ODOT contract 250209 bid tabulation
ALL-Harrod Improvements (MINOR RECONSTRUCTION). Let by Ohio DOT on April 24, 2025, ALL. 6 bids received; low bid $1,538,615 by R D Jones Excavating Inc, -30% against the engineer's estimate of $2,193,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 62
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | R D Jones Excavating Inc | $1,538,615 | Low | -30% |
| 2 | Fenson Contracting LLC | $2,027,885 | +32% | -8.0% |
| 3 | Vernon Nagel Inc | $2,039,028 | +33% | -7.0% |
| 4 | Miller Contracting Group Inc | $2,073,041 | +35% | -5.0% |
| 5 | Underground Utilities Inc | $2,515,288 | +63% | +15% |
| 6 | Helms and Sons Excavating | $2,600,035 | +69% | +19% |
Engineer's estimate: $2,193,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R D Jones Excavating Inc | 2. Fenson Contracting LLC | 3. Vernon Nagel Inc | 4. Miller Contracting Group Inc | 5. Underground Utilities Inc | 6. Helms and Sons Excavating |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $25,750 | $25,500 | $10,000 | $34,524 | $40,000 | $75,000 |
| 2 | Pavement removed (202E23000) | SY | 10,136 | $4.00 | $4.25 | $12.00 | $5.20 | $25.00 | $15.00 |
| 3 | Walk removed (202E30000) | SF | 16,197 | $2.25 | $1.75 | $3.50 | $0.80 | $1.50 | $3.00 |
| 4 | Curb removed (202E32000) | FT | 3,446 | $1.75 | $6.25 | $6.00 | $3.30 | $2.00 | $8.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 510 | $12.80 | $40.00 | $15.00 | $28.50 | $45.00 | $25.00 |
| 6 | Catch basin removed (202E58100) | EACH | 13 | $365.00 | $325.00 | $275.00 | $372.60 | $400.00 | $375.00 |
| 7 | Excavation (203E10000) | CY | 755.60 | $11.65 | $21.50 | $30.00 | $22.90 | $60.00 | $30.00 |
| 8 | Embankment (203E20000) | CY | 82.50 | $7.50 | $14.00 | $30.00 | $20.60 | $30.00 | $32.00 |
| 9 | Subgrade compaction (204E10000) | SY | 10,984 | $0.75 | $1.00 | $1.00 | $1.70 | $0.50 | $2.00 |
| 10 | Excavation of subgrade (204E13000) | CY | 3,490 | $11.65 | $25.00 | $15.00 | $37.00 | $33.00 | $30.00 |
| 11 | Granular material, type B (204E30010) | CY | 3,490 | $42.78 | $50.00 | $62.00 | $64.00 | $50.00 | $60.00 |
| 12 | Proof rolling (204E45000) | HR | 6 | $185.00 | $150.00 | $350.00 | $237.80 | $230.00 | $150.00 |
| 13 | Geotextile fabric (204E50000) | SY | 8,955 | $1.85 | $1.15 | $1.25 | $1.10 | $0.60 | $1.00 |
| 14 | Pavement planing, asphalt CONCRETE1-1/2" (254E01000) | SY | 6,091 | $2.60 | $2.15 | $3.20 | $2.80 | $3.50 | $4.00 |
| 15 | Patching planed surface (254E01600) | SY | 122 | $11.00 | $20.00 | $15.00 | $15.50 | $18.00 | $18.00 |
| 16 | 4" concrete walk (608E10000) | SF | 17,978 | $7.90 | $8.40 | $7.75 | $10.10 | $10.00 | $9.00 |
| 17 | Curb ramp, as per plan (608E52001) | SF | 2,369 | $21.30 | $10.75 | $20.00 | $11.00 | $11.00 | $23.00 |
| 18 | Manhole adjusted to grade (611E99654) | EACH | 8 | $1,150.00 | $1,350.00 | $1,000.00 | $620.00 | $800.00 | $1,000.00 |
| 19 | Topsoil (659E00300) | CY | 134 | $42.15 | $120.00 | $40.00 | $90.00 | $60.00 | $50.00 |
| 20 | Seeding and mulching (659E10000) | SY | 3,789 | $1.75 | $2.50 | $3.25 | $2.00 | $10.00 | $2.00 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.51 | $850.00 | $850.00 | $850.00 | $917.00 | $100.00 | $600.00 |
| 22 | Water (659E35000) | MGAL | 20.50 | $1.00 | $1.00 | $1.00 | $1.00 | $110.00 | $4.00 |
| 23 | Erosion control (832E30000) | EACH | 15,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | 12" conduit, type B (611E04400) | FT | 1,011 | $33.50 | $62.25 | $90.00 | $43.70 | $170.00 | $118.00 |
| 25 | 15" conduit, type B (611E05900) | FT | 87 | $36.25 | $84.50 | $110.00 | $73.00 | $190.00 | $125.00 |
| 26 | 18" conduit, type B (611E07400) | FT | 434 | $43.00 | $72.75 | $125.00 | $66.20 | $200.00 | $116.00 |
| 27 | 24" conduit, type B (611E10400) | FT | 736 | $48.60 | $87.25 | $130.00 | $88.40 | $224.00 | $133.00 |
| 28 | Catch basin, no. 3 (611E98150) | EACH | 4 | $2,885.00 | $4,260.00 | $5,200.00 | $3,833.00 | $4,400.00 | $4,450.00 |
| 29 | Catch basin, no. 3A (611E98180) | EACH | 17 | $2,450.00 | $3,750.00 | $3,500.00 | $2,722.00 | $3,400.00 | $3,575.00 |
| 30 | Catch basin, no. 6 (611E98370) | EACH | 1 | $3,010.00 | $3,400.00 | $3,800.00 | $3,047.00 | $3,700.00 | $4,350.00 |
| 31 | Catch basin, no. 2-2B (611E98470) | EACH | 3 | $1,660.00 | $2,800.00 | $2,200.00 | $1,655.00 | $2,000.00 | $2,900.00 |
| 32 | Manhole, no. 3 (611E99574) | EACH | 3 | $2,560.00 | $4,800.00 | $5,300.00 | $3,665.00 | $5,500.00 | $4,850.00 |
| 33 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 746 | $184.00 | $192.00 | $175.00 | $188.70 | $185.00 | $238.00 |
| 34 | Aggregate base (304E20000) | CY | 2,020 | $42.78 | $54.00 | $64.00 | $55.10 | $50.00 | $60.00 |
| 35 | Non-tracking tack coat (407E20000) | GAL | 1,320 | $2.50 | $3.05 | $4.00 | $5.00 | $3.00 | $3.00 |
| 36 | Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000) | CY | 627 | $212.00 | $230.00 | $195.00 | $210.30 | $220.00 | $280.00 |
| 37 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 435 | $194.00 | $210.00 | $180.00 | $194.10 | $200.00 | $258.00 |
| 38 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 230 | $82.90 | $108.00 | $80.00 | $116.30 | $95.00 | $92.00 |
| 39 | 9" non-reinforced concrete pavement, class QC 1P (452E13010) | SY | 286 | $99.90 | $112.00 | $100.00 | $138.90 | $115.00 | $115.00 |
| 40 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 4,555 | $27.00 | $24.25 | $24.00 | $26.10 | $30.00 | $29.00 |
| 41 | 8" water main polyvinyl chloride pipe and fittings, AWWA C900, DR14, as per plan (638E01711) | FT | 450 | $112.65 | $265.00 | $160.00 | $181.60 | $100.00 | $265.00 |
| 42 | 1" copper service branch (638E04900) | FT | 600 | $31.50 | $70.00 | $30.00 | $98.30 | $20.00 | $85.00 |
| 43 | Valve box adjusted to grade (638E10800) | EACH | 11 | $275.00 | $500.00 | $300.00 | $456.80 | $300.00 | $950.00 |
| 44 | Ground mounted support, no. 3 post (630E03100) | FT | 273.50 | $17.15 | $12.60 | $12.00 | $13.00 | $12.00 | $12.00 |
| 45 | Street name sign support, no. 3 post (630E08520) | FT | 57.50 | $17.15 | $12.60 | $12.00 | $13.00 | $12.00 | $12.00 |
| 46 | Sign post reflector (630E08600) | EACH | 50 | $63.15 | $42.00 | $40.00 | $43.20 | $40.00 | $40.00 |
| 47 | Sign, flat sheet (630E80100) | SF | 131.16 | $19.86 | $25.25 | $24.00 | $25.90 | $24.00 | $25.00 |
| 48 | Removal of ground mounted sign and disposal (630E84900) | EACH | 33 | $16.09 | $15.75 | $15.00 | $17.00 | $15.00 | $15.00 |
| 49 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $62.32 | $52.50 | $50.00 | $54.00 | $50.00 | $50.00 |
| 50 | Removal of ground mounted post support and disposal (630E86002) | EACH | 28 | $21.46 | $15.75 | $15.00 | $17.00 | $15.00 | $15.00 |
| 51 | Center line, type 1 (642E00300) | MI | 0.86 | $6,450.00 | $6,775.00 | $2,000.00 | $2,157.00 | $2,000.00 | $2,000.00 |
| 52 | Stop line (643E00500) | FT | 158 | $8.80 | $9.25 | $7.00 | $7.60 | $7.00 | $7.00 |
| 53 | Crosswalk line, 12" (643E00620) | FT | 612 | $8.35 | $8.75 | $5.00 | $5.40 | $5.00 | $5.00 |
| 54 | Traffic compacted surface, type A or B (410E12000) | CY | 74 | $42.78 | $115.00 | $60.00 | $44.00 | $100.00 | $60.00 |
| 55 | Detour signing (614E12420) | LS | 1 | $7,675.00 | $3,150.00 | $3,000.00 | $13,909 | $6,000.00 | $4,500.00 |
| 56 | Water (616E10000) | MGAL | 20 | $1.00 | $65.00 | $10.00 | $136.00 | $110.00 | $25.00 |
| 57 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,600 | $17,000 | $20,000 | $22,318 | $50,000 | $25,000 |
| 58 | Maintaining traffic (614E11000) | LS | 1 | $4,850.00 | $58,000 | $15,000 | $17,693 | $30,000 | $35,000 |
| 59 | Construction layout stakes and surveying (623E10000) | LS | 1 | $14,600 | $25,500 | $15,000 | $15,720 | $35,000 | $30,000 |
| 60 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,120.00 | $1,950.00 | $3,000.00 | $4,313.00 | $3,000.00 | $10,000 |
| 61 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,120.00 | $1,950.00 | $2,500.00 | $4,313.00 | $3,000.00 | $10,000 |
| 62 | Mobilization (624E10000) | LS | 1 | $25,000 | $100,000 | $100,000 | $141,450 | $100,000 | $150,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.