ODOT contract 250209 bid tabulation

ALL-Harrod Improvements (MINOR RECONSTRUCTION). Let by Ohio DOT on April 24, 2025, ALL. 6 bids received; low bid $1,538,615 by R D Jones Excavating Inc, -30% against the engineer's estimate of $2,193,000.

Owner
Ohio DOT
Letting
24 APR 2025
Pay items
62
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1R D Jones Excavating Inc$1,538,615Low-30%
2Fenson Contracting LLC$2,027,885+32%-8.0%
3Vernon Nagel Inc$2,039,028+33%-7.0%
4Miller Contracting Group Inc$2,073,041+35%-5.0%
5Underground Utilities Inc$2,515,288+63%+15%
6Helms and Sons Excavating$2,600,035+69%+19%
ODOT contract 250209: bids by rank

Engineer's estimate: $2,193,000.

Bid tabulation

LinePay itemUnitQuantity1. R D Jones Excavating Inc2. Fenson Contracting LLC3. Vernon Nagel Inc4. Miller Contracting Group Inc5. Underground Utilities Inc6. Helms and Sons Excavating
1Clearing and grubbing (201E11000)LS1$25,750$25,500$10,000$34,524$40,000$75,000
2Pavement removed (202E23000)SY10,136$4.00$4.25$12.00$5.20$25.00$15.00
3Walk removed (202E30000)SF16,197$2.25$1.75$3.50$0.80$1.50$3.00
4Curb removed (202E32000)FT3,446$1.75$6.25$6.00$3.30$2.00$8.00
5Pipe removed, 24" and under (202E35100)FT510$12.80$40.00$15.00$28.50$45.00$25.00
6Catch basin removed (202E58100)EACH13$365.00$325.00$275.00$372.60$400.00$375.00
7Excavation (203E10000)CY755.60$11.65$21.50$30.00$22.90$60.00$30.00
8Embankment (203E20000)CY82.50$7.50$14.00$30.00$20.60$30.00$32.00
9Subgrade compaction (204E10000)SY10,984$0.75$1.00$1.00$1.70$0.50$2.00
10Excavation of subgrade (204E13000)CY3,490$11.65$25.00$15.00$37.00$33.00$30.00
11Granular material, type B (204E30010)CY3,490$42.78$50.00$62.00$64.00$50.00$60.00
12Proof rolling (204E45000)HR6$185.00$150.00$350.00$237.80$230.00$150.00
13Geotextile fabric (204E50000)SY8,955$1.85$1.15$1.25$1.10$0.60$1.00
14Pavement planing, asphalt CONCRETE1-1/2" (254E01000)SY6,091$2.60$2.15$3.20$2.80$3.50$4.00
15Patching planed surface (254E01600)SY122$11.00$20.00$15.00$15.50$18.00$18.00
164" concrete walk (608E10000)SF17,978$7.90$8.40$7.75$10.10$10.00$9.00
17Curb ramp, as per plan (608E52001)SF2,369$21.30$10.75$20.00$11.00$11.00$23.00
18Manhole adjusted to grade (611E99654)EACH8$1,150.00$1,350.00$1,000.00$620.00$800.00$1,000.00
19Topsoil (659E00300)CY134$42.15$120.00$40.00$90.00$60.00$50.00
20Seeding and mulching (659E10000)SY3,789$1.75$2.50$3.25$2.00$10.00$2.00
21Commercial fertilizer (659E20000)TON0.51$850.00$850.00$850.00$917.00$100.00$600.00
22Water (659E35000)MGAL20.50$1.00$1.00$1.00$1.00$110.00$4.00
23Erosion control (832E30000)EACH15,000$1.00$1.00$1.00$1.00$1.00$1.00
2412" conduit, type B (611E04400)FT1,011$33.50$62.25$90.00$43.70$170.00$118.00
2515" conduit, type B (611E05900)FT87$36.25$84.50$110.00$73.00$190.00$125.00
2618" conduit, type B (611E07400)FT434$43.00$72.75$125.00$66.20$200.00$116.00
2724" conduit, type B (611E10400)FT736$48.60$87.25$130.00$88.40$224.00$133.00
28Catch basin, no. 3 (611E98150)EACH4$2,885.00$4,260.00$5,200.00$3,833.00$4,400.00$4,450.00
29Catch basin, no. 3A (611E98180)EACH17$2,450.00$3,750.00$3,500.00$2,722.00$3,400.00$3,575.00
30Catch basin, no. 6 (611E98370)EACH1$3,010.00$3,400.00$3,800.00$3,047.00$3,700.00$4,350.00
31Catch basin, no. 2-2B (611E98470)EACH3$1,660.00$2,800.00$2,200.00$1,655.00$2,000.00$2,900.00
32Manhole, no. 3 (611E99574)EACH3$2,560.00$4,800.00$5,300.00$3,665.00$5,500.00$4,850.00
33Asphalt concrete base, PG64-22, (449) (301E56000)CY746$184.00$192.00$175.00$188.70$185.00$238.00
34Aggregate base (304E20000)CY2,020$42.78$54.00$64.00$55.10$50.00$60.00
35Non-tracking tack coat (407E20000)GAL1,320$2.50$3.05$4.00$5.00$3.00$3.00
36Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000)CY627$212.00$230.00$195.00$210.30$220.00$280.00
37Asphalt concrete intermediate course, type 2, (448) (441E50300)CY435$194.00$210.00$180.00$194.10$200.00$258.00
386" non-reinforced concrete pavement, class QC 1P (452E10010)SY230$82.90$108.00$80.00$116.30$95.00$92.00
399" non-reinforced concrete pavement, class QC 1P (452E13010)SY286$99.90$112.00$100.00$138.90$115.00$115.00
40Combination curb and gutter, type 2, as per plan (609E12001)FT4,555$27.00$24.25$24.00$26.10$30.00$29.00
418" water main polyvinyl chloride pipe and fittings, AWWA C900, DR14, as per plan (638E01711)FT450$112.65$265.00$160.00$181.60$100.00$265.00
421" copper service branch (638E04900)FT600$31.50$70.00$30.00$98.30$20.00$85.00
43Valve box adjusted to grade (638E10800)EACH11$275.00$500.00$300.00$456.80$300.00$950.00
44Ground mounted support, no. 3 post (630E03100)FT273.50$17.15$12.60$12.00$13.00$12.00$12.00
45Street name sign support, no. 3 post (630E08520)FT57.50$17.15$12.60$12.00$13.00$12.00$12.00
46Sign post reflector (630E08600)EACH50$63.15$42.00$40.00$43.20$40.00$40.00
47Sign, flat sheet (630E80100)SF131.16$19.86$25.25$24.00$25.90$24.00$25.00
48Removal of ground mounted sign and disposal (630E84900)EACH33$16.09$15.75$15.00$17.00$15.00$15.00
49Removal of ground mounted sign and reerection (630E85100)EACH1$62.32$52.50$50.00$54.00$50.00$50.00
50Removal of ground mounted post support and disposal (630E86002)EACH28$21.46$15.75$15.00$17.00$15.00$15.00
51Center line, type 1 (642E00300)MI0.86$6,450.00$6,775.00$2,000.00$2,157.00$2,000.00$2,000.00
52Stop line (643E00500)FT158$8.80$9.25$7.00$7.60$7.00$7.00
53Crosswalk line, 12" (643E00620)FT612$8.35$8.75$5.00$5.40$5.00$5.00
54Traffic compacted surface, type A or B (410E12000)CY74$42.78$115.00$60.00$44.00$100.00$60.00
55Detour signing (614E12420)LS1$7,675.00$3,150.00$3,000.00$13,909$6,000.00$4,500.00
56Water (616E10000)MGAL20$1.00$65.00$10.00$136.00$110.00$25.00
57Premium for contract performance bond and for payment bond (103E05000)LS1$12,600$17,000$20,000$22,318$50,000$25,000
58Maintaining traffic (614E11000)LS1$4,850.00$58,000$15,000$17,693$30,000$35,000
59Construction layout stakes and surveying (623E10000)LS1$14,600$25,500$15,000$15,720$35,000$30,000
60Preconstruction survey monument verification and report (623E50000)LS1$3,120.00$1,950.00$3,000.00$4,313.00$3,000.00$10,000
61Post construction survey monument verification and report (623E51000)LS1$3,120.00$1,950.00$2,500.00$4,313.00$3,000.00$10,000
62Mobilization (624E10000)LS1$25,000$100,000$100,000$141,450$100,000$150,000
ODOT contract 250209: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy