ODOT contract 260150 bid tabulation

HAM-IR 71-05.05 (BRIDGE REPAIR). Let by Ohio DOT on March 26, 2026, HAM. 2 bids received; low bid $2,276,738 by Prus Construction Company, +29% against the engineer's estimate of $1,760,000.

Owner
Ohio DOT
Letting
26 MAR 2026
Pay items
73
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Prus Construction Company$2,276,738Low+29%
2Vimas Painting Company Inc$2,292,994+1.0%+30%
ODOT contract 260150: bids by rank

Engineer's estimate: $1,760,000.

Bid tabulation

LinePay itemUnitQuantity1. Prus Construction Company2. Vimas Painting Company Inc
1Clearing and grubbing (201E11000)LS1$15,250$20,000
2Pavement removed (202E23000)SY18$90.00$100.00
3Curb removed (202E32000)FT79$25.00$30.00
4Pipe removed, 24" and under (202E35100)FT25$68.00$72.00
5Guardrail removed (202E38000)FT262.50$10.00$3.00
6Anchor assembly removed, type E (202E42010)EACH1$137.50$200.00
7Anchor assembly removed, type T (202E42040)EACH1$110.00$200.00
8Catch basin removed (202E58100)EACH2$720.00$800.00
9Excavation (203E10000)CY80$75.50$80.00
10Subgrade compaction (204E10000)SY42$8.50$10.00
11Unclassified excavation (503E21300)LS1$3,500.00$4,300.00
12Guardrail, type MGS (606E15050)FT237.50$34.15$24.00
13Post end anchor (or concrete block end anchor) (606E17500)EACH1$348.00$3,000.00
14Anchor assembly, MGS type T (606E26550)EACH1$1,375.00$2,000.00
15MGS bridge terminal assembly, type 1 (606E35002)EACH1$2,695.00$4,000.00
16Guardrail, misc.: MGS guardrail, buried in backslo (606E98000)FT124.04$53.00$37.00
17Topsoil (659E00300)CY134$87.00$50.00
18Seeding and mulching (659E10000)SY1,210$4.75$5.00
19Repair seeding and mulching (659E14000)SY61$3.85$5.00
20Commercial fertilizer (659E20000)TON0.16$1,100.00$1,000.00
21Lime (659E31000)ACRE0.25$68.00$100.00
22Water (659E35000)MGAL6.70$1.10$100.00
23Erosion control (832E30000)EACH5,000$1.00$1.00
24Concrete masonry (602E20000)CY5$705.00$800.00
256" conduit, type F for underdrain outlets (611E00510)FT30$50.00$55.00
2615" conduit, type B (611E05900)FT25$365.00$420.00
27Inlet, no. 3 for single slope barrier, type D (611E99114)EACH2$18,550$20,000
28Aggregate base (304E20000)CY9.50$175.00$200.00
2910" non-reinforced concrete pavement, class QC MS (452E14050)SY35$255.00$300.00
30Barrier reflector, type 1 (one-way) (626E00102)EACH3$16.50$12.00
31Barrier reflector, type 5 (one-way) (626E00116)EACH16$15.50$17.00
32Lane line, 4", type 1 (642E00200)MI0.12$7,150.00$7,000.00
33Center line, type 1 (642E00300)MI0.06$7,150.00$7,000.00
34Trench, 30" deep, as per plan (625E29011)FT520$18.15$18.00
35Pull box, misc.: reuse existing pull box (625E31600)EACH9$1,100.00$1,200.00
36Underground warning marking tape (625E36010)FT520$1.95$2.00
37Fiber optic cable, 72 fiber (804E15030)FT3,560$9.00$9.00
38ITS pull box with pad and standard lid assembly, 3 (809E01900)EACH1$3,905.00$4,000.00
39Tracer wire (809E10000)FT520$2.25$3.00
40Conduit, 4", multicell, HDPE with 4 - 1" innerducts (809E24500)FT520$55.00$55.00
41Maintaining ITS during construction (809E70000)LS1$1.10$2,500.00
42Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384)EACH3$2,465.00$2,400.00
43Barrier reflector, type 1 (BI-directional) (614E13310)EACH12$13.50$15.00
44Object marker, one way (614E13350)EACH12$23.75$25.00
45Portable barrier, unanchored (622E41100)FT660$41.00$40.00
46Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$18,000$22,000
47Concrete slope protection removed (202E32800)SY40$55.00$65.00
48Sealing of concrete surfaces, as per plan (512E10001)SY1,321$60.00$62.00
49Sealing of concrete surfaces (non-epoxy) (512E10050)SY468$18.00$20.00
50Treating concrete bridge decks with gravity fed resin (512E73500)SY1,587$35.00$36.00
51Removal of existing coatings from concrete surfaces (512E74000)SY1,789$24.00$26.00
52Surface preparation of existing structural steel (514E00050)SF42,042$13.25$13.00
53Field painting of existing structural steel, prime coat (514E00056)SF42,042$5.50$4.00
54Field painting structural steel, intermediate coat (514E00060)SF42,042$3.30$4.00
55Field painting structural steel, finish coat (514E00066)SF42,042$2.25$4.00
56Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR5$220.00$250.00
57Final inspection repair (514E10000)EACH10$220.00$400.00
58Elastomeric strip seal without steel extrusions (516E01300)FT100$180.00$200.00
59Sidewalk cover plate (516E12310)LB997$15.00$25.00
60Special - composite fiber wrap system (519E00100)SF112$65.00$70.00
61Patching concrete structure, as per plan (519E11101)SF1,155$168.00$180.00
62Concrete slope protection (601E21000)SY40$150.00$180.00
63Fence, misc.: vandal protection fence rebuilt (607E98000)FT1,029$27.50$94.00
64Concrete barrier end section, type D, as per plan (622E25001)EACH1$12,450$15,000
65Concrete barrier, end anchorage, reinforced, type D, as per plan (622E25051)EACH1$8,800.00$10,000
66Special - misc.: drainage system cleaning, 36" and (690E98600)HR10$450.00$500.00
67Galvanic anode protection (844E20000)EACH199$70.00$80.00
68Premium for contract performance bond and for payment bond (103E05000)LS1$8,900.00$40,000
69Maintaining traffic (614E11000)LS1$310,000$140,000
70Construction layout stakes and surveying, as per plan (623E10001)LS1$6,500.00$5,000.00
71Mobilization (624E10000)LS1$100,000$100,000
1006" pipe downspout, including specials (518E43300)FT55$322.00$400.00
101Law enforcement officer with patrol car for assistance (614E11110)HR250$132.00$110.00
ODOT contract 260150: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of March 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy