ODOT contract 260341 bid tabulation
ALL-Delphos S. Main St. Trail (SIDEWALK). Let by Ohio DOT on July 30, 2026, ALL. 5 bids received; low bid $466,218 by Fenson Contracting LLC, -9.5% against the engineer's estimate of $515,000.
- Owner
- Ohio DOT
- Letting
- 30 JUL 2026
- Pay items
- 70
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fenson Contracting LLC | $466,218 | Low | -9.0% |
| 2 | Ebony Construction Co | $466,905 | 0.0% | -9.0% |
| 3 | Ward Construction Co | $490,221 | +5.0% | -5.0% |
| 4 | Helms and Sons Excavating | $650,213 | +39% | +26% |
| 5 | Madex Construction Co | $749,002 | +61% | +45% |
Engineer's estimate: $515,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fenson Contracting LLC | 2. Ebony Construction Co | 3. Ward Construction Co | 4. Helms and Sons Excavating | 5. Madex Construction Co |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $10,000 | $6,700.00 | $5,000.00 | $15,000 | $23,158 |
| 2 | Walk removed (202E30000) | SF | 3,200 | $2.00 | $1.40 | $2.50 | $6.00 | $4.16 |
| 3 | Excavation (203E10000) | CY | 590 | $25.00 | $34.50 | $30.00 | $50.00 | $28.95 |
| 4 | Embankment (203E20000) | CY | 7 | $20.00 | $70.50 | $100.00 | $130.00 | $57.89 |
| 5 | Subgrade compaction (204E10000) | SY | 1,380 | $3.50 | $0.50 | $1.00 | $4.00 | $3.47 |
| 6 | 4" concrete walk (608E10000) | SF | 459 | $12.50 | $24.50 | $24.00 | $15.00 | $19.68 |
| 7 | Curb ramp (608E52000) | SF | 237 | $37.00 | $18.00 | $30.00 | $35.00 | $39.37 |
| 8 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,250.00 | $3,245.00 | $4,000.00 | $7,500.00 | $5,789.47 |
| 9 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,250.00 | $3,245.00 | $4,000.00 | $7,500.00 | $5,789.47 |
| 10 | Topsoil (659E00300) | CY | 368 | $40.00 | $74.00 | $90.00 | $80.00 | $75.26 |
| 11 | Seeding and mulching, class 1 (659E00500) | SY | 2,653 | $3.00 | $1.55 | $1.40 | $2.00 | $5.21 |
| 12 | Repair seeding and mulching (659E14000) | SY | 120 | $1.40 | $1.55 | $1.40 | $2.50 | $5.79 |
| 13 | Inter-seeding (659E15000) | SY | 120 | $1.00 | $1.10 | $1.00 | $2.50 | $5.79 |
| 14 | Commercial fertilizer (659E20000) | TON | 0.50 | $850.00 | $945.00 | $850.00 | $900.00 | $2,315.80 |
| 15 | Lime (659E31000) | ACRE | 0.48 | $35.00 | $38.00 | $35.00 | $50.00 | $1,157.90 |
| 16 | Water (659E35000) | MGAL | 12.90 | $1.00 | $1.00 | $10.00 | $5.00 | $57.89 |
| 17 | Erosion control (832E30000) | EACH | 5,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | 6" conduit, type B (611E00900) | FT | 25 | $26.00 | $42.00 | $100.00 | $88.00 | $63.68 |
| 19 | Conduit, misc.: type B for drainage discharge (611E97400) | FT | 10 | $24.00 | $40.50 | $30.00 | $171.00 | $70.53 |
| 20 | Conduit, misc.: type C for drainage discharge (611E97400) | FT | 10 | $24.00 | $48.50 | $28.00 | $151.00 | $70.53 |
| 21 | Conduit, misc.: type E for drainage discharge (611E97400) | FT | 10 | $17.00 | $57.25 | $25.00 | $171.00 | $70.53 |
| 22 | Conduit, misc.: type F for drainage discharge (611E97400) | FT | 10 | $24.00 | $72.50 | $28.00 | $171.00 | $70.53 |
| 23 | Pavement removed (202E23000) | SY | 446 | $12.00 | $11.40 | $18.00 | $38.00 | $34.74 |
| 24 | Aggregate base (304E20000) | CY | 238 | $95.00 | $69.50 | $130.00 | $80.00 | $114.63 |
| 25 | Non-tracking tack coat (407E20000) | GAL | 57 | $3.00 | $2.20 | $3.00 | $4.00 | $9.26 |
| 26 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 37 | $420.00 | $375.00 | $420.00 | $385.00 | $602.11 |
| 27 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 68 | $320.00 | $280.00 | $320.00 | $320.00 | $463.16 |
| 28 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 2 | $860.00 | $595.00 | $860.00 | $996.00 | $1,186.84 |
| 29 | Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700) | CY | 4 | $500.00 | $452.00 | $500.00 | $570.00 | $752.63 |
| 30 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 456 | $105.00 | $93.00 | $130.00 | $112.00 | $196.84 |
| 31 | Service box adjusted to grade (638E10900) | EACH | 2 | $415.00 | $498.00 | $1,000.00 | $1,180.00 | $578.95 |
| 32 | Manhole adjusted to grade (611E99654) | EACH | 2 | $1,450.00 | $940.00 | $1,500.00 | $1,770.00 | $1,736.84 |
| 33 | Manhole reconstructed to grade (611E99660) | EACH | 3 | $2,675.00 | $1,144.00 | $2,000.00 | $5,700.00 | $3,184.21 |
| 34 | 4" conduit, type E (611E00400) | FT | 40 | $1.42 | $15.00 | $1.50 | $15.00 | $5.79 |
| 35 | Connection, fused pull apart, as per plan (625E00451) | EACH | 30 | $172.25 | $194.00 | $172.50 | $250.00 | $214.21 |
| 36 | Connection, unfused pull apart (625E00460) | EACH | 10 | $172.50 | $194.00 | $172.50 | $250.00 | $214.21 |
| 37 | Light pole, decorative, as per plan (625E10481) | EACH | 9 | $7,640.00 | $8,555.00 | $7,640.00 | $4,370.00 | $7,178.95 |
| 38 | Light pole foundation, 24" X 6' deep (625E14000) | EACH | 10 | $2,135.00 | $2,500.00 | $2,134.00 | $3,120.00 | $4,400.00 |
| 39 | No. 4 AWG 600 volt distribution cable (625E23000) | FT | 3,495 | $4.59 | $5.40 | $4.60 | $5.50 | $7.53 |
| 40 | No. 8 AWG 600 volt distribution cable (625E23304) | FT | 3,495 | $3.26 | $3.60 | $3.30 | $4.00 | $6.08 |
| 41 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,440 | $2.64 | $2.95 | $2.65 | $3.00 | $4.05 |
| 42 | Conduit, 2", 725.051 (625E25408) | FT | 825 | $9.45 | $10.60 | $9.45 | $9.00 | $18.53 |
| 43 | Conduit, 3", 725.051 (625E25504) | FT | 47 | $10.60 | $12.00 | $10.60 | $11.00 | $25.47 |
| 44 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 51 | $44.00 | $49.50 | $44.00 | $146.00 | $162.11 |
| 45 | Removal of luminaire and reerection (625E27520) | EACH | 1 | $288.75 | $325.00 | $290.00 | $968.00 | $492.11 |
| 46 | Luminaire, decorative, as per plan, holophane post (625E27551) | EACH | 9 | $1,750.00 | $2,000.00 | $1,750.00 | $2,820.00 | $2,547.37 |
| 47 | Trench (625E29000) | FT | 872 | $12.20 | $13.70 | $12.20 | $20.00 | $30.11 |
| 48 | Pull box, 725.06, size 7 (625E30520) | EACH | 2 | $1,385.00 | $1,550.00 | $1,385.00 | $1,985.00 | $2,142.11 |
| 49 | Ground rod (625E32000) | EACH | 11 | $275.00 | $307.00 | $275.00 | $648.00 | $578.95 |
| 50 | Power service, as per plan (625E34001) | EACH | 1 | $10,595 | $11,875 | $10,595 | $14,050 | $21,421 |
| 51 | Underground warning marking tape (625E36010) | FT | 872 | $2.06 | $2.20 | $2.10 | $3.50 | $4.63 |
| 52 | Light pole removed for reerection (625E60010) | EACH | 1 | $1,675.00 | $1,875.00 | $1,675.00 | $2,410.00 | $4,052.63 |
| 53 | Light pole foundation removed (625E75500) | EACH | 1 | $1,270.00 | $1,425.00 | $1,270.00 | $4,340.00 | $578.95 |
| 54 | Arc flash calculations and label, (lighting power (625E76000) | EACH | 1 | $3,395.00 | $3,800.00 | $3,395.00 | $6,615.00 | $5,234.84 |
| 55 | Power cable, 3 conductor, no. 2 AWG (632E69320) | FT | 81 | $12.53 | $14.00 | $12.60 | $23.00 | $13.89 |
| 56 | Ground mounted support, no. 3 post (630E03100) | FT | 28 | $18.00 | $20.00 | $18.00 | $20.00 | $46.32 |
| 57 | Sign post reflector (630E08600) | EACH | 2 | $50.00 | $55.00 | $50.00 | $56.00 | $86.84 |
| 58 | Sign post reflector (630E08600) | EACH | 1 | $50.00 | $55.00 | $50.00 | $56.00 | $86.84 |
| 59 | Sign, flat sheet (630E80100) | SF | 14 | $35.00 | $39.00 | $35.00 | $39.00 | $70.53 |
| 60 | Sign, double faced, street name (630E80500) | EACH | 2 | $150.00 | $165.00 | $150.00 | $168.00 | $257.05 |
| 61 | Removal of ground mounted sign and disposal (630E84900) | EACH | 5 | $25.00 | $27.00 | $25.00 | $28.00 | $28.95 |
| 62 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $100.00 | $110.00 | $100.00 | $112.00 | $90.32 |
| 63 | Removal of ground mounted post support and disposal (630E86002) | EACH | 3 | $25.00 | $27.00 | $25.00 | $28.00 | $28.95 |
| 64 | Stop line (644E00500) | FT | 14 | $40.00 | $44.00 | $40.00 | $45.00 | $25.47 |
| 65 | Crosswalk line, 12" (644E00620) | FT | 73 | $8.00 | $8.65 | $8.00 | $9.00 | $17.37 |
| 66 | Shared lane marking (644E19000) | EACH | 4 | $450.00 | $500.00 | $450.00 | $503.00 | $966.84 |
| 67 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $6,000.00 | $4,800.00 | $5,000.00 | $10,000 | $16,789 |
| 68 | Maintaining traffic (614E11000) | LS | 1 | $20,000 | $13,550 | $10,000 | $15,000 | $23,158 |
| 69 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $10,000 | $6,300.00 | $7,000.00 | $12,500 | $11,579 |
| 70 | Mobilization (624E10000) | LS | 1 | $20,000 | $18,300 | $16,000 | $85,000 | $45,802 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 30, 2026. Compiled by Mirage Metrics.