ODOT contract 250324 bid tabulation
PUT-Ottawa Ped. Improvements (SPOT SAFETY). Let by Ohio DOT on June 26, 2025, PUT. 4 bids received; low bid $185,523 by Ward Construction Co, -35% against the engineer's estimate of $287,000.
- Owner
- Ohio DOT
- Letting
- 26 JUN 2025
- Pay items
- 41
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ward Construction Co | $185,523 | Low | -35% |
| 2 | Fenson Contracting LLC | $281,751 | +52% | -2.0% |
| 3 | D L Smith Concrete LLC | $298,808 | +61% | +4.0% |
| 4 | Madex Construction Co | $366,897 | +98% | +28% |
Engineer's estimate: $287,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ward Construction Co | 2. Fenson Contracting LLC | 3. D L Smith Concrete LLC | 4. Madex Construction Co |
|---|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 181 | $23.00 | $90.00 | $24.00 | $56.50 |
| 2 | Walk removed (202E30000) | SF | 1,594 | $2.50 | $8.00 | $15.00 | $5.47 |
| 3 | Curb and gutter removed (202E32500) | FT | 220 | $8.50 | $25.00 | $11.50 | $49.55 |
| 4 | Excavation (203E10000) | CY | 55 | $45.00 | $90.00 | $70.00 | $157.14 |
| 5 | Subgrade compaction (204E10000) | SY | 181 | $1.10 | $15.00 | $2.50 | $11.58 |
| 6 | 4" concrete walk (608E10000) | SF | 1,552 | $14.50 | $16.50 | $25.00 | $22.55 |
| 7 | Curb ramp (608E52000) | SF | 340 | $22.50 | $30.00 | $35.00 | $65.71 |
| 8 | Topsoil furnished and placed (653E10000) | CY | 29 | $150.00 | $250.00 | $45.00 | $196.32 |
| 9 | Seeding and mulching, class 1, as per plan (659E00501) | SY | 243 | $13.50 | $10.00 | $12.00 | $26.63 |
| 10 | 4" conduit, type B, as per plan (611E00101) | FT | 25 | $10.00 | $25.00 | $35.00 | $25.26 |
| 11 | 6" conduit, type B, as per plan (611E00901) | FT | 25 | $15.00 | $30.00 | $40.00 | $36.84 |
| 12 | 8" conduit, type B, as per plan (611E01801) | FT | 25 | $20.00 | $35.00 | $48.00 | $48.42 |
| 13 | Manhole adjusted to grade (611E99654) | EACH | 1 | $1,400.00 | $2,500.00 | $2,350.00 | $1,902.32 |
| 14 | Pavement planing, asphalt concrete, 1-1/2" (254E01000) | SY | 264 | $10.00 | $10.00 | $42.00 | $11.58 |
| 15 | Aggregate base (304E20000) | CY | 39 | $145.00 | $180.00 | $80.00 | $235.48 |
| 16 | Non-tracking tack coat (407E20000) | GAL | 8 | $8.00 | $1.00 | $7.00 | $9.26 |
| 17 | Non-tracking tack coat (407E20000) | GAL | 24 | $8.00 | $1.00 | $7.00 | $5.79 |
| 18 | Stabilized crushed aggregate (411E10000) | CY | 21 | $140.00 | $180.00 | $86.00 | $273.87 |
| 19 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 18 | $500.00 | $750.00 | $800.00 | $578.95 |
| 20 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 9 | $500.00 | $875.00 | $800.00 | $578.95 |
| 21 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 225 | $60.00 | $85.00 | $65.00 | $149.28 |
| 22 | Light pole foundation, 24" X 6' deep (625E14000) | EACH | 6 | $1,000.00 | $1,750.00 | $2,500.00 | $1,736.84 |
| 23 | Ground rod (625E32000) | EACH | 6 | $250.00 | $315.00 | $315.00 | $577.59 |
| 24 | Ground mounted support, no. 3 post (630E03100) | FT | 161 | $12.00 | $16.00 | $15.25 | $28.95 |
| 25 | Sign, flat sheet (630E80100) | SF | 58.50 | $20.00 | $30.00 | $25.25 | $31.26 |
| 26 | Removal of ground mounted sign and reerection (630E85100) | EACH | 11 | $30.00 | $68.00 | $38.00 | $68.42 |
| 27 | Removal of ground mounted post support and disposal (630E86002) | EACH | 5 | $20.00 | $95.00 | $25.25 | $60.21 |
| 28 | Signing, misc.: rectangular rapid flashing beacon (630E97700) | EACH | 6 | $7,250.00 | $10,500 | $9,135.00 | $11,579 |
| 29 | Signing, misc.: rectangular rapid flashing beacon (630E97700) | EACH | 2 | $200.00 | $2,000.00 | $25.25 | $2,371.58 |
| 30 | Center line (644E00300) | MI | 0.03 | $15,000 | $19,500 | $19,000 | $26,632 |
| 31 | Crosswalk line, 12" (644E00620) | FT | 167 | $4.00 | $5.00 | $5.05 | $12.74 |
| 32 | Crosswalk line, 24" (644E00630) | FT | 110 | $8.00 | $10.00 | $10.15 | $12.74 |
| 33 | Parking lot stall marking (644E01200) | FT | 4 | $25.00 | $30.00 | $1.50 | $11.58 |
| 34 | Removal of pavement marking (644E30000) | FT | 10 | $150.00 | $175.00 | $190.00 | $318.42 |
| 35 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,000.00 | $4,500.00 | $7,500.00 | $18,784 |
| 36 | Maintaining traffic (614E11000) | LS | 1 | $13,500 | $25,000 | $20,000 | $14,088 |
| 37 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $2,500.00 | $2,500.00 | $10,000 | $10,421 |
| 38 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $4,000.00 | $1,000.00 | $2,500.00 | $2,894.74 |
| 39 | Post construction survey monument verification and report (623E51000) | LS | 1 | $4,000.00 | $1,000.00 | $2,500.00 | $2,894.74 |
| 40 | Mobilization (624E10000) | LS | 1 | $6,500.00 | $10,000 | $25,750 | $30,431 |
| 100 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 26, 2025. Compiled by Mirage Metrics.