ODOT contract 260309 bid tabulation
CUY-S. Waterloo Road (TWO LANE RESURFACING). Let by Ohio DOT on June 25, 2026, CUY. 3 bids received; low bid $1,265,846 by Geauga Highway Co, +2.3% against the engineer's estimate of $1,237,000.
- Owner
- Ohio DOT
- Letting
- 25 JUN 2026
- Pay items
- 88
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Geauga Highway Co | $1,265,846 | Low | +2.0% |
| 2 | Perk Company Inc | $1,296,628 | +2.0% | +5.0% |
| 3 | Karvo Companies Inc | $1,507,471 | +19% | +22% |
Engineer's estimate: $1,237,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Geauga Highway Co | 2. Perk Company Inc | 3. Karvo Companies Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $1,000.00 | $22,000 | $2,000.00 |
| 2 | Pavement removed (202E23000) | SY | 301 | $25.00 | $25.00 | $50.00 |
| 3 | Walk removed, as per plan (202E30001) | SF | 2,614 | $3.00 | $5.00 | $16.00 |
| 4 | Curb removed, as per plan (202E32001) | FT | 1,283 | $12.00 | $20.00 | $16.00 |
| 5 | Guardrail removed (202E38000) | FT | 50 | $20.00 | $20.00 | $16.00 |
| 6 | Catch basin removed (202E58100) | EACH | 1 | $1,000.00 | $1,000.00 | $1,500.00 |
| 7 | Embankment (203E20000) | CY | 93 | $50.00 | $100.00 | $75.00 |
| 8 | Preparing subgrade for shoulder paving, as per plan (209E72001) | STA | 24 | $4,500.00 | $500.00 | $75.00 |
| 9 | 4" concrete walk, as per plan (608E10001) | SF | 2,995 | $11.50 | $25.00 | $18.00 |
| 10 | Curb ramp, as per plan (608E52001) | SF | 399 | $20.00 | $50.00 | $35.00 |
| 11 | Monument assembly, as per plan (623E38501) | EACH | 4 | $1,000.00 | $750.00 | $1,500.00 |
| 12 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 3 | $650.00 | $2,000.00 | $1,250.00 |
| 13 | Monument, misc.:monumnet referencing (623E40900) | EACH | 4 | $350.00 | $200.00 | $700.00 |
| 14 | Topsoil furnished and placed (653E10000) | CY | 27 | $100.00 | $150.00 | $48.00 |
| 15 | Seeding and mulching, class 1 (659E00500) | SY | 231 | $5.00 | $20.00 | $4.00 |
| 16 | Commercial fertilizer (659E20000) | TON | 0.01 | $10.00 | $100.00 | $100.00 |
| 17 | Lime (659E31000) | ACRE | 0.01 | $10.00 | $100.00 | $100.00 |
| 18 | Water (659E35000) | MGAL | 0.12 | $150.00 | $1.00 | $400.00 |
| 19 | Erosion control (832E30000) | EACH | 13,500 | $1.00 | $1.00 | $1.00 |
| 20 | 4" unclassified pipe underdrains, as per plan (605E05201) | FT | 275 | $20.00 | $6.00 | $10.00 |
| 21 | 6" unclassified pipe underdrains, as per plan (605E13301) | FT | 1,262 | $27.50 | $6.00 | $25.00 |
| 22 | 4" conduit, type F for underdrain outlet, as per plan (611E00411) | FT | 30 | $30.00 | $6.00 | $5.00 |
| 23 | 6" conduit, type F for underdrain outlets, as per plan (611E00511) | FT | 70 | $35.00 | $6.00 | $8.00 |
| 24 | 12" conduit, type B (611E04400) | FT | 158 | $100.00 | $100.00 | $200.00 |
| 25 | Catch basin, no. 3A, as per plan (611E98181) | EACH | 4 | $3,000.00 | $2,500.00 | $6,000.00 |
| 26 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 8 | $1,150.00 | $2,000.00 | $1,575.00 |
| 27 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 8 | $1,800.00 | $2,010.00 | $2,000.00 |
| 28 | Manhole, no. 3, as per plan (611E99575) | EACH | 2 | $4,000.00 | $3,000.00 | $8,000.00 |
| 29 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 2 | $1,150.00 | $2,000.00 | $1,250.00 |
| 30 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 1 | $1,800.00 | $2,100.00 | $1,750.00 |
| 31 | Special - miscellaneous metal (611E99820) | LB | 8,875 | $2.25 | $5.00 | $3.00 |
| 32 | Low strength mortar backfill (type 1) (613E41250) | CY | 180 | $135.00 | $20.00 | $125.00 |
| 33 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 135 | $55.00 | $65.00 | $150.00 |
| 34 | Pavement repair, as per plan (253E01001) | SY | 135 | $75.00 | $135.00 | $150.00 |
| 35 | Pavement planing, asphalt concrete, as per plan(T= (254E01001) | SY | 13,786 | $1.90 | $7.00 | $5.00 |
| 36 | Full depth pavement removal and rigid replacement, type 1, class QC1, as per plan (255E11001) | SY | 227 | $145.00 | $280.00 | $250.00 |
| 37 | Full depth pavement sawing (255E20000) | FT | 84 | $9.00 | $10.00 | $5.00 |
| 38 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 25 | $339.00 | $545.00 | $300.00 |
| 39 | Non-tracking tack coat, as per plan (407E20001) | GAL | 1,961 | $3.00 | $4.00 | $3.00 |
| 40 | Prime coat (408E10000) | GAL | 205 | $6.00 | $4.00 | $5.00 |
| 41 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 56 | $350.00 | $385.00 | $500.00 |
| 42 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 449 | $255.00 | $295.00 | $360.00 |
| 43 | Asphalt concrete intermediate course, type 2, (448), as per plan (441E50301) | CY | 691 | $202.00 | $275.00 | $300.00 |
| 44 | 6" non-reinforced concrete pavement, class QC MS, as per plan (452E10051) | SY | 180 | $140.00 | $150.00 | $150.00 |
| 45 | Curb, type 6, as per plan (609E26001) | FT | 1,537 | $45.00 | $75.00 | $30.00 |
| 46 | Compacted aggregate, as per plan (617E10101) | CY | 44 | $150.00 | $115.00 | $100.00 |
| 47 | Longitudinal joint adhesive (875E10000) | LB | 733 | $3.50 | $4.00 | $1.00 |
| 48 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 5 | $650.00 | $2,000.00 | $1,000.00 |
| 49 | Ground mounted support, no. 2 post (630E02100) | FT | 249.20 | $14.00 | $17.90 | $14.00 |
| 50 | Ground mounted support, no. 3 post (630E03100) | FT | 72.20 | $15.00 | $19.40 | $15.00 |
| 51 | Street name sign support, no. 3 post (630E08520) | FT | 26.80 | $16.00 | $19.40 | $16.00 |
| 52 | Sign post reflector (630E08600) | EACH | 8 | $75.00 | $62.70 | $75.00 |
| 53 | Sign support assembly, pole mounted (630E79500) | EACH | 3 | $125.00 | $121.70 | $125.00 |
| 54 | Sign, flat sheet (630E80100) | SF | 129 | $16.00 | $22.25 | $16.00 |
| 55 | Sign, street name, as per plan (630E80511) | EACH | 6 | $285.00 | $216.90 | $285.00 |
| 56 | Removal of ground mounted sign and disposal (630E84900) | EACH | 41 | $30.00 | $17.50 | $30.00 |
| 57 | Removal of ground mounted sign and reerection, as per plan (630E85101) | EACH | 1 | $95.00 | $59.35 | $95.00 |
| 58 | Removal of ground mounted post support and disposal (630E86002) | EACH | 27 | $40.00 | $23.30 | $40.00 |
| 59 | Removal of pole mounted sign and disposal (630E87500) | EACH | 2 | $25.00 | $17.50 | $25.00 |
| 60 | Detector loop, as per plan (632E26501) | EACH | 2 | $1,800.00 | $1,900.00 | $1,800.00 |
| 61 | Edge line, 4" (644E00100) | MI | 0.46 | $4,800.00 | $6,000.00 | $4,800.00 |
| 62 | Lane line, 4" (644E00200) | MI | 0.43 | $2,800.00 | $1,990.00 | $2,800.00 |
| 63 | Channelizing line, 8" (644E00400) | FT | 729 | $1.50 | $2.25 | $1.50 |
| 64 | Crosswalk line, 12" (644E00620) | FT | 93 | $5.00 | $9.00 | $5.00 |
| 65 | Chevron marking (644E00720) | FT | 56 | $9.00 | $14.00 | $9.00 |
| 66 | Lane arrow (644E01300) | EACH | 6 | $125.00 | $110.00 | $125.00 |
| 67 | Dotted line, 4" (644E01500) | FT | 680 | $3.00 | $1.05 | $3.00 |
| 68 | Traffic compacted surface, type A or B (410E12000) | CY | 75 | $50.00 | $10.00 | $25.00 |
| 69 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $100.00 | $150.00 | $125.00 |
| 70 | Asphalt concrete for maintaining traffic (614E13000) | CY | 150 | $5.00 | $50.00 | $250.00 |
| 71 | Portable changeable message sign, as per plan (614E18601) | SNMT | 10 | $1,000.00 | $1,000.00 | $1,000.00 |
| 72 | Work zone lane line, class I, 4", 642 paint (614E20100) | MI | 0.62 | $1,500.00 | $975.00 | $1,500.00 |
| 73 | Work zone lane line, class III, 4", 642 paint (614E20550) | MI | 0.43 | $1,500.00 | $960.00 | $1,500.00 |
| 74 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 2.08 | $2,100.00 | $1,530.00 | $2,100.00 |
| 75 | Work zone edge line, class I, 4", 740.06, type I (614E22200) | MI | 0.52 | $8,350.00 | $10,125 | $8,350.00 |
| 76 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 0.46 | $2,100.00 | $1,510.00 | $2,100.00 |
| 77 | Work zone channelizing line, class I, 8", 642 paint (614E23200) | FT | 650 | $1.25 | $1.50 | $1.25 |
| 78 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 729 | $1.25 | $1.50 | $1.25 |
| 79 | Work zone dotted line, class III, 4", 642 paint (614E24610) | FT | 680 | $3.00 | $1.00 | $3.00 |
| 80 | Work zone arrow, class I, 642 paint (614E30200) | EACH | 6 | $85.00 | $70.00 | $85.00 |
| 81 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 6 | $85.00 | $70.00 | $85.00 |
| 82 | Water (616E10000) | MGAL | 50 | $150.00 | $1.00 | $5.00 |
| 83 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $17,000 | $12,800 | $25,000 |
| 84 | Maintaining traffic (614E11000) | LS | 1 | $324,000 | $23,642 | $118,768 |
| 85 | Field office, type B, as per plan (619E16011) | MNTH | 12 | $850.00 | $2,800.00 | $3,000.00 |
| 86 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $1,500.00 | $8,000.00 | $20,000 |
| 87 | Mobilization (624E10000) | LS | 1 | $3,500.00 | $88,000 | $171,026 |
| 88 | Special - pre-construction video (690E98400) | LS | 1 | $1,200.00 | $1,000.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 25, 2026. Compiled by Mirage Metrics.