ODOT contract 260149 bid tabulation

HAM-CR 196-01.89 Delhi Ave (INTERSECTION). Let by Ohio DOT on March 26, 2026, HAM. 4 bids received; low bid $1,531,958 by Sunesis Construction Co, +23% against the engineer's estimate of $1,245,000.

Owner
Ohio DOT
Letting
26 MAR 2026
Pay items
120
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Sunesis Construction Co$1,531,958Low+23%
2Prus Construction Company$1,557,456+2.0%+25%
3John R Jurgensen Company$1,594,615+4.0%+28%
4Barrett Paving Materials Inc$1,663,561+9.0%+34%
ODOT contract 260149: bids by rank

Engineer's estimate: $1,245,000.

Bid tabulation

LinePay itemUnitQuantity1. Sunesis Construction Co2. Prus Construction Company3. John R Jurgensen Company4. Barrett Paving Materials Inc
1Clearing and grubbing (201E11000)LS1$11,534$3,156.75$14,975$10,000
2Pavement removed (202E23000)SY654$30.68$26.62$46.49$30.00
3Walk removed (202E30000)SF1,661$2.50$4.20$7.39$5.00
4Curb removed (202E32000)FT290$17.70$20.11$21.82$22.00
5Pipe removed, 24" and under (202E35100)FT291$27.32$79.52$81.80$35.00
6Manhole removed (202E58000)EACH1$1,261.47$1,775.43$3,521.38$1,000.00
7Fence removed (202E75000)FT11$24.47$30.84$40.00$6.00
8Excavation (203E10000)CY370$77.07$45.87$90.08$85.00
9Embankment (203E20000)CY123$40.20$39.22$56.91$80.00
10Granular embankment (203E35000)CY15$176.17$238.09$233.89$175.00
11Subgrade compaction (204E10000)SY1,099$5.62$4.47$4.35$7.50
12Proof rolling (204E45000)HR2$390.78$153.59$309.20$2,500.00
13Geotextile fabric (204E50000)SY1,092$2.23$4.47$4.62$2.50
14Railing, misc.: decorative railing (517E76300)FT140$96.00$110.13$96.00$96.00
155" concrete walk (608E12000)SF3,166$13.38$12.56$15.81$14.50
16Curb ramp (608E52000)SF690$17.55$22.93$18.22$16.00
17Topsoil (659E00300)CY15$194.26$106.33$171.69$175.00
18Seeding and mulching (659E10000)SY140$10.11$2.19$35.00$10.00
19Commercial fertilizer (659E20000)TON0.02$1,000.00$1,650.00$1,500.00$2,000.00
20Lime (659E31000)ACRE0.03$1,000.00$550.00$200.00$500.00
21Water (659E35000)MGAL0.80$1.39$1.10$3.00$1.00
22Mowing (659E40000)MSF0.30$100.00$110.00$1,800.00$500.00
23Erosion control (832E30000)EACH5,000$1.00$1.00$1.00$1.00
246" shallow pipe underdrains with geotextile fabric (605E11110)FT642$24.67$30.18$52.60$40.00
256" conduit, type F for underdrain outlets (611E00510)FT68$26.87$57.51$78.14$50.00
2612" conduit, type B (611E04400)FT49$305.43$170.24$236.92$185.00
2718" conduit, type B (611E07400)FT229$257.72$200.77$165.60$195.00
28Catch basin, no. 3A (611E98180)EACH2$4,397.02$5,096.42$3,994.95$5,000.00
29Catch basin adjusted to grade (611E98630)EACH1$924.32$1,384.31$1,533.41$3,000.00
30Manhole, no. 3 (611E99574)EACH2$4,903.86$7,659.26$5,561.96$7,500.00
31Asphalt concrete base, PG64-22, (449) (301E56000)CY256$530.00$274.42$530.00$525.00
32Aggregate base (304E20000)CY200$161.88$115.09$184.98$200.00
33Non-tracking tack coat (407E20000)GAL100$5.00$17.49$5.00$4.00
34Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY44$820.00$493.06$820.00$800.00
35Asphalt concrete intermediate course, type 1, (449) (441E70200)CY43$830.00$663.18$830.00$700.00
36Curb, type 6 (609E26000)FT553$50.67$36.96$57.64$55.00
38Manhole adjusted to grade (611E99654)EACH3$1,113.78$923.82$1,533.41$1,500.00
39Special - gas valve box adjusted to grade (611E99700)EACH4$112.30$807.92$1,533.40$800.00
40Ground mounted support, no. 3 post (630E03100)FT51.50$15.50$18.70$17.00$17.00
41Sign post reflector (630E08600)EACH1$50.00$55.00$50.00$50.00
42Sign hanger assembly, mast arm (630E79100)EACH18$449.10$236.50$215.00$215.00
43Sign support assembly, pole mounted (630E79500)EACH4$55.00$115.50$105.00$105.00
44Sign, flat sheet (630E80100)SF171.30$16.00$25.30$23.00$23.00
45Removal of ground mounted sign and disposal (630E84900)EACH10$15.00$16.50$15.00$15.00
46Removal of ground mounted post support and disposal (630E86002)EACH8$20.00$27.50$25.00$25.00
47Center line (644E00300)MI0.05$18,000$19,800$18,000$18,000
48Channelizing line, 8" (644E00400)FT192$3.00$3.30$3.00$3.00
49Stop line (644E00500)FT71$12.00$13.20$12.00$12.00
50Crosswalk line, 12" (644E00620)FT413$7.00$7.70$7.00$7.00
51Lane arrow (644E01300)EACH3$210.00$231.00$210.00$210.00
52Removal of pavement marking (644E30000)FT160$16.45$18.10$16.45$16.45
53Connection, fused pull apart (625E00450)EACH4$120.77$132.00$120.00$130.00
54Connection, unfused pull apart (625E00460)EACH8$120.77$132.00$120.00$130.00
55Connection, unfused permanent (625E00480)EACH4$120.77$132.00$120.00$130.00
56Bracket arm, 20', as per plan (625E18401)EACH1$1,761.28$1,925.00$1,750.00$2,200.00
57Bracket arm, 30', as per plan (625E18511)EACH4$3,180.38$3,476.00$3,160.00$3,600.00
58No. 8 AWG 600 volt distribution cable (625E23304)FT1,008$2.16$2.37$2.15$5.00
59No. 10 AWG pole and bracket cable (625E23400)FT753$2.01$2.20$2.00$3.00
60Conduit, 2", 725.051 (625E25408)FT66$6.29$6.88$6.25$14.00
61Conduit, 4", 725.051 (625E25604)FT95$11.98$13.09$11.90$22.00
62Conduit, jacked or drilled, 725.052, 4" (625E25908)FT465$77.50$84.70$77.00$68.00
63Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH5$478.06$522.50$475.00$650.00
64Trench, 24" deep (625E29002)FT147$16.35$17.88$16.25$18.00
65Pull box, 725.08, 24" (625E30706)EACH10$1,313.41$1,435.50$1,305.00$1,650.00
66Ground rod (625E32000)EACH15$493.16$539.00$490.00$300.00
67Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH14$1,363.74$1,490.50$1,355.00$1,600.00
68Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007)EACH4$1,489.54$1,628.00$1,480.00$1,700.00
69Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086)EACH2$2,143.74$2,343.00$2,130.00$2,375.00
70Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH12$674.32$737.00$670.00$850.00
71Covering of vehicular signal head (632E25000)EACH20$85.55$93.50$85.00$50.00
72Covering of pedestrian signal head (632E25010)EACH12$85.55$93.50$85.00$40.00
73Signal cable, 5 conductor, no. 14 AWG (632E40500)FT1,814$2.47$2.70$2.45$3.50
74Signal cable, 7 conductor, no. 14 AWG (632E40700)FT2,182$2.62$2.86$2.60$4.00
75Signal support foundation (632E64010)EACH6$8,031.45$8,778.00$7,980.00$14,500
76Pedestal foundation, as per plan (632E64021)EACH7$2,999.21$3,278.00$2,980.00$1,500.00
77Loop detector lead-in cable, 2 conductor, no. 14 AWG (632E65300)FT1,754$2.16$2.37$2.15$3.00
78Power cable, 3 conductor, no. 10 AWG (632E66104)FT47$6.14$6.71$6.10$7.00
79Service cable, 3 conductor, no. 6 AWG (632E69800)FT224$7.25$7.92$7.20$9.00
80Power service, as per plan (632E70001)EACH2$6,390.95$6,985.00$6,350.00$2,700.00
81Signal support, type TC-12.31 design 10 pole, with mast arms TC-81.22 design 14 and design 12, as per plan (632E71389)EACH1$39,322$42,977$39,070$40,000
82Signal support, type TC-81.22, design 13, as per plan (632E72141)EACH1$22,097$24,151$21,955$22,900
83Combination signal support, type TC-12.31 design 1 (632E78349)EACH1$41,858$45,749$41,590$36,400
84Combination signal support, type TC-81.22, design 4, as per plan (632E79111)EACH3$14,770$16,143$14,675$17,500
85Pedestal, 10.7' tall, transformer base, as per plan (632E89921)EACH7$2,304.77$2,519.00$2,290.00$2,400.00
86Removal of traffic signal installation, as per plan (632E90101)EACH2$5,349.27$5,846.50$5,315.00$4,500.00
87Signalization, misc.: vacuum excavation of foundat (632E90400)EACH4$2,465.80$2,695.00$2,450.00$4,200.00
88Cabinet, type 332, as per plan (633E65521)EACH2$22,529$24,624$22,385$19,300
89Cabinet foundation, as per plan (633E67101)EACH2$1,982.70$2,167.00$1,970.00$3,200.00
90Controller work pad (633E67200)EACH2$1,358.71$1,485.00$1,350.00$850.00
96Accessible pedestrian pushbutton (632E20750)EACH12$800.13$874.50$795.00$1,500.00
97GPS (global positioning system) clock assembly (633E45000)EACH2$1,157.42$1,265.00$1,150.00$1,850.00
98Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001)EACH2$7,432.62$8,123.50$7,385.00$6,000.00
99Stop line radar detection, as per plan (809E69101)EACH8$8,303.20$9,075.00$8,250.00$11,100
100Atc controller, as per plan (809E69123)EACH2$5,802.17$6,341.50$5,765.00$7,800.00
101Law enforcement officer with patrol car for assistance (614E11110)HR16$110.00$157.82$169.88$100.00
102Special - work zone traffic signal (614E11300)EACH1$54,348$59,400$54,000$68,000
104Maintaining traffic, misc.:temporary signal vehicl (614E18002)LS1$10,000$11,000$10,000$48,000
105Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY75$50.00$66.61$50.00$50.00
106Joint sealer (516E31000)FT25$40.00$23.59$40.00$40.00
107Porous backfill with geotextile fabric (518E21200)CY20$244.56$146.50$237.46$240.00
108Prefabricated modular retaining wall, as per plan (870E10001)SF538$101.21$85.69$112.87$105.00
109Wall excavation (870E11000)CY33$88.64$97.46$111.64$115.00
110Natural soil (870E11100)CY7$114.38$117.58$245.94$150.00
1116" drainage pipe, perforated (870E12000)FT140$4.28$11.00$20.49$16.00
1126" drainage pipe, non-perforated (870E12100)FT12$43.59$63.08$119.50$50.00
113Concrete coping (870E12500)FT140$261.79$248.76$105.15$160.00
114On-site assistance (870E14000)DAY2$0.02$305.00$400.00$1,000.00
115PMRW inspection and compaction testing (870E15000)LS1$2,099.50$1,272.70$2,308.00$2,500.00
116Premium for contract performance bond and for payment bond (103E05000)LS1$9,229.19$18,300$7,342.26$4,500.00
117CPM progress schedule (108E10000)LS1$4,580.00$5,185.00$5,915.63$3,000.00
118Maintaining traffic (614E11000)LS1$18,500$198,306$66,444$60,000
119Construction layout stakes and surveying (623E10000)LS1$11,400$10,560$9,323.62$15,000
120Mobilization (624E10000)LS1$106,168$40,000$75,000$40,000
200Roads for maintaining traffic (615E10000)LS1$16,723$2,211.34$4,750.52$20,000
201Pavement for maintaining traffic, class B (615E25000)SY220$165.00$111.18$165.00$225.00
202Special -adjust existing chamber to grade (690E98000)EACH1$1,291.04$706.97$3,492.35$1,500.00
203Special - furnishing and installing 6? plug in exi (690E98000)EACH1$9,038.08$2,439.34$6,246.12$7,000.00
204Special -removing existing manhole curb and cover (690E98000)EACH1$2,424.61$1,080.79$3,521.38$3,000.00
205Special -removing existing valuve box (690E98000)EACH1$1,783.48$559.53$1,434.99$350.00
206Special -removing fire hydrant (690E98000)EACH1$1,657.39$879.96$2,130.43$1,500.00
ODOT contract 260149: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of March 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy