ODOT contract 260159 bid tabulation

CUY-SIGN FY2026 (SIGNING). Let by Ohio DOT on March 26, 2026, CUY. 1 bid received; low bid $477,480 by Lake Erie Construction Company, +17% against the engineer's estimate of $409,000.

Owner
Ohio DOT
Letting
26 MAR 2026
Pay items
23
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Lake Erie Construction Company$477,480Low+17%
ODOT contract 260159: bids by rank

Engineer's estimate: $409,000.

Bid tabulation

LinePay itemUnitQuantity1. Lake Erie Construction Company
1Ground mounted structural beam support, S4X7.7 (630E06400)FT76$40.00
2Ground mounted structural beam support, W10X12 (630E07600)FT62$52.00
3Breakaway structural beam connection (630E09000)EACH10$645.00
4Overhead sign support, type TC-12.31, design 6 (630E72320)EACH1$32,550
5Overhead sign support, type TC-12.31, design 10 (630E72330)EACH2$44,825
6Overhead sign support, type TC-15.116, design 1 (630E72410)EACH1$66,500
7Combination overhead sign support, type TC-9.11, design 2 (630E73110)EACH1$16,750
8Sign attachment assembly (630E75000)EACH23$1,150.00
9Sign support assembly, bridge mounted, type 1 (630E79600)EACH5$2,275.00
10Sign, flat sheet (630E80100)SF569$19.00
11Sign, overhead extrusheet (630E80224)SF1,055$26.00
12Sign backing assembly (630E82000)EACH77$375.00
13Ground mounted structural beam support foundation (630E84500)EACH10$980.00
14Rigid overhead sign support foundation (630E84510)EACH6$11,450
15Removal of structure mounted sign and disposal (630E86310)EACH43$325.00
16Removal of structure mounted sign and reerection (630E86320)EACH1$550.00
17Removal of overhead sign support and disposal, as per plan (630E89703)EACH2$1,850.00
18Signing, misc.: removal of sign support foundation (630E97700)EACH6$925.00
19Law enforcement officer with patrol car for assistance (614E11110)HR80$80.00
20Signing, misc.: additional signs, ground mounted, (630E97800)SF100$10.00
21Premium for contract performance bond and for payment bond (103E05000)LS1$2,550.00
22Maintaining traffic (614E11000)LS1$22,750
23Mobilization (624E10000)LS1$19,400
ODOT contract 260159: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of March 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy