ODOT contract 260144 bid tabulation

CLE-US 50-02.25 (BRIDGE REPAIR). Let by Ohio DOT on March 26, 2026, CLE. 5 bids received; low bid $655,092 by Prus Construction Company, -16% against the engineer's estimate of $780,000.

Owner
Ohio DOT
Letting
26 MAR 2026
Pay items
56
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Prus Construction Company$655,092Low-16%
2Sunesis Construction Co$662,386+1.0%-15%
3Axis Civil Construction LLC$691,455+6.0%-11%
4KT Holden Construction LLC$755,619+15%-3.0%
5John R Jurgensen Company$1,502,953+129%+93%
ODOT contract 260144: bids by rank

Engineer's estimate: $780,000.

Bid tabulation

LinePay itemUnitQuantity1. Prus Construction Company2. Sunesis Construction Co3. Axis Civil Construction LLC4. KT Holden Construction LLC5. John R Jurgensen Company
1Clearing and grubbing, as per plan (201E11001)LS1$25,500$2,616.86$15,000$29,200$54,072
3Fence removed (202E75000)FT261$6.65$1.84$8.00$6.00$6.00
4Removal misc.: post with electric outlet (202E98100)EACH2$660.00$310.17$1,000.00$500.00$1,323.88
5Excavation (203E10000)CY2,108$46.00$54.75$56.00$49.00$141.24
6Embankment (203E20000)CY23$95.50$25.38$100.00$56.00$100.22
7Gate, type CLT, as per plan (607E61201)EACH1$3,050.00$2,771.00$2,771.00$2,771.00$2,771.00
8Gate, type CLT, as per plan (607E61201)EACH1$5,000.00$4,546.00$4,546.00$4,546.00$4,546.00
9Fence, misc.: gate removal and reinstallation (607E98100)EACH1$2,150.00$1,946.00$1,946.00$1,946.00$1,946.00
10Fence, misc.: temporary chain link fence (607E98200)LS1$5,885.00$5,346.00$5,346.00$5,346.00$5,346.00
11Monument assembly, type D (623E38550)EACH4$1,775.00$2,471.91$2,400.00$650.00$3,076.92
12Right-of-way monument, type B (623E40520)EACH1$585.00$156.09$250.00$175.00$1,055.48
13Special - work involving petroleum contaminated soil (690E65016)TON650$72.50$10.00$101.00$54.50$164.39
14Cofferdams and excavation bracing, as per plan (503E11101)LS1$38,500$38,117$28,000$96,270$101,237
15Class QC1 concrete, misc.: sediment basin (511E53010)CY84$1,050.00$1,309.75$1,150.00$1,250.00$1,471.82
16Porous backfill with geotextile fabric, as per plan (518E21201)CY72$168.00$181.86$140.00$153.00$258.31
176" perforated corrugated plastic pipe (518E40000)FT215$25.00$6.49$15.00$14.00$72.57
186" non-perforated corrugated plastic pipe, including specials (518E40010)FT60$34.00$37.24$25.00$28.00$86.84
19Riprap, type D, as per plan (601E11001)SY400$155.00$225.17$225.00$225.00$760.29
20Rock channel protection, type C with geotextile fabric (601E32204)CY269$108.00$233.64$135.00$200.00$284.13
21Topsoil (659E00300)CY369$83.50$65.00$65.00$65.00$75.91
22Seeding and mulching (659E10000)SY1,767$2.25$3.35$1.75$2.05$2.05
23Seeding and mulching, as per plan (659E10001)SY1,563$2.25$5.00$3.75$2.05$2.05
24Repair seeding and mulching (659E14000)SY88$2.25$3.35$1.00$2.05$2.05
25Repair seeding and mulching, as per plan (659E14001)SY78$2.25$5.00$3.75$2.05$2.05
26Inter-seeding (659E15000)SY88$1.15$3.35$0.01$1.00$1.00
27Inter-seeding, as per plan (659E15001)SY78$1.15$5.00$3.75$1.00$1.00
28Commercial fertilizer (659E20000)TON0.49$1,025.00$760.00$1,500.00$925.00$925.00
29Lime (659E31000)ACRE0.69$85.00$50.00$200.00$75.00$75.00
30Water (659E35000)MGAL19$1.00$50.00$1.00$1.00$1.00
31Erosion control mat, type C (671E15020)SY1,563$7.50$5.00$2.75$6.75$6.75
33Storm water pollution prevention plan (832E15000)LS1$3,750.00$3,400.00$3,400.00$4,000.00$3,400.00
34Storm water pollution prevention inspections (832E15002)LS1$4,275.00$5,830.00$6,420.00$12,840$11,640
35Storm water pollution prevention inspection software (832E15010)LS1$19,950$12,673$16,500$12,700$12,673
36Erosion control (832E30000)EACH15,000$1.00$1.00$1.00$1.00$1.00
3712" conduit, type D (611E04900)FT28$180.00$94.82$125.00$85.00$269.19
38Ground mounted support, no. 3 post (630E03100)FT51$45.00$15.50$15.50$41.00$41.00
39Removal of ground mounted sign and reerection (630E85100)EACH4$61.00$45.00$45.00$55.00$55.00
40Removal of ground mounted post support and disposal (630E86002)EACH4$61.00$25.00$25.00$55.00$55.00
41Signing, misc.:removal and RE-erection of miami to (630E97700)EACH1$358.00$300.00$300.00$325.00$325.00
42Tree seedling, as per plan, 1-gal, american sycamo (661E00101)EACH20$101.00$60.00$115.00$92.00$92.00
43Tree seedling, as per plan, 1-gal, black willow (661E00101)EACH20$101.00$60.00$115.00$92.00$92.00
44Tree seedling, as per plan, 1-gal, eastern cottonw (661E00101)EACH20$101.00$60.00$115.00$92.00$92.00
45Tree seedling, as per plan, 1-gal, silver maple (661E00101)EACH20$101.00$60.00$115.00$92.00$92.00
46Planting, misc.: live stakes, american sycamore (661E99900)EACH125$12.50$35.00$45.00$11.15$11.15
47Planting, misc.: live stakes, arrowwood (661E99900)EACH125$12.50$35.00$45.00$11.15$11.15
48Planting, misc.: live stakes, black willow (661E99900)EACH125$12.50$35.00$45.00$11.15$11.15
49Traffic compacted surface, type A or B (410E12000)CY200$115.00$99.73$110.00$75.00$314.40
50Water (616E10000)MGAL12$55.00$1.37$1.00$37.00$100.03
51Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY8$325.00$218.50$150.00$150.00$150.00
52Concrete repair by epoxy injection (512E10600)FT35$150.00$80.28$150.00$150.00$150.00
53Patching concrete structures with trowelable mortar (843E50000)SF4$225.00$669.16$200.00$200.00$200.00
54Premium for contract performance bond and for payment bond (103E05000)LS1$3,750.00$4,418.43$6,500.00$12,845$1,120.24
55Maintaining traffic (614E11000)LS1$40,000$9,622.39$12,000$20,300$97,612
56Construction layout stakes and surveying (623E10000)LS1$6,000.00$6,000.00$12,000$8,000.00$11,027
57Mobilization (624E10000)LS1$20,000$37,069$25,000$37,780$72,500
100Removal of existing coatings from concrete surfaces (512E74000)SY8$245.00$290.02$45.00$45.00$40.00
ODOT contract 260144: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of March 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy