ODOT contract 260166 bid tabulation
ALL-Lafayette Improvements (TWO LANE RESURFACING). Let by Ohio DOT on March 26, 2026, ALL. 2 bids received; low bid $1,185,353 by R D Jones Excavating Inc, -18% against the engineer's estimate of $1,454,000.
- Owner
- Ohio DOT
- Letting
- 26 MAR 2026
- Pay items
- 71
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | R D Jones Excavating Inc | $1,185,353 | Low | -18% |
| 2 | Fenson Contracting LLC | $1,581,469 | +33% | +9.0% |
Engineer's estimate: $1,454,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R D Jones Excavating Inc | 2. Fenson Contracting LLC |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $17,550 | $30,000 |
| 2 | Pavement removed (202E23000) | SY | 3,857 | $6.45 | $10.00 |
| 3 | Walk removed (202E30000) | SF | 15,018 | $1.55 | $2.50 |
| 4 | Curb removed (202E32000) | FT | 380 | $3.50 | $20.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 668 | $15.00 | $50.00 |
| 6 | Pipe removed, over 24" diameter (202E35200) | FT | 80 | $15.00 | $85.00 |
| 7 | Manhole removed (202E58000) | EACH | 1 | $250.00 | $750.00 |
| 8 | Catch basin removed (202E58100) | EACH | 9 | $250.00 | $750.00 |
| 9 | Excavation (203E10000) | CY | 305.50 | $18.50 | $40.00 |
| 10 | Embankment (203E20000) | CY | 23.90 | $35.00 | $200.00 |
| 11 | Subgrade compaction (204E10000) | SY | 4,261 | $3.55 | $2.50 |
| 12 | Excavation of subgrade (204E13000) | CY | 1,230 | $18.00 | $18.00 |
| 13 | Granular material, type B (204E30010) | CY | 1,230 | $45.00 | $55.00 |
| 14 | Proof rolling (204E45000) | HR | 2 | $185.00 | $150.00 |
| 15 | Geotextile fabric (204E50000) | SY | 3,691 | $2.45 | $2.00 |
| 16 | 4" concrete walk (608E10000) | SF | 16,694 | $7.75 | $10.00 |
| 17 | Curb ramp, as per plan (608E52001) | SF | 1,741 | $19.50 | $28.00 |
| 18 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 3 | $2,000.00 | $1,500.00 |
| 19 | Monument assembly removed and reset (623E40000) | EACH | 20 | $950.00 | $2,500.00 |
| 20 | Topsoil (659E00300) | CY | 193 | $45.00 | $90.00 |
| 21 | Seeding and mulching (659E10000) | SY | 1,736 | $3.50 | $9.00 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.24 | $850.00 | $950.00 |
| 23 | Water (659E35000) | MGAL | 9.50 | $10.00 | $1.00 |
| 24 | Erosion control (832E30000) | EACH | 15,000 | $1.00 | $1.00 |
| 25 | 4" unclassified pipe underdrains (605E05200) | FT | 395 | $25.00 | $22.00 |
| 26 | 4" conduit, type F (611E00406) | FT | 30 | $45.00 | $22.00 |
| 27 | 8" conduit, type B (611E01800) | FT | 11 | $85.00 | $105.00 |
| 28 | 12" conduit, type B (611E04400) | FT | 492 | $42.00 | $110.00 |
| 29 | 18" conduit, type B (611E07400) | FT | 232 | $48.00 | $145.00 |
| 30 | 36" conduit, type B (611E16400) | FT | 80 | $120.00 | $205.00 |
| 31 | Catch basin, no. 3A, as per plan (611E98181) | EACH | 9 | $2,950.00 | $4,400.00 |
| 32 | Catch basin, no. 3A, as per plan (611E98181) | EACH | 1 | $2,950.00 | $4,100.00 |
| 33 | Manhole, no. 3 (611E99574) | EACH | 1 | $4,650.00 | $9,000.00 |
| 34 | Pavement planing, asphalt concrete 1 1/2" (254E01000) | SY | 9,303 | $2.40 | $2.50 |
| 35 | Patching planed surface (254E01600) | SY | 182 | $10.00 | $13.50 |
| 36 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 275 | $222.00 | $220.00 |
| 37 | Aggregate base (304E20000) | CY | 883 | $45.00 | $57.00 |
| 38 | Non-tracking tack coat (407E20000) | GAL | 875 | $3.00 | $3.00 |
| 39 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 525 | $236.00 | $280.00 |
| 40 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 160 | $209.00 | $250.00 |
| 41 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 277 | $82.75 | $100.00 |
| 42 | 9" non-reinforced concrete pavement, class QC 1P (452E13010) | SY | 285 | $104.50 | $122.00 |
| 43 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 1,189 | $34.00 | $33.00 |
| 44 | Curb, type 6 (609E26000) | FT | 71 | $39.00 | $50.00 |
| 45 | 8" water main polyvinyl chloride pipe and fittings, AWWA C900, DR14 (638E01710) | FT | 200 | $125.00 | $230.00 |
| 46 | 1" copper service branch (638E04900) | FT | 400 | $50.00 | $75.00 |
| 47 | Fire hydrant and gate valve removed and reset (638E10600) | EACH | 3 | $2,650.00 | $3,000.00 |
| 48 | Valve box adjusted to grade (638E10800) | EACH | 2 | $500.00 | $950.00 |
| 49 | Service box adjusted to grade (638E10900) | EACH | 7 | $500.00 | $300.00 |
| 50 | Meter and chamber removed and reset (638E11100) | EACH | 6 | $1,175.00 | $2,050.00 |
| 51 | Ground mounted support, no. 3 post (630E03100) | FT | 377 | $21.52 | $14.00 |
| 52 | Street name sign support, no. 3 post (630E08520) | FT | 80.50 | $21.52 | $16.00 |
| 53 | Sign post reflector (630E08600) | EACH | 21 | $76.60 | $50.00 |
| 54 | Sign, flat sheet (630E80100) | SF | 206.25 | $25.11 | $30.00 |
| 55 | Removal of ground mounted sign and disposal (630E84900) | EACH | 55 | $26.41 | $30.00 |
| 56 | Removal of ground mounted post support and disposal (630E86002) | EACH | 35 | $35.21 | $30.00 |
| 57 | Center line, type 1 (642E00300) | MI | 0.58 | $2,500.00 | $2,800.00 |
| 58 | Stop line (643E00500) | FT | 27 | $18.00 | $20.00 |
| 59 | Crosswalk line, 12" (643E00620) | FT | 1,213 | $7.00 | $8.00 |
| 60 | Traffic compacted surface, type A or B (410E12000) | CY | 93 | $60.00 | $72.00 |
| 61 | Stabilized crushed aggregate (411E10000) | CY | 100 | $60.00 | $82.00 |
| 62 | Detour signing (614E12420) | LS | 1 | $9,950.00 | $9,000.00 |
| 63 | Asphalt concrete for maintaining traffic (614E13000) | CY | 250 | $207.00 | $290.00 |
| 64 | Water (616E10000) | MGAL | 10 | $10.00 | $40.00 |
| 65 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $1,500.00 | $6,250.00 |
| 66 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,000.00 | $20,000 |
| 67 | Maintaining traffic (614E11000) | LS | 1 | $8,500.00 | $50,000 |
| 68 | Construction layout stakes and surveying (623E10000) | LS | 1 | $22,700 | $25,000 |
| 69 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $6,300.00 | $5,000.00 |
| 70 | Post construction survey monument verification and report (623E51000) | LS | 1 | $6,300.00 | $5,000.00 |
| 71 | Mobilization (624E10000) | LS | 1 | $89,260 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 26, 2026. Compiled by Mirage Metrics.