ODOT contract 260157 bid tabulation
STA-SR 241-14.58 (SRTS) (SIDEWALK). Let by Ohio DOT on March 26, 2026, STA. 5 bids received; low bid $394,878 by Ruhlin Company, -15% against the engineer's estimate of $465,000.
- Owner
- Ohio DOT
- Letting
- 26 MAR 2026
- Pay items
- 62
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ruhlin Company | $394,878 | Low | -15% |
| 2 | Bog Construction Inc | $450,761 | +14% | -3.0% |
| 3 | Shelly Company | $479,729 | +21% | +3.0% |
| 4 | Rietschlin Construction Inc | $500,111 | +27% | +8.0% |
| 5 | Stanley Miller Construction Company | $555,436 | +41% | +19% |
Engineer's estimate: $465,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ruhlin Company | 2. Bog Construction Inc | 3. Shelly Company | 4. Rietschlin Construction Inc | 5. Stanley Miller Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $4,303.00 | $3,500.00 | $12,000 | $7,700.00 | $6,000.00 |
| 2 | Walk removed (202E30000) | SF | 280 | $2.60 | $10.00 | $3.00 | $7.00 | $2.00 |
| 3 | Curb removed (202E32000) | FT | 341 | $6.00 | $16.00 | $17.00 | $8.50 | $10.00 |
| 4 | Guardrail removed (202E38000) | FT | 166 | $2.00 | $4.00 | $2.50 | $10.00 | $10.00 |
| 5 | Excavation (203E10000) | CY | 322 | $14.00 | $40.00 | $80.00 | $56.00 | $80.00 |
| 6 | Embankment (203E20000) | CY | 70 | $52.00 | $50.00 | $100.00 | $46.00 | $80.00 |
| 7 | Subgrade compaction (204E10000) | SY | 1,459 | $1.50 | $5.00 | $3.50 | $6.00 | $1.50 |
| 8 | Guardrail, type MGS (606E15050) | FT | 75 | $35.00 | $49.00 | $44.80 | $38.00 | $60.00 |
| 9 | Anchor assembly, MGS type E (606E26150) | EACH | 2 | $3,150.00 | $3,100.00 | $2,820.00 | $3,402.00 | $3,500.00 |
| 10 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 2 | $2,850.00 | $3,100.00 | $2,940.00 | $3,078.00 | $3,500.00 |
| 11 | 4" concrete walk (608E10000) | SF | 10,182 | $11.00 | $8.50 | $8.50 | $8.00 | $9.50 |
| 12 | Curb ramp, as per plan (608E52001) | SF | 1,320 | $16.50 | $23.00 | $18.00 | $16.00 | $27.50 |
| 13 | Special - as-built construction plans (690E91000) | LS | 1 | $1,000.00 | $6,000.00 | $2,000.00 | $825.00 | $5,000.00 |
| 14 | Special - survey control verification (690E98400) | LS | 1 | $1,000.00 | $5,000.00 | $1,000.00 | $2,100.00 | $2,500.00 |
| 15 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $50.00 | $300.00 | $162.00 | $150.00 |
| 16 | Topsoil (659E00300) | CY | 116 | $50.00 | $45.00 | $120.00 | $62.00 | $50.00 |
| 17 | Seeding and mulching (659E10000) | SY | 1,040 | $4.00 | $6.50 | $1.30 | $6.00 | $6.00 |
| 18 | Commercial fertilizer (659E20000) | TON | 0.14 | $1,250.00 | $1,000.00 | $1,500.00 | $1,200.00 | $800.00 |
| 19 | Lime (659E31000) | ACRE | 0.03 | $150.00 | $100.00 | $10.00 | $200.00 | $150.00 |
| 20 | Water (659E35000) | MGAL | 6 | $1.00 | $1.00 | $40.00 | $11.00 | $1.00 |
| 21 | Erosion control (832E30000) | EACH | 8,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | Manhole reconstructed to grade (611E99660) | EACH | 1 | $1,500.00 | $1,500.00 | $1,300.00 | $1,600.00 | $1,200.00 |
| 23 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 33 | $500.00 | $790.00 | $590.00 | $540.00 | $625.00 |
| 24 | Aggregate base (304E20000) | CY | 181 | $165.00 | $180.00 | $35.00 | $125.00 | $150.00 |
| 25 | Non-tracking tack coat (407E20000) | GAL | 44 | $3.00 | $10.00 | $3.00 | $4.00 | $10.00 |
| 26 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 6 | $720.00 | $1,500.00 | $1,100.00 | $780.00 | $900.00 |
| 27 | Asphalt concrete intermediate course, type 1, (449) (441E70200) | CY | 6 | $720.00 | $1,500.00 | $1,100.00 | $780.00 | $900.00 |
| 28 | 8" non-reinforced concrete pavement, class QC MS (452E12050) | SY | 109 | $120.00 | $125.00 | $130.00 | $135.00 | $150.00 |
| 29 | Curb, type 6 (609E26000) | FT | 711 | $27.00 | $40.00 | $45.00 | $45.00 | $42.00 |
| 30 | Curb, type 7 (609E28000) | FT | 35 | $55.00 | $45.00 | $50.00 | $88.00 | $75.00 |
| 31 | Manhole reconstructed to grade (611E99660) | EACH | 2 | $1,200.00 | $1,500.00 | $1,700.00 | $1,600.00 | $1,500.00 |
| 32 | Barrier reflector, type 3 bidirection (614E13314) | EACH | 4 | $35.00 | $50.00 | $12.50 | $13.00 | $50.00 |
| 33 | Ground mounted support, no. 2 post (630E02100) | FT | 56 | $25.00 | $30.00 | $25.00 | $28.00 | $50.00 |
| 34 | Sign post reflector (630E08600) | EACH | 4 | $35.00 | $50.00 | $35.00 | $88.00 | $50.00 |
| 35 | Sign, flat sheet (630E80100) | SF | 33 | $20.00 | $30.00 | $20.00 | $32.00 | $40.00 |
| 36 | Edge line, 6" (646E10010) | MI | 0.10 | $15,000 | $30,000 | $15,000 | $407,000 | $30,000 |
| 37 | Crosswalk line, 24" (646E10520) | FT | 390 | $6.50 | $10.00 | $6.50 | $9.00 | $10.00 |
| 38 | Removal of pavement marking (646E50100) | FT | 244 | $15.00 | $20.00 | $15.00 | $3.00 | $30.00 |
| 39 | Pull box removed and replaced, as per plan (625E31507) | EACH | 1 | $993.70 | $4,000.00 | $800.00 | $800.00 | $5,000.00 |
| 40 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $80.00 | $50.00 | $100.00 | $87.00 | $200.00 |
| 41 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $2,800.00 | $2,700.00 | $3,500.00 | $2,600.00 | $4,000.00 |
| 42 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $500.00 | $150.00 | $100.00 | $500.00 | $150.00 |
| 43 | Barrier reflector, type 1, one way (614E13310) | EACH | 4 | $40.00 | $40.00 | $10.00 | $10.00 | $80.00 |
| 44 | Object marker, one way (614E13350) | EACH | 4 | $40.00 | $40.00 | $10.00 | $24.00 | $80.00 |
| 45 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.05 | $17,500 | $20,000 | $17,500 | $16,200 | $30,000 |
| 46 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 0.05 | $17,500 | $20,000 | $17,500 | $1,620.00 | $30,000 |
| 47 | Water (616E10000) | MGAL | 2 | $31.00 | $1.00 | $50.00 | $10.00 | $1.00 |
| 48 | Portable barrier, unanchored (622E41100) | FT | 150 | $30.00 | $50.00 | $40.00 | $61.00 | $55.00 |
| 49 | Wearing course removed (202E23500) | SY | 14 | $10.00 | $50.00 | $100.00 | $60.00 | $100.00 |
| 50 | Bridge railing removed (202E38500) | FT | 18 | $80.00 | $40.00 | $50.00 | $90.00 | $50.00 |
| 51 | Epoxy coated steel reinforcement (509E10000) | LB | 1,269 | $2.22 | $2.50 | $6.00 | $4.00 | $3.50 |
| 52 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 80 | $38.00 | $15.00 | $23.00 | $22.00 | $22.00 |
| 53 | Class QC2 concrete, superstructure (511E31610) | CY | 6 | $1,100.00 | $1,000.00 | $700.00 | $1,150.00 | $1,900.00 |
| 54 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 13 | $12.00 | $40.00 | $75.00 | $49.00 | $80.00 |
| 55 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 18 | $23.00 | $60.00 | $100.00 | $135.00 | $80.00 |
| 56 | 1" preformed expansion joint filler (516E13600) | SF | 9 | $6.26 | $40.00 | $5.00 | $22.00 | $100.00 |
| 57 | Railing, concrete (517E74500) | FT | 18 | $265.00 | $300.00 | $1,200.00 | $440.00 | $1,600.00 |
| 58 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $13,992 | $10,000 | $1,500.00 | $7,000.00 | $12,000 |
| 59 | Maintaining traffic (614E11000) | LS | 1 | $17,800 | $18,000 | $50,500 | $35,000 | $42,000 |
| 60 | Field office, type B (619E16010) | MNTH | 6 | $1,530.00 | $1,000.00 | $3,500.00 | $1,500.00 | $1,500.00 |
| 61 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,225.00 | $12,000 | $5,000.00 | $8,000.00 | $10,000 |
| 62 | Mobilization (624E10000) | LS | 1 | $17,250 | $20,000 | $25,000 | $45,000 | $32,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 26, 2026. Compiled by Mirage Metrics.