ODOT contract 260311 bid tabulation
CUY-Van Aken Blvd Resurfacing (FOUR LANE RESURFACING). Let by Ohio DOT on June 25, 2026, CUY. 4 bids received; low bid $1,007,100 by Perk Company Inc, -18% against the engineer's estimate of $1,230,000.
- Owner
- Ohio DOT
- Letting
- 25 JUN 2026
- Pay items
- 58
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Perk Company Inc | $1,007,100 | Low | -18% |
| 2 | Geauga Highway Co | $1,028,813 | +2.0% | -16% |
| 3 | Karvo Companies Inc | $1,075,602 | +7.0% | -13% |
| 4 | Phillips Paving LLC | $1,282,675 | +27% | +4.0% |
Engineer's estimate: $1,230,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Perk Company Inc | 2. Geauga Highway Co | 3. Karvo Companies Inc | 4. Phillips Paving LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $30,000 | $500.00 | $1,000.00 | $500.00 |
| 2 | Walk removed, as per plan (202E30001) | SF | 1,003 | $5.00 | $3.50 | $8.00 | $5.00 |
| 3 | Curb removed, as per plan (202E32001) | FT | 250 | $20.00 | $15.00 | $20.00 | $10.00 |
| 4 | Excavation of subgrade (204E13000) | CY | 170 | $1.00 | $60.00 | $5.00 | $25.00 |
| 5 | Granular material, type B (204E30010) | CY | 170 | $10.00 | $60.00 | $25.00 | $75.00 |
| 6 | Geotextile fabric (204E50000) | SY | 340 | $1.00 | $5.00 | $2.00 | $3.00 |
| 7 | Geogrid (204E51000) | SY | 340 | $1.00 | $6.00 | $2.00 | $5.00 |
| 8 | 6" concrete walk, as per plan (608E13001) | SF | 1,003 | $25.00 | $12.50 | $35.00 | $20.00 |
| 9 | Curb ramp, as per plan (608E52001) | SF | 1,169 | $40.00 | $23.00 | $15.00 | $40.00 |
| 10 | Monument assembly, as per plan (623E38501) | EACH | 2 | $100.00 | $1,200.00 | $1,750.00 | $1,500.00 |
| 11 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 2 | $3,000.00 | $650.00 | $1,550.00 | $1,500.00 |
| 12 | Monument, misc.:monument referencing (623E40900) | EACH | 1 | $1,000.00 | $1,650.00 | $400.00 | $750.00 |
| 13 | Seeding and mulching, class 1, as per plan (659E00501) | SY | 70 | $20.00 | $15.00 | $4.00 | $25.00 |
| 14 | Commercial fertilizer (659E20000) | TON | 0.01 | $100.00 | $100.00 | $100.00 | $1,000.00 |
| 15 | Lime (659E31000) | ACRE | 0.05 | $100.00 | $100.00 | $100.00 | $1,000.00 |
| 16 | Water (659E35000) | MGAL | 0.50 | $1.00 | $1,000.00 | $2.00 | $100.00 |
| 17 | Erosion control, as per plan (832E30001) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | 6" unclassified pipe underdrains, as per plan (605E13301) | FT | 50 | $3.00 | $30.00 | $5.00 | $50.00 |
| 19 | 6" conduit, type F for underdrain outlets, as per plan (611E00511) | FT | 50 | $3.00 | $35.00 | $5.00 | $75.00 |
| 20 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 25 | $2,000.00 | $1,200.00 | $1,250.00 | $1,750.00 |
| 21 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 5 | $2,050.00 | $1,900.00 | $1,750.00 | $3,500.00 |
| 22 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 3 | $2,000.00 | $1,200.00 | $1,250.00 | $1,500.00 |
| 23 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 4 | $2,001.00 | $1,900.00 | $1,750.00 | $2,500.00 |
| 24 | Special - miscellaneous metal (611E99820) | LB | 20,000 | $2.50 | $2.30 | $1.00 | $4.00 |
| 25 | Low strength mortar backfill (type 1), as per plan (613E41251) | CY | 50 | $80.00 | $120.00 | $25.00 | $195.00 |
| 26 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 1,200 | $35.00 | $32.00 | $95.00 | $75.00 |
| 27 | Pavement planing, asphalt concrete, as per plan (T (254E01001) | SY | 10,642 | $8.15 | $3.58 | $6.00 | $5.00 |
| 28 | Full depth pavement removal and rigid replacement, type 1, class QC1, as per plan (255E11001) | SY | 800 | $70.00 | $150.00 | $165.00 | $250.00 |
| 29 | Tack coat, 702.13 (407E13900) | GAL | 801 | $4.00 | $3.25 | $3.00 | $2.00 |
| 30 | Non-tracking tack coat (407E20000) | GAL | 1,066 | $4.00 | $3.25 | $3.00 | $2.00 |
| 31 | Asphalt concrete surface course, type 1, (449), as per plan (441E70101) | CY | 370 | $335.00 | $300.00 | $325.00 | $275.00 |
| 32 | Asphalt concrete intermediate course, type 1, (449), as per plan (441E70201) | CY | 516 | $270.00 | $260.00 | $300.00 | $260.00 |
| 33 | 6" non-reinforced concrete pavement, class QC MS, as per plan (452E10051) | SY | 130 | $70.00 | $130.00 | $185.00 | $200.00 |
| 34 | 8" non-reinforced concrete pavement, class QC MS, as per plan (452E12051) | SY | 130 | $75.00 | $150.00 | $200.00 | $250.00 |
| 35 | Curb, type 6, as per plan (609E26001) | FT | 250 | $76.00 | $60.00 | $50.00 | $90.00 |
| 36 | Special - concrete mix design for class QC MS conc (690E98700) | CY | 500 | $1.00 | $7.50 | $15.00 | $50.00 |
| 37 | Longitudinal joint adhesive (875E10000) | LB | 850 | $5.00 | $3.50 | $1.00 | $3.00 |
| 38 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 1 | $2,000.00 | $650.00 | $1,250.00 | $1,500.00 |
| 39 | Water work, misc.:water meter manhole adjusted to (638E98000) | EACH | 2 | $1,250.00 | $1,150.00 | $1,250.00 | $1,500.00 |
| 40 | Water work, misc.:water meter manhole recpnstructe (638E98000) | EACH | 2 | $2,500.00 | $1,850.00 | $2,000.00 | $2,500.00 |
| 41 | Lane line, 4" (644E00200) | MI | 0.66 | $1,990.00 | $3,100.00 | $3,100.00 | $3,100.00 |
| 42 | Channelizing line, 8" (644E00400) | FT | 159 | $2.20 | $1.50 | $1.50 | $1.50 |
| 43 | Stop line (644E00500) | FT | 142 | $14.00 | $9.00 | $9.00 | $9.00 |
| 44 | Crosswalk line, 12" (644E00620) | FT | 672 | $9.00 | $4.00 | $4.00 | $4.00 |
| 45 | Island marking (644E00900) | SF | 1,380 | $9.00 | $1.50 | $1.50 | $1.50 |
| 46 | Parking lot stall marking (644E01200) | FT | 400 | $2.00 | $4.00 | $4.00 | $4.00 |
| 47 | Lane arrow (644E01300) | EACH | 3 | $115.00 | $125.00 | $125.00 | $125.00 |
| 48 | Law enforcement officer with patrol car for assistance, as per plan (614E11111) | HR | 160 | $110.00 | $100.00 | $125.00 | $100.00 |
| 49 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,103.16 | $1,200.00 | $1,200.00 | $1,200.00 |
| 50 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 0.66 | $3,100.00 | $3,500.00 | $1,200.00 | $3,500.00 |
| 51 | Water (616E10000) | MGAL | 50 | $1.00 | $10.00 | $100.00 | $10.00 |
| 52 | Calcium chloride (616E20000) | TON | 5 | $300.00 | $5.00 | $1,600.00 | $10.00 |
| 53 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $5,000.00 | $10,000 | $7,500.00 | $5,000.00 |
| 54 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $9,800.00 | $6,800.00 | $22,900 | $25,000 |
| 55 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $61,000 | $258,000 | $49,651 | $125,000 |
| 56 | Field office, type B, as per plan (619E16011) | MNTH | 3 | $100.00 | $1,000.00 | $3,000.00 | $2,500.00 |
| 57 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $5,000.00 | $1,500.00 | $3,200.00 | $1,000.00 |
| 58 | Mobilization (624E10000) | LS | 1 | $105,790 | $6,500.00 | $100,000 | $97,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 25, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.