ODOT contract 260149 bid tabulation
HAM-CR 196-01.89 Delhi Ave (INTERSECTION). Let by Ohio DOT on March 26, 2026, HAM. 4 bids received; low bid $1,531,958 by Sunesis Construction Co, +23% against the engineer's estimate of $1,245,000.
- Owner
- Ohio DOT
- Letting
- 26 MAR 2026
- Pay items
- 120
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sunesis Construction Co | $1,531,958 | Low | +23% |
| 2 | Prus Construction Company | $1,557,456 | +2.0% | +25% |
| 3 | John R Jurgensen Company | $1,594,615 | +4.0% | +28% |
| 4 | Barrett Paving Materials Inc | $1,663,561 | +9.0% | +34% |
Engineer's estimate: $1,245,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sunesis Construction Co | 2. Prus Construction Company | 3. John R Jurgensen Company | 4. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $11,534 | $3,156.75 | $14,975 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 654 | $30.68 | $26.62 | $46.49 | $30.00 |
| 3 | Walk removed (202E30000) | SF | 1,661 | $2.50 | $4.20 | $7.39 | $5.00 |
| 4 | Curb removed (202E32000) | FT | 290 | $17.70 | $20.11 | $21.82 | $22.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 291 | $27.32 | $79.52 | $81.80 | $35.00 |
| 6 | Manhole removed (202E58000) | EACH | 1 | $1,261.47 | $1,775.43 | $3,521.38 | $1,000.00 |
| 7 | Fence removed (202E75000) | FT | 11 | $24.47 | $30.84 | $40.00 | $6.00 |
| 8 | Excavation (203E10000) | CY | 370 | $77.07 | $45.87 | $90.08 | $85.00 |
| 9 | Embankment (203E20000) | CY | 123 | $40.20 | $39.22 | $56.91 | $80.00 |
| 10 | Granular embankment (203E35000) | CY | 15 | $176.17 | $238.09 | $233.89 | $175.00 |
| 11 | Subgrade compaction (204E10000) | SY | 1,099 | $5.62 | $4.47 | $4.35 | $7.50 |
| 12 | Proof rolling (204E45000) | HR | 2 | $390.78 | $153.59 | $309.20 | $2,500.00 |
| 13 | Geotextile fabric (204E50000) | SY | 1,092 | $2.23 | $4.47 | $4.62 | $2.50 |
| 14 | Railing, misc.: decorative railing (517E76300) | FT | 140 | $96.00 | $110.13 | $96.00 | $96.00 |
| 15 | 5" concrete walk (608E12000) | SF | 3,166 | $13.38 | $12.56 | $15.81 | $14.50 |
| 16 | Curb ramp (608E52000) | SF | 690 | $17.55 | $22.93 | $18.22 | $16.00 |
| 17 | Topsoil (659E00300) | CY | 15 | $194.26 | $106.33 | $171.69 | $175.00 |
| 18 | Seeding and mulching (659E10000) | SY | 140 | $10.11 | $2.19 | $35.00 | $10.00 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.02 | $1,000.00 | $1,650.00 | $1,500.00 | $2,000.00 |
| 20 | Lime (659E31000) | ACRE | 0.03 | $1,000.00 | $550.00 | $200.00 | $500.00 |
| 21 | Water (659E35000) | MGAL | 0.80 | $1.39 | $1.10 | $3.00 | $1.00 |
| 22 | Mowing (659E40000) | MSF | 0.30 | $100.00 | $110.00 | $1,800.00 | $500.00 |
| 23 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | 6" shallow pipe underdrains with geotextile fabric (605E11110) | FT | 642 | $24.67 | $30.18 | $52.60 | $40.00 |
| 25 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 68 | $26.87 | $57.51 | $78.14 | $50.00 |
| 26 | 12" conduit, type B (611E04400) | FT | 49 | $305.43 | $170.24 | $236.92 | $185.00 |
| 27 | 18" conduit, type B (611E07400) | FT | 229 | $257.72 | $200.77 | $165.60 | $195.00 |
| 28 | Catch basin, no. 3A (611E98180) | EACH | 2 | $4,397.02 | $5,096.42 | $3,994.95 | $5,000.00 |
| 29 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $924.32 | $1,384.31 | $1,533.41 | $3,000.00 |
| 30 | Manhole, no. 3 (611E99574) | EACH | 2 | $4,903.86 | $7,659.26 | $5,561.96 | $7,500.00 |
| 31 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 256 | $530.00 | $274.42 | $530.00 | $525.00 |
| 32 | Aggregate base (304E20000) | CY | 200 | $161.88 | $115.09 | $184.98 | $200.00 |
| 33 | Non-tracking tack coat (407E20000) | GAL | 100 | $5.00 | $17.49 | $5.00 | $4.00 |
| 34 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 44 | $820.00 | $493.06 | $820.00 | $800.00 |
| 35 | Asphalt concrete intermediate course, type 1, (449) (441E70200) | CY | 43 | $830.00 | $663.18 | $830.00 | $700.00 |
| 36 | Curb, type 6 (609E26000) | FT | 553 | $50.67 | $36.96 | $57.64 | $55.00 |
| 38 | Manhole adjusted to grade (611E99654) | EACH | 3 | $1,113.78 | $923.82 | $1,533.41 | $1,500.00 |
| 39 | Special - gas valve box adjusted to grade (611E99700) | EACH | 4 | $112.30 | $807.92 | $1,533.40 | $800.00 |
| 40 | Ground mounted support, no. 3 post (630E03100) | FT | 51.50 | $15.50 | $18.70 | $17.00 | $17.00 |
| 41 | Sign post reflector (630E08600) | EACH | 1 | $50.00 | $55.00 | $50.00 | $50.00 |
| 42 | Sign hanger assembly, mast arm (630E79100) | EACH | 18 | $449.10 | $236.50 | $215.00 | $215.00 |
| 43 | Sign support assembly, pole mounted (630E79500) | EACH | 4 | $55.00 | $115.50 | $105.00 | $105.00 |
| 44 | Sign, flat sheet (630E80100) | SF | 171.30 | $16.00 | $25.30 | $23.00 | $23.00 |
| 45 | Removal of ground mounted sign and disposal (630E84900) | EACH | 10 | $15.00 | $16.50 | $15.00 | $15.00 |
| 46 | Removal of ground mounted post support and disposal (630E86002) | EACH | 8 | $20.00 | $27.50 | $25.00 | $25.00 |
| 47 | Center line (644E00300) | MI | 0.05 | $18,000 | $19,800 | $18,000 | $18,000 |
| 48 | Channelizing line, 8" (644E00400) | FT | 192 | $3.00 | $3.30 | $3.00 | $3.00 |
| 49 | Stop line (644E00500) | FT | 71 | $12.00 | $13.20 | $12.00 | $12.00 |
| 50 | Crosswalk line, 12" (644E00620) | FT | 413 | $7.00 | $7.70 | $7.00 | $7.00 |
| 51 | Lane arrow (644E01300) | EACH | 3 | $210.00 | $231.00 | $210.00 | $210.00 |
| 52 | Removal of pavement marking (644E30000) | FT | 160 | $16.45 | $18.10 | $16.45 | $16.45 |
| 53 | Connection, fused pull apart (625E00450) | EACH | 4 | $120.77 | $132.00 | $120.00 | $130.00 |
| 54 | Connection, unfused pull apart (625E00460) | EACH | 8 | $120.77 | $132.00 | $120.00 | $130.00 |
| 55 | Connection, unfused permanent (625E00480) | EACH | 4 | $120.77 | $132.00 | $120.00 | $130.00 |
| 56 | Bracket arm, 20', as per plan (625E18401) | EACH | 1 | $1,761.28 | $1,925.00 | $1,750.00 | $2,200.00 |
| 57 | Bracket arm, 30', as per plan (625E18511) | EACH | 4 | $3,180.38 | $3,476.00 | $3,160.00 | $3,600.00 |
| 58 | No. 8 AWG 600 volt distribution cable (625E23304) | FT | 1,008 | $2.16 | $2.37 | $2.15 | $5.00 |
| 59 | No. 10 AWG pole and bracket cable (625E23400) | FT | 753 | $2.01 | $2.20 | $2.00 | $3.00 |
| 60 | Conduit, 2", 725.051 (625E25408) | FT | 66 | $6.29 | $6.88 | $6.25 | $14.00 |
| 61 | Conduit, 4", 725.051 (625E25604) | FT | 95 | $11.98 | $13.09 | $11.90 | $22.00 |
| 62 | Conduit, jacked or drilled, 725.052, 4" (625E25908) | FT | 465 | $77.50 | $84.70 | $77.00 | $68.00 |
| 63 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 5 | $478.06 | $522.50 | $475.00 | $650.00 |
| 64 | Trench, 24" deep (625E29002) | FT | 147 | $16.35 | $17.88 | $16.25 | $18.00 |
| 65 | Pull box, 725.08, 24" (625E30706) | EACH | 10 | $1,313.41 | $1,435.50 | $1,305.00 | $1,650.00 |
| 66 | Ground rod (625E32000) | EACH | 15 | $493.16 | $539.00 | $490.00 | $300.00 |
| 67 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 14 | $1,363.74 | $1,490.50 | $1,355.00 | $1,600.00 |
| 68 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007) | EACH | 4 | $1,489.54 | $1,628.00 | $1,480.00 | $1,700.00 |
| 69 | Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086) | EACH | 2 | $2,143.74 | $2,343.00 | $2,130.00 | $2,375.00 |
| 70 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 12 | $674.32 | $737.00 | $670.00 | $850.00 |
| 71 | Covering of vehicular signal head (632E25000) | EACH | 20 | $85.55 | $93.50 | $85.00 | $50.00 |
| 72 | Covering of pedestrian signal head (632E25010) | EACH | 12 | $85.55 | $93.50 | $85.00 | $40.00 |
| 73 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 1,814 | $2.47 | $2.70 | $2.45 | $3.50 |
| 74 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 2,182 | $2.62 | $2.86 | $2.60 | $4.00 |
| 75 | Signal support foundation (632E64010) | EACH | 6 | $8,031.45 | $8,778.00 | $7,980.00 | $14,500 |
| 76 | Pedestal foundation, as per plan (632E64021) | EACH | 7 | $2,999.21 | $3,278.00 | $2,980.00 | $1,500.00 |
| 77 | Loop detector lead-in cable, 2 conductor, no. 14 AWG (632E65300) | FT | 1,754 | $2.16 | $2.37 | $2.15 | $3.00 |
| 78 | Power cable, 3 conductor, no. 10 AWG (632E66104) | FT | 47 | $6.14 | $6.71 | $6.10 | $7.00 |
| 79 | Service cable, 3 conductor, no. 6 AWG (632E69800) | FT | 224 | $7.25 | $7.92 | $7.20 | $9.00 |
| 80 | Power service, as per plan (632E70001) | EACH | 2 | $6,390.95 | $6,985.00 | $6,350.00 | $2,700.00 |
| 81 | Signal support, type TC-12.31 design 10 pole, with mast arms TC-81.22 design 14 and design 12, as per plan (632E71389) | EACH | 1 | $39,322 | $42,977 | $39,070 | $40,000 |
| 82 | Signal support, type TC-81.22, design 13, as per plan (632E72141) | EACH | 1 | $22,097 | $24,151 | $21,955 | $22,900 |
| 83 | Combination signal support, type TC-12.31 design 1 (632E78349) | EACH | 1 | $41,858 | $45,749 | $41,590 | $36,400 |
| 84 | Combination signal support, type TC-81.22, design 4, as per plan (632E79111) | EACH | 3 | $14,770 | $16,143 | $14,675 | $17,500 |
| 85 | Pedestal, 10.7' tall, transformer base, as per plan (632E89921) | EACH | 7 | $2,304.77 | $2,519.00 | $2,290.00 | $2,400.00 |
| 86 | Removal of traffic signal installation, as per plan (632E90101) | EACH | 2 | $5,349.27 | $5,846.50 | $5,315.00 | $4,500.00 |
| 87 | Signalization, misc.: vacuum excavation of foundat (632E90400) | EACH | 4 | $2,465.80 | $2,695.00 | $2,450.00 | $4,200.00 |
| 88 | Cabinet, type 332, as per plan (633E65521) | EACH | 2 | $22,529 | $24,624 | $22,385 | $19,300 |
| 89 | Cabinet foundation, as per plan (633E67101) | EACH | 2 | $1,982.70 | $2,167.00 | $1,970.00 | $3,200.00 |
| 90 | Controller work pad (633E67200) | EACH | 2 | $1,358.71 | $1,485.00 | $1,350.00 | $850.00 |
| 96 | Accessible pedestrian pushbutton (632E20750) | EACH | 12 | $800.13 | $874.50 | $795.00 | $1,500.00 |
| 97 | GPS (global positioning system) clock assembly (633E45000) | EACH | 2 | $1,157.42 | $1,265.00 | $1,150.00 | $1,850.00 |
| 98 | Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001) | EACH | 2 | $7,432.62 | $8,123.50 | $7,385.00 | $6,000.00 |
| 99 | Stop line radar detection, as per plan (809E69101) | EACH | 8 | $8,303.20 | $9,075.00 | $8,250.00 | $11,100 |
| 100 | Atc controller, as per plan (809E69123) | EACH | 2 | $5,802.17 | $6,341.50 | $5,765.00 | $7,800.00 |
| 101 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 16 | $110.00 | $157.82 | $169.88 | $100.00 |
| 102 | Special - work zone traffic signal (614E11300) | EACH | 1 | $54,348 | $59,400 | $54,000 | $68,000 |
| 104 | Maintaining traffic, misc.:temporary signal vehicl (614E18002) | LS | 1 | $10,000 | $11,000 | $10,000 | $48,000 |
| 105 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 75 | $50.00 | $66.61 | $50.00 | $50.00 |
| 106 | Joint sealer (516E31000) | FT | 25 | $40.00 | $23.59 | $40.00 | $40.00 |
| 107 | Porous backfill with geotextile fabric (518E21200) | CY | 20 | $244.56 | $146.50 | $237.46 | $240.00 |
| 108 | Prefabricated modular retaining wall, as per plan (870E10001) | SF | 538 | $101.21 | $85.69 | $112.87 | $105.00 |
| 109 | Wall excavation (870E11000) | CY | 33 | $88.64 | $97.46 | $111.64 | $115.00 |
| 110 | Natural soil (870E11100) | CY | 7 | $114.38 | $117.58 | $245.94 | $150.00 |
| 111 | 6" drainage pipe, perforated (870E12000) | FT | 140 | $4.28 | $11.00 | $20.49 | $16.00 |
| 112 | 6" drainage pipe, non-perforated (870E12100) | FT | 12 | $43.59 | $63.08 | $119.50 | $50.00 |
| 113 | Concrete coping (870E12500) | FT | 140 | $261.79 | $248.76 | $105.15 | $160.00 |
| 114 | On-site assistance (870E14000) | DAY | 2 | $0.02 | $305.00 | $400.00 | $1,000.00 |
| 115 | PMRW inspection and compaction testing (870E15000) | LS | 1 | $2,099.50 | $1,272.70 | $2,308.00 | $2,500.00 |
| 116 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $9,229.19 | $18,300 | $7,342.26 | $4,500.00 |
| 117 | CPM progress schedule (108E10000) | LS | 1 | $4,580.00 | $5,185.00 | $5,915.63 | $3,000.00 |
| 118 | Maintaining traffic (614E11000) | LS | 1 | $18,500 | $198,306 | $66,444 | $60,000 |
| 119 | Construction layout stakes and surveying (623E10000) | LS | 1 | $11,400 | $10,560 | $9,323.62 | $15,000 |
| 120 | Mobilization (624E10000) | LS | 1 | $106,168 | $40,000 | $75,000 | $40,000 |
| 200 | Roads for maintaining traffic (615E10000) | LS | 1 | $16,723 | $2,211.34 | $4,750.52 | $20,000 |
| 201 | Pavement for maintaining traffic, class B (615E25000) | SY | 220 | $165.00 | $111.18 | $165.00 | $225.00 |
| 202 | Special -adjust existing chamber to grade (690E98000) | EACH | 1 | $1,291.04 | $706.97 | $3,492.35 | $1,500.00 |
| 203 | Special - furnishing and installing 6? plug in exi (690E98000) | EACH | 1 | $9,038.08 | $2,439.34 | $6,246.12 | $7,000.00 |
| 204 | Special -removing existing manhole curb and cover (690E98000) | EACH | 1 | $2,424.61 | $1,080.79 | $3,521.38 | $3,000.00 |
| 205 | Special -removing existing valuve box (690E98000) | EACH | 1 | $1,783.48 | $559.53 | $1,434.99 | $350.00 |
| 206 | Special -removing fire hydrant (690E98000) | EACH | 1 | $1,657.39 | $879.96 | $2,130.43 | $1,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 26, 2026. Compiled by Mirage Metrics.