ODOT letting results, March 26, 2026
26 contracts let by Ohio DOT on March 26, 2026, $110,077,025 in low bids, a median of 3 bidders per contract. On the 26 with an engineer's estimate, the low bid came in under it 13 times; median low bid +1.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 26
- Low bids, total
- $110,077,025
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 260152 | HAS-US 22-15.11 (MAJOR RECONSTRUCTION) | HAS | 2 | Shelly & Sands Inc | $37,148,699 | $40,792,851 | +10% | +4.0% | ODOT |
| 260076 | MAH-IR 76/IR 80-08.50/00.00 (MAJOR RECONSTRUCTION) | MAH | 3 | Karvo Companies Inc | $21,127,840 | $22,330,414 | +6.0% | +13% | ODOT |
| 260124 | HAM-IR 74-07.05 (FOUR LANE RESURFACING) | HAM | 2 | Barrett Paving Materials Inc | $9,582,695 | $11,372,870 | +19% | -6.0% | ODOT |
| 260148 | FRA-IR 270-32.92 at Easton Way (INTERCHANGE) | FRA | 3 | Complete General Construction Company | $5,189,580 | $5,505,688 | +6.0% | +4.0% | ODOT |
| 260156 | LOG-US 33-09.58 (INTERSECTION) | LOG | 5 | Eagle Bridge Co | $3,999,678 | $4,619,919 | +16% | -11% | ODOT |
| 260145 | D08-Noise Walls FY2026 (NOISE WALLS) | District 8 | 3 | Complete General Construction Company | $3,187,506 | $3,765,785 | +18% | +27% | ODOT |
| 260155 | LIC-CR 803-00.88 (PART 1 AND PART 2) (BIKEWAYS) | LIC | 3 | Rietschlin Construction Inc | $2,696,421 | $2,722,746 | +1.0% | -4.0% | ODOT |
| 260161 | D08-PM/RPM-FY2026 (PAVEMENT MARKING) | District 8 | 2 | Oglesby Construction Inc | $2,495,584 | $2,952,000 | +18% | -32% | ODOT |
| 260121 | HAM-CR 158/CR 460-02.04/00.54 (INTERSECTION) | HAM | 4 | Sunesis Construction Co | $2,411,597 | $2,412,139 | 0.0% | +6.0% | ODOT |
| 260146 | D12-GR FY2026 (GUARDRAIL REBUILDING) | District 12 | 1 | Lake Erie Construction Company | $2,388,850 | +5.0% | ODOT | ||
| 260151 | HAS-SR 151-00.00 (TWO LANE RESURFACING) | HAS | 3 | Shelly & Sands Inc | $2,367,377 | $2,537,826 | +7.0% | -5.0% | ODOT |
| 260150 | HAM-IR 71-05.05 (BRIDGE REPAIR) | HAM | 2 | Prus Construction Company | $2,276,738 | $2,292,994 | +1.0% | +29% | ODOT |
| 260162 | D10-Pavement Marking FY2026 (PAVEMENT MARKING) | District 10 | 3 | Oglesby Construction Inc | $2,198,543 | $2,327,000 | +6.0% | -18% | ODOT |
| 260154 | LAW-US 52-21.52 (INTERSECTION) | LAW | 2 | Shelly Company | $2,110,991 | $2,519,261 | +19% | +34% | ODOT |
| 260143 | AUG-SR 501/SR 198-02.32/02.36 (INTERSECTION) | AUG | 2 | Miller Contracting Group Inc | $1,699,234 | $2,166,924 | +28% | +11% | ODOT |
| 260160 | D04-PM/RPM FY2026 (West) (PAVEMENT MARKING) | District 4 | 3 | The Aero-Mark Company LLC | $1,653,000 | $1,816,597 | +10% | -24% | ODOT |
| 260149 | HAM-CR 196-01.89 Delhi Ave (INTERSECTION) | HAM | 4 | Sunesis Construction Co | $1,531,958 | $1,557,456 | +2.0% | +23% | ODOT |
| 260164 | D12-LG FY2026 (LIGHTING) | District 12 | 3 | Ruhlin Company | $1,399,007 | $1,499,832 | +7.0% | +8.0% | ODOT |
| 260166 | ALL-Lafayette Improvements (TWO LANE RESURFACING) | ALL | 2 | R D Jones Excavating Inc | $1,185,353 | $1,581,469 | +33% | -18% | ODOT |
| 260158 | WOO-SR 25-06.64 Resurface Portage (FOUR LANE RESURFACING) | WOO | 2 | Gerken Paving Inc | $1,171,249 | $1,228,439 | +5.0% | -22% | ODOT |
| 260144 | CLE-US 50-02.25 (BRIDGE REPAIR) | CLE | 5 | Prus Construction Company | $655,092 | $662,386 | +1.0% | -16% | ODOT |
| 260159 | CUY-SIGN FY2026 (SIGNING) | CUY | 1 | Lake Erie Construction Company | $477,480 | +17% | ODOT | ||
| 260157 | STA-SR 241-14.58 (SRTS) (SIDEWALK) | STA | 5 | Ruhlin Company | $394,878 | $450,761 | +14% | -15% | ODOT |
| 260163 | D11-RPM-FY2026 (RAISED PAVEMENT MARKERS) | District 11 | 3 | A & A Safety Inc | $270,570 | $289,451 | +7.0% | -13% | ODOT |
| 260153 | LAW-SR 141/CR 7E-02.45 (INTERSECTION) | LAW | 3 | Shelly Company | $257,739 | $272,886 | +6.0% | +13% | ODOT |
| 260165 | MOT-SR 725/Jamaica TSG (SIGNALIZATION) | MOT | 6 | Bansal Construction Inc | $199,365 | $200,490 | +1.0% | -2.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.