 | $3,000.00 | $5,000.00 | $3,500.00 |
| 28 | Rock channel protection, type C with filter (601E32200) | CY | 3 | $514.00 | $195.00 | $450.00 |
| 29 | Seeding and mulching (659E10000) | SY | 1,127 | $3.00 | $5.00 | $5.00 |
| 30 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 |
| 31 | 6" conduit, type B (611E00900) | FT | 30 | $14.50 | $10.00 | $10.00 |
| 32 | 6" conduit, type E (611E01400) | FT | 30 | $12.00 | $10.00 | $10.00 |
| 33 | 6" conduit, type F (611E01500) | FT | 30 | $13.00 | $10.00 | $10.00 |
| 34 | 12" conduit, type B (611E04400) | FT | 37 | $227.00 | $265.00 | $265.00 |
| 35 | Conduit, misc.: type B for drainage discharge cont (611E97400) | FT | 10 | $37.00 | $10.00 | $10.00 |
| 36 | Conduit, misc.: type C for drainage discharge cont (611E97400) | FT | 10 | $37.00 | $10.00 | $10.00 |
| 37 | Conduit, misc.: type E for drainage discharge cont (611E97400) | FT | 10 | $37.00 | $10.00 | $10.00 |
| 38 | Conduit, misc.: type F for drainage discharge cont (611E97400) | FT | 10 | $37.00 | $10.00 | $10.00 |
| 39 | Catch basin adjusted to grade (611E98630) | EACH | 6 | $1,500.00 | $1,500.00 | $1,500.00 |
| 40 | Catch basin reconstructed to grade (611E98634) | EACH | 2 | $2,000.00 | $2,000.00 | $2,000.00 |
| 41 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 2 | $2,200.00 | $2,200.00 | $2,200.00 |
| 42 | Inspection well (611E99720) | EACH | 1 | $2,000.00 | $1,000.00 | $3,500.00 |
| 43 | Special - miscellaneous metal (611E99820) | LB | 2,400 | $3.00 | $3.00 | $3.00 |
| 44 | Partial depth pavement repair (441) (251E01000) | SY | 800 | $45.00 | $40.00 | $80.00 |
| 45 | Pavement repair (253E01000) | SY | 400 | $96.00 | $135.00 | $175.00 |
| 46 | Pavement planing, asphalt concrete (T=1.5") (254E01000) | SY | 87,167 | $0.80 | $1.50 | $1.50 |
| 47 | Full depth pavement removal and rigid replacement, type 2, class QC1 (255E12000) | SY | 200 | $250.00 | $175.00 | $285.00 |
| 48 | Aggregate base (304E20000) | CY | 100 | $85.00 | $145.00 | $145.00 |
| 49 | Aggregate base (304E20000) | CY | 34 | $65.00 | $25.00 | $60.00 |
| 50 | 9" concrete base, class QC 1P (305E13010) | SY | 587 | $87.00 | $92.00 | $92.00 |
| 51 | Non-tracking tack coat (407E20000) | GAL | 7,876 | $3.05 | $2.75 | $2.50 |
| 52 | Prime coat, as per plan (408E10001) | GAL | 667 | $3.50 | $5.00 | $5.00 |
| 53 | Stabilized crushed aggregate (411E10000) | CY | 19 | $124.00 | $25.00 | $125.00 |
| 54 | Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100) | CY | 3,637 | $186.00 | $220.00 | $212.00 |
| 55 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 58 | $300.00 | $275.00 | $485.00 |
| 57 | Combination curb and gutter, type 3, as per plan (609E18001) | FT | 2,220 | $55.00 | $75.00 | $118.00 |
| 58 | Curb, type 6 (609E26000) | FT | 30 | $35.00 | $60.00 | $50.00 |
| 59 | Compacted aggregate, as per plan (617E10101) | CY | 70 | $105.00 | $75.00 | $125.00 |
| 60 | Valve box adjusted to grade (638E10800) | EACH | 3 | $200.00 | $2,000.00 | $1,600.00 |
| 61 | RPM (621E00100) | EACH | 586 | $46.00 | $40.00 | $41.50 |
| 62 | Raised pavement marker removed (621E54000) | EACH | 469 | $5.00 | $1.00 | $4.00 |
| 63 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 10 | $12.40 | $11.00 | $12.40 |
| 64 | Edge line, 6" (646E10010) | MI | 6.40 | $2,800.00 | $2,800.00 | $2,800.00 |
| 65 | Lane line, 6" (646E10110) | MI | 5.12 | $1,250.00 | $1,250.00 | $1,250.00 |
| 66 | Center line (646E10200) | MI | 3.20 | $3,970.00 | $3,970.00 | $3,970.00 |
| 67 | Channelizing line, 12" (646E10310) | FT | 580 | $1.65 | $1.65 | $1.65 |
| 68 | Stop line (646E10400) | FT | 118 | $12.50 | $12.50 | $12.50 |
| 69 | Crosswalk line, 24" (646E10520) | FT | 161 | $12.50 | $12.50 | $12.50 |
| 70 | Lane arrow (646E20300) | EACH | 14 | $175.00 | $175.00 | $175.00 |
| 71 | Detector loop, as per plan (632E26501) | EACH | 6 | $3,000.00 | $3,000.00 | $1,350.00 |
| 72 | Traffic compacted surface, type A or B (410E12000) | CY | 9 | $245.00 | $25.00 | $20.00 |
| 73 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $90.00 | $100.00 | $100.00 |
| 74 | Special - work zone traffic signal (614E11300) | EACH | 5 | $8,000.00 | $8,000.00 | $8,000.00 |
| 75 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 4 | $2,680.00 | $3,500.00 | $3,500.00 |
| 76 | Work zone marking sign (614E12460) | EACH | 6 | $85.00 | $85.00 | $85.00 |
| 77 | Asphalt concrete for maintaining traffic (614E13000) | CY | 5 | $300.00 | $200.00 | $120.00 |
| 78 | Barrier reflector, type 1, BI-directional (614E13310) | EACH | 16 | $7.50 | $7.50 | $7.50 |
| 79 | Barrier reflector, type 2, BI-directional (614E13312) | EACH | 12 | $8.50 | $8.50 | $8.50 |
| 80 | Object marker, two way (614E13360) | EACH | 28 | $17.50 | $17.50 | $17.50 |
| 81 | Portable changeable message sign, as per plan (614E18601) | SNMT | 16 | $800.00 | $800.00 | $800.00 |
| 82 | Work zone lane line, class I, 6" (614E20010) | MI | 5.12 | $750.00 | $750.00 | $750.00 |
| 83 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 1.02 | $750.00 | $750.00 | $950.00 |
| 84 | Work zone lane line, class I, 6", 740.06, type I (614E20210) | MI | 0.12 | $3,250.00 | $3,250.00 | $12,000 |
| 85 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 5.16 | $750.00 | $750.00 | $750.00 |
| 86 | Work zone center line, class I (614E21000) | MI | 3.20 | $1,250.00 | $1,250.00 | $950.00 |
| 87 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.50 | $1,250.00 | $1,250.00 | $2,000.00 |
| 88 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.47 | $17,750 | $17,750 | $12,000 |
| 89 | Work zone center line, class III, 642 paint (614E21550) | MI | 3.22 | $1,250.00 | $1,250.00 | $950.00 |
| 90 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.83 | $850.00 | $850.00 | $900.00 |
| 91 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 1.46 | $10,000 | $10,000 | $6,000.00 |
| 92 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 6.40 | $850.00 | $850.00 | $750.00 |
| 93 | Work zone channelizing line, class I, 12" (614E23010) | FT | 580 | $0.85 | $0.85 | $2.00 |
| 94 | Work zone channelizing line, class I, 12", 740.06, type I (614E23410) | FT | 1,120 | $5.75 | $5.75 | $7.00 |
| 95 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 580 | $0.85 | $0.85 | $2.00 |
| 96 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 2,640 | $1.00 | $1.00 | $3.00 |
| 97 | Work zone stop line, class I (614E26000) | FT | 166 | $3.50 | $3.50 | $5.00 |
| 98 | Work zone stop line, class III, 642 paint (614E26610) | FT | 118 | $3.50 | $3.50 | $5.00 |
| 99 | Roads for maintaining traffic (615E10000) | LS | 1 | $2,000.00 | $1,000.00 | $5,500.00 |
| 100 | Pavement for maintaining traffic, class B (615E25000) | SY | 30 | $86.00 | $100.00 | $660.00 |
| 101 | Portable barrier, unanchored (622E41100) | FT | 700 | $16.00 | $26.50 | $26.50 |
| 102 | Structure removed, as per plan (202E11001) | LS | 1 | $19,000 | $72,000 | $72,000 |
| 103 | Excavation (203E10000) | CY | 87 | $35.00 | $30.00 | $30.00 |
| 104 | Granular material, type B (203E35110) | CY | 87 | $79.00 | $50.00 | $50.00 |
| 105 | Geotextile fabric (204E50000) | SY | 174 | $3.75 | $5.00 | $5.00 |
| 106 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $44,700 | $25,000 | $25,000 |
| 107 | Unclassified excavation (503E21300) | LS | 1 | $2,325.00 | $8,750.00 | $8,750.00 |
| 108 | Epoxy coated steel reinforcement (509E10000) | LB | 3,534 | $2.75 | $3.00 | $3.00 |
| 109 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 9 | $4,480.00 | $3,400.00 | $3,400.00 |
| 110 | Class QC1 concrete, footing (511E46510) | CY | 15 | $1,605.00 | $1,825.00 | $1,825.00 |
| 111 | Class QC1 concrete, headwall (511E46610) | CY | 1 | $1,920.00 | $3,000.00 | $3,000.00 |
| 112 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 49 | $50.00 | $60.00 | $60.00 |
| 113 | Type 2 waterproofing (512E33000) | SY | 176 | $28.00 | $50.00 | $50.00 |
| 114 | 1" preformed expansion joint filler (516E13600) | SF | 15 | $0.25 | $20.00 | $20.00 |
| 115 | Porous backfill with geotextile fabric (518E21200) | CY | 5 | $600.00 | $200.00 | $200.00 |
| 116 | Rock channel protection, type B with aggregate filter (601E32110) | CY | 23 | $255.00 | $125.00 | $125.00 |
| 117 | 12' X 4' conduit, type A, 706.05, as per plan (des (611E95601) | FT | 98 | $1,857.00 | $1,560.00 | $1,460.00 |
| 118 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,000.00 | $10,000 | $15,000 |
| 119 | Maintaining traffic (614E11000) | LS | 1 | $86,395 | $139,963 | $276,500 |
| 120 | Field office, type B (619E16010) | MNTH | 6 | $3,000.00 | $2,500.00 | $3,000.00 |
| 121 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,000 | $11,334 | $15,000 |
| 122 | Mobilization (624E10000) | LS | 1 | $90,000 | $130,000 | $100,000 |
| 200 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $245.00 | $265.00 | $245.00 |
| 201 | Excavation (203E10000) | CY | 6 | $70.00 | $25.00 | $500.00 |
| 202 | Embankment (203E20000) | CY | 6 | $40.50 | $25.00 | $500.00 |
| 203 | Business entrance sign, as per plan (614E40051) | EACH | 1 | $400.00 | $175.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.