ODOT contract 260187 bid tabulation
WYA-Carey SRTS Phase 2 (SIDEWALK). Let by Ohio DOT on April 9, 2026, WYA. 6 bids received; low bid $262,074 by Smith Paving & Excavating Inc, -14% against the engineer's estimate of $306,000.
- Owner
- Ohio DOT
- Letting
- 09 APR 2026
- Pay items
- 50
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Smith Paving & Excavating Inc | $262,074 | Low | -14% |
| 2 | R M H Concrete & Foundations Inc | $269,766 | +3.0% | -12% |
| 3 | D L Smith Concrete LLC | $290,883 | +11% | -5.0% |
| 4 | Fenson Contracting LLC | $344,718 | +32% | +13% |
| 5 | Crawford Construction Company Inc | $366,080 | +40% | +20% |
| 6 | Madex Construction Co | $579,757 | +121% | +89% |
Engineer's estimate: $306,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Smith Paving & Excavating Inc | 2. R M H Concrete & Foundations Inc | 3. D L Smith Concrete LLC | 4. Fenson Contracting LLC | 5. Crawford Construction Company Inc | 6. Madex Construction Co |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,800.00 | $2,500.00 | $2,500.00 | $4,500.00 | $2,200.00 | $3,118.70 |
| 2 | Pavement removed (202E23000) | SY | 411 | $20.00 | $13.50 | $18.00 | $32.00 | $14.50 | $44.75 |
| 3 | Walk removed (202E30000) | SF | 37 | $10.00 | $2.50 | $2.00 | $9.50 | $10.00 | $23.01 |
| 4 | Excavation (203E10000) | CY | 124 | $75.00 | $70.00 | $40.00 | $88.00 | $93.00 | $83.02 |
| 5 | Embankment (203E20000) | CY | 8 | $65.00 | $78.00 | $60.00 | $18.00 | $140.00 | $70.53 |
| 6 | 4" concrete walk, as per plan (608E10001) | SF | 9,758 | $7.00 | $6.50 | $9.50 | $7.75 | $10.70 | $12.55 |
| 7 | Curb ramp, as per plan (608E52001) | SF | 929 | $7.00 | $16.80 | $18.00 | $34.00 | $27.00 | $45.16 |
| 8 | Special - mailbox removed and reset (690E50350) | EACH | 4 | $150.00 | $375.00 | $245.00 | $240.00 | $490.00 | $289.47 |
| 9 | Commercial fertilizer (654E11000) | TON | 0.20 | $1,500.00 | $1,355.00 | $1,000.00 | $750.00 | $708.00 | $2,315.80 |
| 10 | Topsoil (659E00300) | CY | 163 | $70.00 | $81.00 | $60.00 | $78.00 | $62.00 | $75.26 |
| 11 | Seeding and mulching, class 1 (659E00500) | SY | 1,464 | $2.65 | $3.95 | $3.00 | $4.00 | $5.00 | $9.26 |
| 12 | Repair seeding and mulching (659E14000) | SY | 74 | $5.00 | $8.90 | $10.00 | $1.00 | $1.00 | $5.79 |
| 13 | Inter-seeding (659E15000) | SY | 74 | $5.00 | $8.50 | $10.00 | $0.50 | $1.00 | $1.16 |
| 14 | Lime (659E31000) | ACRE | 0.30 | $500.00 | $2,300.00 | $200.00 | $1.00 | $780.00 | $1,157.90 |
| 15 | Water (659E35000) | MGAL | 8.10 | $20.00 | $100.00 | $1.00 | $1.00 | $3.75 | $28.95 |
| 16 | Curb removed (202E32000) | FT | 87 | $15.00 | $8.50 | $10.00 | $15.00 | $51.00 | $33.67 |
| 17 | Curb and gutter removed (202E32500) | FT | 84 | $15.00 | $9.00 | $10.00 | $15.00 | $80.00 | $40.32 |
| 18 | Pipe removed, 24" and under (202E35100) | FT | 49 | $35.00 | $15.00 | $20.00 | $13.00 | $16.00 | $42.62 |
| 19 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 94 | $47.00 | $45.00 | $52.00 | $75.00 | $90.00 | $121.58 |
| 20 | Curb, type 6, as per plan (609E26001) | FT | 77 | $37.00 | $35.00 | $20.00 | $62.00 | $100.00 | $98.42 |
| 21 | 4" conduit, type B (611E00100) | FT | 615 | $40.00 | $27.50 | $20.00 | $26.00 | $34.00 | $68.73 |
| 22 | 4" conduit, type B, as per plan (611E00101) | FT | 50 | $30.00 | $29.00 | $30.00 | $17.00 | $25.00 | $57.89 |
| 23 | 6" conduit, type B, as per plan (611E00901) | FT | 50 | $35.00 | $30.00 | $60.00 | $19.00 | $25.00 | $86.84 |
| 24 | 8" conduit, type B, as per plan (611E01801) | FT | 50 | $40.00 | $37.00 | $65.00 | $23.00 | $25.00 | $115.79 |
| 25 | 10" conduit, type B (611E03100) | FT | 10 | $80.00 | $70.00 | $100.00 | $110.00 | $150.00 | $231.58 |
| 26 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $4,800.00 | $3,500.00 | $8,500.00 | $2,900.00 | $3,600.00 | $2,952.63 |
| 27 | Drainage structure, misc.:storm cleanout (611E99900) | EACH | 6 | $300.00 | $1,400.00 | $1,500.00 | $415.00 | $200.00 | $578.95 |
| 28 | Aggregate base (304E20000) | CY | 23 | $95.00 | $89.00 | $110.00 | $235.00 | $226.00 | $255.10 |
| 29 | Non-tracking tack coat (407E20000) | GAL | 7 | $50.00 | $8.00 | $8.00 | $5.00 | $15.00 | $70.53 |
| 30 | Stabilized crushed aggregate (411E10000) | CY | 126 | $95.00 | $75.00 | $65.00 | $98.00 | $153.00 | $239.91 |
| 31 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 2 | $700.00 | $1,050.00 | $1,450.00 | $800.00 | $1,000.00 | $5,789.47 |
| 32 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 3 | $700.00 | $1,050.00 | $1,450.00 | $800.00 | $1,000.00 | $6,368.42 |
| 33 | Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700) | CY | 5 | $650.00 | $750.00 | $1,200.00 | $600.00 | $1,000.00 | $5,789.47 |
| 34 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 313 | $79.00 | $80.00 | $95.00 | $125.00 | $144.00 | $156.32 |
| 35 | Low strength mortar backfill (613E41200) | CY | 5 | $250.00 | $325.00 | $225.00 | $465.00 | $400.00 | $289.47 |
| 36 | Valve box adjusted to grade (638E10800) | EACH | 3 | $250.00 | $400.00 | $145.00 | $360.00 | $375.00 | $752.63 |
| 37 | Meter and chamber removed and reset (638E11100) | EACH | 5 | $400.00 | $950.00 | $425.00 | $1,800.00 | $1,000.00 | $1,157.89 |
| 38 | Sign post reflector (630E08600) | EACH | 3 | $50.00 | $79.00 | $85.00 | $60.00 | $60.00 | $173.68 |
| 39 | Removal of ground mounted sign and reerection (630E85100) | EACH | 11 | $75.00 | $115.00 | $85.00 | $90.00 | $87.00 | $173.68 |
| 40 | Removal of ground mounted post support and reerection (630E86010) | EACH | 6 | $11.00 | $215.00 | $15.00 | $14.00 | $13.00 | $260.53 |
| 41 | Stop line (644E00500) | FT | 33 | $11.00 | $13.00 | $12.00 | $14.00 | $23.00 | $17.37 |
| 42 | Crosswalk line, 12" (644E00620) | FT | 134 | $5.00 | $7.50 | $7.00 | $6.00 | $8.30 | $16.21 |
| 43 | Crosswalk line, 24" (644E00630) | FT | 260 | $11.00 | $13.00 | $12.00 | $12.75 | $14.00 | $20.84 |
| 44 | Maintaining traffic (614E11000) | LS | 1 | $5,000.00 | $4,000.00 | $3,500.00 | $25,000 | $4,100.00 | $10,113 |
| 45 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,000.00 | $3,500.00 | $5,500.00 | $7,500.00 | $3,900.00 | $12,505 |
| 46 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $5,000.00 | $17,500 | $6,000.00 | $10,500 | $4,700.00 | $11,579 |
| 47 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,300.00 | $3,000.00 | $1,000.00 | $2,520.00 | $1,400.00 | $8,684.21 |
| 48 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,300.00 | $3,000.00 | $1,800.00 | $2,520.00 | $1,400.00 | $5,789.47 |
| 49 | Mobilization (624E10000) | LS | 1 | $18,500 | $6,500.00 | $12,500 | $10,000 | $18,400 | $38,656 |
| 100 | Erosion control (832E30000) | EACH | 8,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.