ODOT contract 260165 bid tabulation

MOT-SR 725/Jamaica TSG (SIGNALIZATION). Let by Ohio DOT on March 26, 2026, MOT. 6 bids received; low bid $199,365 by Bansal Construction Inc, -1.8% against the engineer's estimate of $203,000.

Owner
Ohio DOT
Letting
26 MAR 2026
Pay items
42
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Bansal Construction Inc$199,365Low-2.0%
2Complete General Construction Company$200,490+1.0%-1.0%
3Perram Electric Inc$203,633+2.0%0.0%
4Security Fence Group Inc$207,508+4.0%+2.0%
5Capital Electric Line Builders Inc$253,314+27%+25%
6Miller Cable Company$399,023+100%+97%
ODOT contract 260165: bids by rank

Engineer's estimate: $203,000.

Bid tabulation

LinePay itemUnitQuantity1. Bansal Construction Inc2. Complete General Construction Company3. Perram Electric Inc4. Security Fence Group Inc5. Capital Electric Line Builders Inc6. Miller Cable Company
1Seeding and mulching (659E10000)SY50$5.00$51.00$15.00$25.00$44.90$48.00
2Erosion control (832E30000)EACH500$1.00$1.00$1.00$1.00$1.00$1.00
3Ground mounted support, no. 3 post (630E03100)FT54$25.33$25.33$22.90$17.05$29.90$37.00
4Sign support assembly, pole mounted (630E79500)EACH2$152.82$152.82$157.50$60.50$175.95$400.00
5Sign, flat sheet (630E80100)SF36$27.21$27.21$32.00$17.60$32.20$40.00
6Removal of ground mounted sign and disposal (630E84900)EACH20$17.02$17.02$107.50$16.50$19.55$18.00
7Removal of ground mounted post support and disposal (630E86002)EACH20$22.70$22.70$107.50$22.00$26.45$25.00
8Removal of pole mounted sign and reerection (630E87520)EACH2$166.61$166.61$215.00$49.50$192.05$300.00
9Stop line (644E00500)FT42$29.95$57.54$30.00$32.95$66.70$42.00
10Removal of pavement marking (644E30000)FT218$12.00$15.90$12.00$13.20$18.40$16.00
11Bracket arm, 15' (625E18200)EACH1$1,530.00$1,100.00$895.00$999.00$1,151.73$1,800.00
12Conduit, 2", 725.04 (625E25400)FT11$19.40$30.00$34.35$42.25$43.82$45.00
13Conduit, 4", 725.04 (625E25600)FT14$47.30$62.00$93.75$94.85$73.06$65.00
14Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH1$515.00$550.00$545.00$489.00$447.93$850.00
15Trench (625E29000)FT25$16.10$10.00$17.20$13.65$47.24$32.00
16Pull box, 725.08, 24" (625E30706)EACH1$1,290.00$1,700.00$2,825.00$1,428.00$1,784.80$2,400.00
17Ground rod (625E32000)EACH3$490.00$325.00$340.00$270.00$338.10$350.00
18Underground warning marking tape (625E36010)FT25$1.65$1.00$1.30$1.90$1.94$5.00
19Arc flash calculations and label (SR-725/jamaica R (625E76000)EACH1$500.00$3,600.00$2,000.00$2,320.00$4,917.40$6,500.00
20Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH8$1,400.00$1,100.00$1,100.00$1,365.00$1,261.55$1,950.00
21Covering of vehicular signal head (632E25000)EACH8$80.50$40.00$20.00$41.00$19.44$150.00
22Signal cable, 4 conductor, no. 14 AWG (632E40400)FT78$2.40$2.50$2.95$2.80$6.08$5.50
23Signal cable, 7 conductor, no. 14 AWG (632E40700)FT506$2.60$3.50$4.10$4.00$6.42$7.50
24Signal support foundation, as per plan (632E64011)EACH1$9,850.00$12,750$13,385$9,600.00$12,084$19,000
25Power cable, 2 conductor, no. 6 AWG (632E68200)FT55$4.75$5.50$4.75$5.20$7.46$8.00
26Service cable, 3 conductor, no. 6 AWG (632E69800)FT26$7.15$7.00$8.35$6.60$8.72$12.00
27Power service (632E70000)EACH1$6,625.00$3,450.00$3,175.00$4,670.00$3,569.60$8,500.00
28Combination signal support, misc.: type TC-81.22, (632E81700)EACH1$27,570$27,100$24,350$28,425$30,139$36,000
29Cabinet, type TS-2, as per plan (633E65511)EACH1$21,850$20,300$20,508$21,880$22,540$30,000
30Cabinet foundation, as per plan (633E67101)EACH1$1,850.00$4,000.00$3,750.00$1,990.00$3,974.40$4,500.00
31Controller work pad, as per plan (633E67201)EACH1$1,350.00$1,600.00$945.00$1,290.00$3,859.40$2,000.00
32Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001)EACH1$8,700.00$7,500.00$7,950.00$8,440.00$8,252.40$10,500
33CCTV IP-camera system, dome-type (809E60000)EACH1$7,500.00$7,700.00$6,065.00$7,970.00$6,872.40$10,000
34Ethernet cable, outdoor-rated (809E64550)FT63$3.20$2.50$3.05$4.00$5.89$9.00
35Advance radar detection, as per plan (809E69001)EACH4$10,860$9,550.00$10,385$10,420$10,780$18,000
36Stop line radar detection, as per plan (809E69101)EACH2$10,750$9,300.00$10,055$10,090$10,435$19,000
37Atc controller, as per plan (809E69123)EACH1$700.00$850.00$565.00$2,470.00$949.90$2,500.00
38Law enforcement officer with patrol car for assistance (614E11110)HR40$75.00$110.00$80.00$135.00$143.75$250.00
39Premium for contract performance bond and for payment bond (103E05000)LS1$1,405.45$1,000.00$4,017.35$2,850.00$1,735.35$900.00
40Maintaining traffic (614E11000)LS1$6,000.00$3,200.00$8,140.00$9,800.00$41,099$45,000
41Construction layout stakes and surveying (623E10000)LS1$5,000.00$1,000.00$2,000.00$2,200.00$3,105.00$32,000
42Mobilization (624E10000)LS1$4,000.00$15,000$10,000$7,680.00$4,379.20$27,000
ODOT contract 260165: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of March 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy