ODOT letting results, June 25, 2026

25 contracts let by Ohio DOT on June 25, 2026, $37,939,393 in low bids, a median of 3 bidders per contract. On the 25 with an engineer's estimate, the low bid came in under it 13 times; median low bid -1.0% against the estimate.

Owner
Ohio DOT
Contracts
25
Low bids, total
$37,939,393
Data through
12 NOV 2026

Contracts let that day

ContractProjectCountyBidsLow bidderLow bidSecond bidGapAgainst estimateSource
260308CUY-IR-IR 90-00.00 (FOUR LANE RESURFACING)CUY3Kokosing Construction Company Inc$6,955,876$7,022,927+1.0%0.0%ODOT
260312GUE-SR 146/SR 265/SR 821 VAR (TWO LANE RESURFACING)GUE2Shelly & Sands Inc$4,805,855$5,169,829+8.0%+12%ODOT
260310CUY-SR 10-01.97 (FOUR LANE RESURFACING)CUY4Ronyak Paving Inc$4,357,635$4,595,464+5.0%-3.0%ODOT
260303ATH-SR 13-03.15 & Various (TWO LANE RESURFACING)ATH1Shelly & Sands Inc$3,458,086+10%ODOT
260319FRA-VAR DMS & QWS-FY2026 (SIGNALIZATION)FRA3Ruhlin Company$2,357,443$2,400,967+2.0%+16%ODOT
260307COS-SR 93-19.20 (BRIDGE REPLACEMENT (1 BRIDGE))COS4Complete General Construction Company$1,904,650$2,078,669+9.0%-7.0%ODOT
260304BRO-SR 32-15.29 (MICROSURFACING)BRO1Strawser Construction Inc$1,813,630-1.0%ODOT
260322MOE-CR 48-00.96, MOE-CR 17-00.00 (MINOR RECONSTRUCTION)MOE1Shelly & Sands Inc$1,289,289-4.0%ODOT
260309CUY-S. Waterloo Road (TWO LANE RESURFACING)CUY3Geauga Highway Co$1,265,846$1,296,628+2.0%+2.0%ODOT
268014POR-/SUM Culverts FY2026 (CULVERT REPLACEMENT)POR3Eclipse Co LLC$1,233,250$1,349,754+9.0%-7.0%ODOT
260316D05-FY2027 Bridge Rehab West (BRIDGE REPAIR)District 52Aad Contracting Inc$1,087,192$1,253,688+15%-32%ODOT
260321MAH-LG FY2027 (LIGHTING)MAH4Cornerstone Electric Inc$1,026,569$1,383,553+35%-5.0%ODOT
260311CUY-Van Aken Blvd Resurfacing (FOUR LANE RESURFACING)CUY4Perk Company Inc$1,007,100$1,028,813+2.0%-18%ODOT
260324PER-SR 345-06.48 (BRIDGE REPAIR)PER6Buds Inc$867,500$868,7680.0%-16%ODOT
260317DAR-BH-FY27 (BRIDGE REPAIR)DAR2Vimas Painting Company Inc$688,625$729,945+6.0%+38%ODOT
260320HIG-SR 321-00.00 (MICROSURFACING)HIG1Strawser Construction Inc$614,907+4.0%ODOT
268012VAN-Bonnewitz Avenue Signal (SIGNALIZATION)VAN3Perram Electric Inc$567,680$593,531+5.0%0.0%ODOT
260315D03-CRSEAL FY2027 (CRACK SEALING)District 32Scodeller Construction Inc$565,783$602,987+7.0%+17%ODOT
260313HAS-SR 9-10.24 (SLIDE REPAIR)HAS5Ohio-West Virginia Excavating Co$529,237$574,981+9.0%-6.0%ODOT
260305BRO-Riverfront East Paving (MINOR RECONSTRUCTION)BRO5Fillmore Construction$378,589$388,494+3.0%-11%ODOT
260323POR-Ravenna Rd (Parking Lot) (PARKING AREAS)POR5Madex Construction Co$274,979$297,422+8.0%+2.0%ODOT
264016HAN-SR 15-23.33 (INTERSECTION)HAN2Advanced Excavating & Demolition LLC$249,186$299,652+20%+20%ODOT
260318ERI-ODNR Castalia Hatchery (PARKING AREAS)ERI2Henry W Bergman Inc$219,646$304,016+38%+1.0%ODOT
260314RIC-US 42-03.22 (Lexington) (CULVERT REPLACEMENT)RIC3Crawford Construction Company Inc$214,379$228,340+7.0%-18%ODOT
268013RIC-SR 546-04.98 (BRIDGE REPAIR)RIC2Eius Company$206,459$214,760+4.0%-17%ODOT
ODOT contracts let on June 25, 2026, largest low bid first

Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.