ODOT contract 260143 bid tabulation
AUG-SR 501/SR 198-02.32/02.36 (INTERSECTION). Let by Ohio DOT on March 26, 2026, AUG. 2 bids received; low bid $1,699,234 by Miller Contracting Group Inc, +11% against the engineer's estimate of $1,537,000.
- Owner
- Ohio DOT
- Letting
- 26 MAR 2026
- Pay items
- 157
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Miller Contracting Group Inc | $1,699,234 | Low | +11% |
| 2 | Fenson Contracting LLC | $2,166,924 | +28% | +41% |
Engineer's estimate: $1,537,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Miller Contracting Group Inc | 2. Fenson Contracting LLC |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $15,640 | $18,000 |
| 2 | Pavement removed (202E23000) | SY | 2,629 | $0.80 | $25.00 |
| 3 | Walk removed (202E30000) | SF | 5,334 | $0.60 | $10.00 |
| 4 | Curb removed (202E32000) | FT | 84 | $1.00 | $10.00 |
| 5 | Curb and gutter removed (202E32500) | FT | 1,309 | $2.80 | $15.00 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 211 | $41.30 | $65.00 |
| 7 | Catch basin removed (202E58100) | EACH | 2 | $484.00 | $1,000.00 |
| 8 | Removal misc.: brick landscape column (202E98100) | EACH | 4 | $398.00 | $1,200.00 |
| 9 | Removal misc.: inspection well (202E98100) | EACH | 2 | $300.00 | $1,500.00 |
| 10 | Removal misc.: conduit (202E98200) | FT | 50 | $50.00 | $25.00 |
| 11 | Excavation (203E10000) | CY | 1,909 | $25.80 | $40.00 |
| 12 | Embankment (203E20000) | CY | 174 | $17.00 | $55.00 |
| 13 | Embankment, as per plan (203E20001) | CY | 10 | $54.30 | $100.00 |
| 14 | Subgrade compaction (204E10000) | SY | 2,961 | $1.40 | $5.00 |
| 15 | Excavation of subgrade (204E13000) | CY | 646 | $15.50 | $30.00 |
| 16 | Granular material, type B (204E30010) | CY | 646 | $62.80 | $60.00 |
| 17 | Proof rolling (204E45000) | HR | 2 | $269.00 | $150.00 |
| 18 | Geotextile fabric (204E50000) | SY | 1,189 | $2.00 | $4.00 |
| 19 | Geogrid (204E51000) | SY | 741 | $3.00 | $6.00 |
| 20 | 4" concrete walk, as per plan (608E10001) | SF | 5,733 | $9.00 | $13.50 |
| 21 | Concrete steps, type A, as per plan (608E40001) | FT | 10 | $60.00 | $450.00 |
| 22 | Curb ramp, as per plan (608E52001) | SF | 1,147 | $27.00 | $30.00 |
| 23 | Monument assembly, type C (623E38500) | EACH | 5 | $727.00 | $2,500.00 |
| 24 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,500.00 | $2,500.00 |
| 25 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,500.00 | $2,500.00 |
| 26 | Topsoil (659E00300) | CY | 372 | $17.00 | $95.00 |
| 27 | Seeding and mulching, class 1 (659E00500) | SY | 3,350 | $2.10 | $6.00 |
| 28 | Repair seeding and mulching (659E14000) | SY | 168 | $2.10 | $2.00 |
| 29 | Inter-seeding (659E15000) | SY | 168 | $1.20 | $1.00 |
| 30 | Commercial fertilizer (659E20000) | TON | 0.45 | $960.00 | $950.00 |
| 31 | Lime (659E31000) | ACRE | 0.69 | $20.00 | $35.00 |
| 32 | Water (659E35000) | MGAL | 18.10 | $1.00 | $1.00 |
| 33 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,200.00 | $4,250.00 |
| 34 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $14,500 | $12,500 |
| 35 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $15,100 | $15,000 |
| 36 | Erosion control (832E30000) | EACH | 18,500 | $1.00 | $1.00 |
| 37 | 4" unclassified pipe underdrains (605E05200) | FT | 309 | $19.20 | $40.00 |
| 38 | 4" base pipe underdrains (605E06000) | FT | 583 | $15.90 | $40.00 |
| 39 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 75 | $37.20 | $65.00 |
| 40 | 6" conduit, type B (611E00900) | FT | 158 | $26.10 | $85.00 |
| 41 | 12" conduit, type B (611E04400) | FT | 131 | $67.90 | $110.00 |
| 42 | 12" conduit, type C (611E04600) | FT | 51 | $79.00 | $100.00 |
| 43 | 15" conduit, type B (611E05900) | FT | 20 | $106.70 | $120.00 |
| 44 | 15" conduit, type C (611E06100) | FT | 108 | $80.00 | $100.00 |
| 45 | Conduit, misc.: type E for drainage discharge cont (611E97400) | FT | 50 | $50.00 | $50.00 |
| 46 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $1,981.00 | $4,000.00 |
| 47 | Catch basin, misc.: type CB-1 (611E98690) | EACH | 2 | $3,139.00 | $5,000.00 |
| 48 | Catch basin, misc.: type CB-1A (611E98690) | EACH | 3 | $4,328.00 | $6,000.00 |
| 49 | Manhole, no. 3 with 90" base I.D. and 8" weir (611E99582) | EACH | 1 | $14,265 | $30,000 |
| 50 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 1 | $889.00 | $3,000.00 |
| 51 | Inspection well (611E99720) | EACH | 2 | $1,500.00 | $3,500.00 |
| 52 | Inspection well, as per plan (611E99721) | EACH | 1 | $1,500.00 | $4,000.00 |
| 53 | Manufactured water quality structure, type 2 (895E10020) | EACH | 1 | $20,100 | $38,000 |
| 54 | Pavement planing, asphalt concrete (1.25" thick) (254E01000) | SY | 3,202 | $4.80 | $4.50 |
| 55 | Patching planed surface (254E01600) | SY | 160 | $11.30 | $10.00 |
| 56 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 394 | $326.30 | $340.00 |
| 57 | Aggregate base (304E20000) | CY | 527 | $57.00 | $70.00 |
| 58 | Non-tracking tack coat (407E20000) | GAL | 252 | $5.70 | $5.00 |
| 59 | Stabilized crushed aggregate (411E10000) | CY | 77 | $66.20 | $80.00 |
| 60 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 172 | $368.10 | $375.00 |
| 61 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 147 | $414.00 | $420.00 |
| 62 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 1 | $369.00 | $375.00 |
| 63 | Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700) | CY | 2 | $414.00 | $420.00 |
| 64 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 62 | $132.00 | $120.00 |
| 65 | 9" non-reinforced concrete pavement, class QC 1P, as per plan (452E13011) | SY | 18 | $158.00 | $155.00 |
| 66 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 744 | $50.00 | $60.00 |
| 67 | Combination curb and gutter, type 3, as per plan (609E18001) | FT | 415 | $50.00 | $60.00 |
| 68 | Curb, type 6, as per plan (609E26001) | FT | 54 | $42.00 | $50.00 |
| 69 | Special - asphalt rejuvenating agent (690E12150) | GAL | 628 | $50.00 | $11.50 |
| 70 | Special - testing (690E12160) | LS | 1 | $500.00 | $3,500.00 |
| 71 | Valve box adjusted to grade (638E10800) | EACH | 3 | $750.00 | $1,500.00 |
| 72 | Service box adjusted to grade (638E10900) | EACH | 1 | $750.00 | $1,500.00 |
| 73 | Manhole adjusted to grade (611E99654) | EACH | 1 | $750.00 | $3,500.00 |
| 74 | Sign post reflector (630E08600) | EACH | 1 | $63.00 | $63.00 |
| 75 | Sign hanger assembly, mast arm, as per plan (630E79101) | EACH | 5 | $565.00 | $575.00 |
| 76 | Sign, flat sheet (630E80100) | SF | 6.30 | $23.00 | $23.00 |
| 77 | Sign, flat sheet, as per plan (630E80101) | SF | 76.40 | $57.00 | $58.00 |
| 78 | Sign, double faced, street name, as per plan (630E80501) | EACH | 2 | $339.00 | $345.00 |
| 79 | Sign, street name, as per plan (630E80511) | EACH | 3 | $226.00 | $240.00 |
| 80 | Removal of ground mounted sign and disposal (630E84900) | EACH | 46 | $29.00 | $28.00 |
| 81 | Removal of ground mounted post support and disposal (630E86002) | EACH | 25 | $29.00 | $28.00 |
| 82 | Removal of pole mounted sign and reerection (630E87520) | EACH | 1 | $170.00 | $170.00 |
| 83 | Signing, misc.: traffic sign support system (black (630E97900) | FT | 208 | $74.00 | $75.00 |
| 84 | Edge line, 4" (644E00100) | MI | 0.40 | $6,209.00 | $6,300.00 |
| 85 | Center line (644E00300) | MI | 0.60 | $11,289 | $11,500 |
| 86 | Channelizing line, 8" (644E00400) | FT | 243 | $2.30 | $2.30 |
| 87 | Stop line (644E00500) | FT | 93 | $8.00 | $8.00 |
| 88 | Crosswalk line, 12" (644E00620) | FT | 433 | $4.60 | $4.60 |
| 89 | Lane arrow (644E01300) | EACH | 8 | $142.00 | $143.00 |
| 90 | Removal of pavement marking (644E30000) | FT | 381 | $10.00 | $10.00 |
| 91 | 4" conduit, type E (611E00400) | FT | 100 | $24.00 | $1.60 |
| 92 | Connection, fused pull apart (625E00450) | EACH | 3 | $209.00 | $200.00 |
| 93 | Connection, unfused pull apart (625E00460) | EACH | 3 | $209.00 | $192.00 |
| 94 | Light pole, conventional, as per plan, truss arm(A (625E10491) | EACH | 2 | $6,209.00 | $5,200.00 |
| 95 | Light pole foundation, 24" X 6' deep (625E14000) | EACH | 3 | $4,290.00 | $2,300.00 |
| 96 | Bracket arm, 10', as per plan (625E18001) | EACH | 1 | $1,920.00 | $1,270.00 |
| 97 | Conduit, 2", 725.051 (625E25408) | FT | 177 | $24.90 | $10.00 |
| 98 | Conduit, 3", 725.051 (625E25504) | FT | 72 | $29.40 | $13.00 |
| 99 | Conduit, 4", 725.051 (625E25604) | FT | 44 | $32.80 | $13.50 |
| 100 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 350 | $73.40 | $49.00 |
| 101 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 136 | $84.70 | $53.00 |
| 102 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 70 | $107.30 | $61.00 |
| 103 | Luminaire, installation only, as per plan (625E27561) | EACH | 3 | $508.10 | $257.00 |
| 104 | Trench (625E29000) | FT | 289 | $51.00 | $14.00 |
| 105 | Pull box, 725.08, 18" (625E30700) | EACH | 3 | $2,033.00 | $1,300.00 |
| 106 | Pull box, 725.08, 24" (625E30706) | EACH | 2 | $2,484.00 | $1,560.00 |
| 107 | Ground rod (625E32000) | EACH | 10 | $480.00 | $348.00 |
| 108 | Underground warning marking tape (625E36010) | FT | 289 | $4.60 | $2.30 |
| 109 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007) | EACH | 6 | $1,694.00 | $1,390.00 |
| 110 | Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate, as per plan (632E05087) | EACH | 3 | $3,613.00 | $2,300.00 |
| 111 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 8 | $1,355.00 | $965.00 |
| 112 | Accessible pedestrian pushbutton, as per plan (632E20751) | EACH | 8 | $1,694.00 | $1,500.00 |
| 113 | Covering of vehicular signal head (632E25000) | EACH | 9 | $57.00 | $42.00 |
| 114 | Covering of pedestrian signal head (632E25010) | EACH | 8 | $46.00 | $34.00 |
| 115 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 1,117 | $6.00 | $4.60 |
| 116 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 746 | $6.30 | $5.75 |
| 117 | Signal cable, 3 conductor, no. 12 AWG (632E42300) | FT | 534 | $4.60 | $4.00 |
| 118 | Signal support foundation, as per plan (632E64011) | EACH | 1 | $25,410 | $11,000 |
| 119 | Pedestal foundation (632E64020) | EACH | 5 | $2,490.00 | $2,025.00 |
| 120 | Loop detector lead-in cable, 2 conductor, no. 12 AWG (632E65400) | FT | 1,089 | $4.00 | $3.50 |
| 121 | Power cable, 3 conductor, no. 6 AWG (632E68300) | FT | 267 | $11.30 | $5.50 |
| 122 | Power service, as per plan (632E70001) | EACH | 1 | $7,340.00 | $4,800.00 |
| 123 | Conduit riser, 2" diameter (632E70400) | EACH | 2 | $960.00 | $1,625.00 |
| 124 | Pedestal, 8', transformer base, as per plan (632E89901) | EACH | 5 | $1,355.00 | $1,400.00 |
| 125 | Pedestal, 15', transformer base (632E90008) | EACH | 1 | $2,484.00 | $2,400.00 |
| 126 | Removal of traffic signal installation, as per plan (632E90101) | EACH | 1 | $6,492.00 | $8,800.00 |
| 127 | Signalization, misc.: combination signal support ( (632E90400) | EACH | 1 | $55,277 | $52,000 |
| 128 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 1 | $26,191 | $25,750 |
| 129 | Cabinet foundation (633E67100) | EACH | 1 | $3,839.00 | $2,650.00 |
| 130 | Controller work pad, as per plan (633E67201) | EACH | 1 | $960.00 | $1,100.00 |
| 131 | Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001) | EACH | 1 | $9,596.00 | $8,400.00 |
| 132 | Stop line radar detection, as per plan (809E69101) | EACH | 5 | $12,136 | $12,700 |
| 133 | Atc controller, as per plan (809E69123) | EACH | 1 | $7,903.00 | $6,500.00 |
| 134 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 32 | $95.00 | $125.00 |
| 135 | Special - work zone traffic signal (614E11300) | EACH | 1 | $50,810 | $17,200 |
| 136 | Detour signing, as per plan (614E12421) | LS | 1 | $28,230 | $35,000 |
| 137 | Work zone center line, class I (614E21000) | MI | 0.60 | $1,694.00 | $1,700.00 |
| 138 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.60 | $1,694.00 | $1,700.00 |
| 139 | Work zone edge line, class I, 4" (614E22000) | MI | 0.40 | $1,355.00 | $1,300.00 |
| 140 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 0.40 | $1,355.00 | $1,300.00 |
| 141 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 0.40 | $1,355.00 | $1,300.00 |
| 142 | Work zone channelizing line, class I, 8" (614E23000) | FT | 243 | $1.20 | $1.10 |
| 143 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 243 | $1.20 | $1.10 |
| 144 | Work zone dotted line, class I, 4", 642 paint (614E24200) | FT | 99 | $1.20 | $1.10 |
| 145 | Work zone stop line, class I (614E26000) | FT | 93 | $3.40 | $3.40 |
| 146 | Work zone stop line, class III, 642 paint (614E26610) | FT | 93 | $3.40 | $3.40 |
| 147 | Work zone arrow, class I (614E30000) | EACH | 8 | $46.00 | $46.00 |
| 148 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 8 | $46.00 | $46.00 |
| 149 | Roads for maintaining traffic, as per plan (615E10001) | LS | 1 | $3,300.00 | $35,000 |
| 150 | Pavement for maintaining traffic, class A, as per plan (615E20001) | SY | 177 | $195.00 | $300.00 |
| 151 | Water (616E10000) | MGAL | 7.70 | $1.00 | $50.00 |
| 152 | Down guy, as per plan (632E89401) | EACH | 1 | $1,073.00 | $1,260.00 |
| 153 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $18,000 | $25,000 |
| 154 | Maintaining traffic (614E11000) | LS | 1 | $58,140 | $155,000 |
| 155 | Field office, type B (619E16010) | MNTH | 12 | $1,870.00 | $8,600.00 |
| 156 | Construction layout stakes and surveying (623E10000) | LS | 1 | $18,200 | $40,500 |
| 157 | Mobilization (624E10000) | LS | 1 | $165,000 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 26, 2026. Compiled by Mirage Metrics.