ODOT contract 260285 bid tabulation
CUY-SR 237-06.35 (FOUR LANE RESURFACING). Let by Ohio DOT on June 11, 2026, CUY. 3 bids received; low bid $3,245,457 by Karvo Companies Inc, +15% against the engineer's estimate of $2,828,000.
- Owner
- Ohio DOT
- Letting
- 11 JUN 2026
- Pay items
- 67
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Karvo Companies Inc | $3,245,457 | Low | +15% |
| 2 | Kokosing Construction Company Inc | $4,061,100 | +25% | +44% |
| 3 | Shelly Company | $4,070,320 | +25% | +44% |
Engineer's estimate: $2,828,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Karvo Companies Inc | 2. Kokosing Construction Company Inc | 3. Shelly Company |
|---|---|---|---|---|---|---|
| 1 | Excavation (203E10000) | CY | 20 | $10.00 | $60.00 | $50.00 |
| 2 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 20 | $1,100.00 | $1,000.00 | $1,100.00 |
| 3 | Monument assembly reconstructed to grade, as per plan (623E39601) | EACH | 6 | $1,200.00 | $1,500.00 | $1,200.00 |
| 4 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 |
| 5 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 25 | $1,600.00 | $1,750.00 | $1,600.00 |
| 6 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 5 | $1,700.00 | $2,500.00 | $1,700.00 |
| 7 | Inlet adjusted to grade, as per plan (611E99151) | EACH | 36 | $1,800.00 | $1,750.00 | $1,800.00 |
| 8 | Inlet reconstructed to grade, as per plan (611E99155) | EACH | 10 | $2,200.00 | $2,500.00 | $2,200.00 |
| 9 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 25 | $1,400.00 | $1,750.00 | $1,400.00 |
| 10 | Special - miscellaneous metal (611E99820) | LB | 10,000 | $2.00 | $3.50 | $2.00 |
| 11 | Partial depth pavement repair (442), as per plan (251E01021) | SY | 400 | $100.00 | $150.00 | $125.00 |
| 12 | Partial depth pavement repair (442), as per plan (251E01021) | SY | 600 | $125.00 | $170.00 | $160.00 |
| 13 | Pavement repair (253E02000) | CY | 35 | $500.00 | $1,600.00 | $1,000.00 |
| 14 | Pavement planing, asphalt concrete, as per plan, 1 (254E01001) | SY | 108,256 | $3.15 | $2.65 | $2.25 |
| 15 | Full depth pavement removal and rigid replacement, type 1, class QC RS, as per plan (255E19001) | SY | 1,000 | $240.00 | $589.00 | $500.00 |
| 16 | Full depth pavement removal and rigid replacement, type 1, class QC RS, as per plan (255E19001) | SY | 215 | $240.00 | $460.00 | $450.00 |
| 17 | Full depth pavement sawing (255E20000) | FT | 5,800 | $5.75 | $5.00 | $4.25 |
| 18 | Aggregate base (304E20000) | CY | 20 | $25.00 | $95.00 | $40.00 |
| 19 | Non-tracking tack coat (407E20000) | GAL | 9,744 | $3.00 | $2.75 | $3.15 |
| 20 | Anti-segregation equipment (442E00100) | CY | 4,511 | $8.00 | $1.00 | $9.00 |
| 21 | Asphalt concrete surface course, 12.5 MM, type A (446), as per plan (442E10001) | CY | 1,178 | $300.00 | $410.00 | $300.00 |
| 22 | Asphalt concrete surface course, 12.5 MM, type A (447), as per plan (442E10301) | CY | 3,333 | $235.00 | $325.00 | $275.00 |
| 23 | Rumble strips, shoulder (asphalt concrete), as per plan (618E40601) | MI | 3.93 | $1,750.00 | $1,750.00 | $3,325.00 |
| 24 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 11.42 | $1,460.00 | $1,450.00 | $1,460.00 |
| 25 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 600 | $0.80 | $1.25 | $0.80 |
| 26 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 10,963 | $1.00 | $1.75 | $1.00 |
| 27 | Void reducing asphalt membrane (vram) (872E10000) | FT | 8,031 | $1.00 | $4.50 | $4.25 |
| 28 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 15 | $1,100.00 | $1,000.00 | $1,100.00 |
| 29 | Service box adjusted to grade, as per plan (638E10901) | EACH | 2 | $600.00 | $1,000.00 | $600.00 |
| 30 | RPM (621E00100) | EACH | 521 | $39.00 | $49.00 | $39.00 |
| 31 | Raised pavement marker removed (621E54000) | EACH | 391 | $1.00 | $4.00 | $4.50 |
| 32 | Detector loop, as per plan (632E26501) | EACH | 13 | $1,500.00 | $1,650.00 | $1,750.00 |
| 33 | Center line (646E10200) | MI | 0.01 | $4,500.00 | $50,000 | $4,500.00 |
| 34 | Stop line (646E10400) | FT | 250 | $12.00 | $13.50 | $12.00 |
| 35 | Chevron marking (646E10620) | FT | 471 | $7.00 | $12.50 | $7.00 |
| 36 | Lane arrow (646E20300) | EACH | 25 | $160.00 | $170.00 | $160.00 |
| 37 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 7.68 | $3,950.00 | $5,000.00 | $3,950.00 |
| 38 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 3.74 | $2,100.00 | $1,800.00 | $2,100.00 |
| 39 | Wet reflective epoxy pavement marking, channelizing line, 12" (807E12310) | FT | 7,472 | $2.25 | $2.25 | $2.25 |
| 40 | Wet reflective epoxy pavement marking, dotted line, 6" (807E12410) | FT | 600 | $0.80 | $1.25 | $0.80 |
| 41 | Wet reflective epoxy pavement marking, dotted line, 12" (807E12430) | FT | 3,491 | $1.60 | $2.25 | $1.60 |
| 42 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 1,000 | $75.00 | $120.00 | $100.00 |
| 43 | Work zone increased penalties sign (614E12484) | EACH | 4 | $250.00 | $175.00 | $255.00 |
| 44 | Asphalt concrete for maintaining traffic, as per plan (614E13001) | CY | 200 | $200.00 | $150.00 | $140.00 |
| 45 | Portable changeable message sign, as per plan (614E18601) | SNMT | 24 | $1,025.00 | $700.00 | $1,025.00 |
| 46 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 3.74 | $650.00 | $750.00 | $650.00 |
| 47 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 3.74 | $650.00 | $650.00 | $650.00 |
| 48 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.01 | $1,200.00 | $5,000.00 | $1,200.00 |
| 49 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.01 | $1,200.00 | $4,750.00 | $1,200.00 |
| 50 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 7.68 | $875.00 | $900.00 | $875.00 |
| 51 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 7.68 | $875.00 | $750.00 | $875.00 |
| 52 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 7,472 | $1.00 | $0.80 | $1.00 |
| 53 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 7,472 | $1.00 | $0.80 | $1.00 |
| 54 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 600 | $0.60 | $0.65 | $0.60 |
| 55 | Work zone dotted line, class I, 12", 642 paint (614E24208) | FT | 3,491 | $0.65 | $1.00 | $0.65 |
| 56 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 600 | $0.60 | $0.70 | $0.60 |
| 57 | Work zone dotted line, class III, 12", 642 paint (614E24618) | FT | 3,491 | $0.65 | $0.75 | $0.65 |
| 58 | Work zone stop line, class I, 642 paint (614E26200) | FT | 250 | $3.75 | $3.25 | $3.75 |
| 59 | Work zone stop line, class III, 642 paint (614E26610) | FT | 250 | $3.75 | $3.00 | $3.75 |
| 60 | Work zone arrow, class I, 642 paint (614E30200) | EACH | 25 | $50.00 | $50.00 | $50.00 |
| 61 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 25 | $25.00 | $45.00 | $50.00 |
| 62 | Signing, misc.: additional signs, ground mounted, (630E97800) | SF | 300 | $24.00 | $7.50 | $25.00 |
| 63 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $49,800 | $16,250 | $57,500 |
| 64 | Maintaining traffic (614E11000) | LS | 1 | $272,637 | $271,027 | $785,000 |
| 65 | Field office, type C, as per plan (619E16021) | MNTH | 6 | $5,000.00 | $5,700.00 | $15,000 |
| 66 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $16,349 | $21,000 | $15,000 |
| 67 | Mobilization (624E10000) | LS | 1 | $292,617 | $203,050 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 11, 2026. Compiled by Mirage Metrics.