ODOT contract 264008 bid tabulation
PUT-SR 190-05.71 (CULVERT REPLACEMENT). Let by Ohio DOT on April 9, 2026, PUT. 3 bids received; low bid $598,999 by Fenson Contracting LLC, -38% against the engineer's estimate of $970,000.
- Owner
- Ohio DOT
- Letting
- 09 APR 2026
- Pay items
- 80
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fenson Contracting LLC | $598,999 | Low | -38% |
| 2 | Sand Ridge Excavating | $838,452 | +40% | -14% |
| 3 | Vernon Nagel Inc | $839,265 | +40% | -13% |
Engineer's estimate: $970,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fenson Contracting LLC | 2. Sand Ridge Excavating | 3. Vernon Nagel Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $8,500.00 | $2,000.00 | $5,000.00 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $475.00 | $2,000.00 | $250.00 |
| 3 | Pavement removed (202E23000) | SY | 2,324 | $5.75 | $6.00 | $20.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 554 | $7.50 | $30.00 | $24.00 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 32 | $54.00 | $70.00 | $100.00 |
| 6 | Excavation (203E10000) | CY | 516 | $16.00 | $8.00 | $25.00 |
| 7 | Embankment (203E20000) | CY | 3,164 | $16.00 | $18.65 | $33.00 |
| 8 | Subgrade compaction (204E10000) | SY | 2,664 | $1.25 | $4.00 | $1.00 |
| 9 | Excavation of subgrade (204E13000) | CY | 221 | $5.00 | $8.00 | $30.00 |
| 10 | Granular material, type C (204E30020) | CY | 221 | $35.00 | $118.29 | $50.00 |
| 11 | Proof rolling (204E45000) | HR | 1 | $100.00 | $200.00 | $300.00 |
| 12 | Geotextile fabric (204E50000) | SY | 662 | $2.00 | $2.60 | $2.00 |
| 13 | Right-of-way monument, type B (623E40520) | EACH | 8 | $350.00 | $661.50 | $450.00 |
| 14 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,000.00 | $5,292.00 | $2,000.00 |
| 15 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,000.00 | $5,292.00 | $500.00 |
| 16 | Special - mailbox support system, single (690E50100) | EACH | 1 | $300.00 | $413.00 | $295.00 |
| 17 | Special - mailbox support system, double (690E50200) | EACH | 1 | $365.00 | $588.00 | $420.00 |
| 18 | Special - mailbox removed and reset (690E50350) | EACH | 3 | $95.00 | $483.00 | $345.00 |
| 19 | Rock channel protection, type B with filter (601E32100) | CY | 165 | $77.00 | $114.51 | $150.00 |
| 20 | Rock channel protection, type C with filter (601E32200) | CY | 2 | $175.00 | $857.44 | $150.00 |
| 21 | Topsoil (659E00300) | CY | 450 | $28.00 | $25.00 | $50.00 |
| 22 | Seeding and mulching (659E10000) | SY | 4,042 | $3.30 | $5.04 | $1.10 |
| 23 | Commercial fertilizer (659E20000) | TON | 0.55 | $850.00 | $870.00 | $850.00 |
| 24 | Lime (659E31000) | ACRE | 0.84 | $35.00 | $60.00 | $35.00 |
| 25 | Water (659E35000) | MGAL | 22 | $1.00 | $1.00 | $1.00 |
| 26 | Slope erosion protection (670E00500) | SY | 1,052 | $1.80 | $3.92 | $1.80 |
| 27 | Storm water pollution prevention plan (832E15000) | LS | 1 | $1,000.00 | $1,295.00 | $3,100.00 |
| 28 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,000.00 | $8,372.00 | $3,000.00 |
| 29 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,275 | $14,245 | $9,000.00 |
| 30 | Erosion control (832E30000) | EACH | 17,000 | $1.00 | $1.00 | $1.00 |
| 31 | Concrete masonry (602E20000) | CY | 1 | $3,750.00 | $265.00 | $3,000.00 |
| 32 | Aggregate drains (605E31100) | FT | 181 | $22.50 | $30.00 | $20.00 |
| 33 | 4" conduit, type C (611E00200) | FT | 27 | $16.00 | $33.62 | $33.00 |
| 34 | 4" conduit, type E (611E00400) | FT | 97 | $14.25 | $22.73 | $33.00 |
| 35 | 4" conduit, type F (611E00406) | FT | 10 | $36.25 | $22.22 | $33.00 |
| 36 | 6" conduit, type E (611E01400) | FT | 24 | $19.00 | $27.13 | $53.00 |
| 37 | 6" conduit, type F (611E01500) | FT | 10 | $24.75 | $31.96 | $40.00 |
| 38 | 8" conduit, type C (611E02000) | FT | 51 | $30.75 | $43.90 | $60.00 |
| 39 | 8" conduit, type E (611E02500) | FT | 10 | $25.00 | $47.78 | $42.00 |
| 40 | 12" conduit, type B (611E04400) | FT | 10 | $35.50 | $64.00 | $110.00 |
| 41 | 12" conduit, type C (611E04600) | FT | 779 | $35.75 | $44.97 | $55.00 |
| 42 | 15" conduit, type C (611E06100) | FT | 148 | $70.00 | $61.38 | $70.00 |
| 43 | 21" conduit, type C (611E09100) | FT | 10 | $165.00 | $153.22 | $70.00 |
| 44 | 24" conduit, type C (611E10600) | FT | 146 | $59.00 | $76.26 | $125.00 |
| 45 | 60" conduit, type A, 706.02 (611E23600) | FT | 80 | $410.00 | $694.54 | $500.00 |
| 46 | Catch basin, no. 7 (611E98390) | EACH | 3 | $1,950.00 | $3,187.86 | $5,000.00 |
| 47 | Manhole, no. 3 (611E99574) | EACH | 3 | $4,225.00 | $3,976.00 | $7,500.00 |
| 48 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 442 | $191.00 | $266.00 | $216.72 |
| 49 | Asphalt concrete base, PG64-22, (449), (driveways) (301E56100) | CY | 9 | $257.00 | $357.00 | $350.00 |
| 50 | Aggregate base (304E20000) | CY | 488 | $54.00 | $118.29 | $75.00 |
| 51 | Non-tracking tack coat (407E20000) | GAL | 407 | $3.00 | $4.20 | $2.50 |
| 52 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 184 | $244.00 | $338.80 | $260.00 |
| 53 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 3 | $480.00 | $665.00 | $850.00 |
| 54 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 118 | $93.00 | $70.12 | $100.00 |
| 55 | RPM (621E00100) | EACH | 10 | $80.00 | $644.00 | $460.00 |
| 56 | Raised pavement marker removed (621E54000) | EACH | 9 | $10.00 | $30.00 | $50.00 |
| 57 | Ground mounted support, no. 3 post (630E03100) | FT | 8 | $40.00 | $77.00 | $55.00 |
| 58 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $100.00 | $168.00 | $120.00 |
| 59 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $35.00 | $35.00 | $25.00 |
| 60 | Removal of ground mounted post support and reerection (630E86010) | EACH | 1 | $250.00 | $273.00 | $195.00 |
| 61 | Edge line, 6", type 1 (642E00104) | MI | 0.28 | $3,600.00 | $5,600.00 | $4,000.00 |
| 62 | Center line, type 1 (642E00300) | MI | 0.14 | $6,000.00 | $8,400.00 | $6,000.00 |
| 63 | Pavement repair (253E02000) | CY | 20 | $353.00 | $350.00 | $400.00 |
| 64 | Non-tracking tack coat (407E20000) | GAL | 20 | $5.00 | $5.00 | $2.50 |
| 65 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 10 | $303.00 | $300.00 | $800.00 |
| 66 | Water (616E10000) | MGAL | 8 | $54.00 | $1.00 | $10.00 |
| 67 | Compacted aggregate (617E10100) | CY | 50 | $62.00 | $125.00 | $100.00 |
| 68 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $4,100.00 | $20,000 | $10,000 |
| 69 | Unclassified excavation (503E21100) | CY | 20 | $106.00 | $8.00 | $150.00 |
| 70 | Epoxy coated steel reinforcement (509E10000) | LB | 3,632 | $1.90 | $1.01 | $2.15 |
| 71 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 13 | $1,825.00 | $823.00 | $1,800.00 |
| 72 | Class QC1 concrete, footing (511E46510) | CY | 20 | $360.00 | $823.00 | $700.00 |
| 73 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 50 | $40.00 | $90.26 | $60.00 |
| 74 | Porous backfill with geotextile fabric (518E21200) | CY | 7 | $185.00 | $262.29 | $115.00 |
| 75 | Patching concrete structures with trowelable mortar (843E50000) | SF | 110 | $25.00 | $95.00 | $40.00 |
| 76 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,250.00 | $15,000 | $10,000 |
| 77 | Maintaining traffic (614E11000) | LS | 1 | $22,500 | $15,000 | $5,000.00 |
| 78 | Field office, type B (619E16010) | MNTH | 3 | $1,500.00 | $5,000.00 | $2,000.00 |
| 79 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,500.00 | $20,000 | $15,000 |
| 80 | Mobilization (624E10000) | LS | 1 | $20,000 | $20,000 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.