ODOT contract 260307 bid tabulation
COS-SR 93-19.20 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on June 25, 2026, COS. 4 bids received; low bid $1,904,650 by Complete General Construction Company, -7.1% against the engineer's estimate of $2,050,000.
- Owner
- Ohio DOT
- Letting
- 25 JUN 2026
- Pay items
- 81
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Complete General Construction Company | $1,904,650 | Low | -7.0% |
| 2 | Shelly & Sands Inc | $2,078,669 | +9.0% | +1.0% |
| 3 | Alan Stone Co Inc | $2,389,974 | +25% | +17% |
| 4 | Perk Company Inc | $2,999,990 | +58% | +46% |
Engineer's estimate: $2,050,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Complete General Construction Company | 2. Shelly & Sands Inc | 3. Alan Stone Co Inc | 4. Perk Company Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $6,000.00 | $2,000.00 | $60,000 | $9,500.00 |
| 2 | Pavement removed (202E23000) | SY | 377 | $24.00 | $28.00 | $25.00 | $38.55 |
| 3 | Wearing course removed (202E23500) | SY | 67 | $15.00 | $20.00 | $20.00 | $47.90 |
| 4 | Guardrail removed (202E38000) | FT | 675 | $2.40 | $5.00 | $4.00 | $6.80 |
| 5 | Excavation, as per plan (203E10001) | CY | 446 | $32.00 | $20.00 | $30.00 | $60.15 |
| 6 | Embankment (203E20000) | CY | 1,210 | $35.00 | $25.00 | $30.00 | $46.60 |
| 7 | Subgrade compaction (204E10000) | SY | 819 | $4.50 | $10.00 | $4.50 | $2.30 |
| 8 | Reshaping under guardrail (209E15000) | STA | 7.40 | $80.00 | $50.00 | $200.00 | $525.00 |
| 9 | Borrow (209E70000) | CY | 20 | $70.00 | $50.00 | $75.00 | $225.00 |
| 10 | Guardrail, type MGS (606E15050) | FT | 750 | $20.40 | $24.00 | $30.00 | $20.40 |
| 11 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 3 | $2,520.00 | $2,700.00 | $2,600.00 | $2,520.00 |
| 12 | Anchor assembly, type T (606E26500) | EACH | 1 | $1,395.00 | $1,000.00 | $990.00 | $1,395.00 |
| 13 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 4 | $2,560.00 | $2,700.00 | $3,200.00 | $2,560.00 |
| 14 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,200.00 | $3,100.00 | $3,500.00 | $3,500.00 |
| 15 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,200.00 | $3,100.00 | $3,500.00 | $3,500.00 |
| 16 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 7 | $115.00 | $153.00 | $220.00 | $250.00 |
| 17 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 536 | $130.00 | $100.00 | $230.00 | $200.00 |
| 18 | Precast reinforced concrete outlet (611E99710) | EACH | 4 | $350.00 | $375.00 | $350.00 | $540.00 |
| 19 | Seeding and mulching, class 2 (659E00510) | SY | 3,672 | $1.00 | $1.00 | $20.00 | $3.30 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.50 | $1,250.00 | $1,250.00 | $980.00 | $600.00 |
| 21 | Lime (659E31000) | ACRE | 0.80 | $150.00 | $150.00 | $400.00 | $1,000.00 |
| 22 | Water (659E35000) | MGAL | 20 | $1.00 | $1.00 | $15.00 | $50.00 |
| 23 | Erosion control (832E30000) | EACH | 4,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Full depth pavement sawing (252E01500) | FT | 725 | $5.00 | $2.10 | $8.50 | $3.40 |
| 25 | Pavement planing, asphalt concrete, 3 1/4" (254E01000) | SY | 1,070 | $11.00 | $11.26 | $15.00 | $8.00 |
| 26 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 122 | $256.00 | $256.00 | $360.00 | $425.00 |
| 27 | Aggregate base (304E20000) | CY | 97 | $140.00 | $150.00 | $100.00 | $108.00 |
| 28 | Non-tracking tack coat (407E20000) | GAL | 165 | $4.10 | $4.10 | $5.00 | $2.75 |
| 29 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 45 | $270.00 | $270.00 | $400.00 | $650.00 |
| 30 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 52 | $240.00 | $240.00 | $370.00 | $460.00 |
| 31 | Raised pavement marker removed (621E54000) | EACH | 9 | $24.00 | $40.00 | $25.00 | $75.00 |
| 32 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 19 | $12.00 | $12.00 | $15.00 | $12.00 |
| 33 | Ground mounted support, no. 3 post (630E03100) | FT | 50 | $20.00 | $18.00 | $20.00 | $20.00 |
| 34 | Sign, flat sheet (630E80100) | SF | 14 | $25.00 | $25.00 | $35.00 | $25.00 |
| 35 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $15.00 | $25.00 | $30.00 | $15.00 |
| 36 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $60.00 | $75.00 | $90.00 | $16.00 |
| 37 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $20.00 | $25.00 | $35.00 | $20.00 |
| 38 | Edge line, 6" (646E10010) | MI | 0.18 | $22,000 | $22,000 | $25,000 | $25,000 |
| 39 | Center line (646E10200) | MI | 0.09 | $22,000 | $22,000 | $20,000 | $25,000 |
| 40 | Traffic compacted surface, type C (410E13000) | CY | 10 | $120.00 | $151.00 | $100.00 | $195.00 |
| 41 | Detour signing (614E12420) | LS | 1 | $9,000.00 | $4,934.00 | $6,900.00 | $5,000.00 |
| 42 | Asphalt concrete for maintaining traffic (614E13000) | CY | 20 | $300.00 | $605.00 | $250.00 | $275.00 |
| 43 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,150.00 | $1,200.00 | $1,400.00 | $1,365.00 |
| 44 | Structure removed, over 20 foot span (202E11002) | LS | 1 | $65,000 | $71,000 | $54,000 | $265,000 |
| 45 | Approach slab removed (202E22900) | SY | 67 | $60.00 | $175.00 | $45.00 | $87.00 |
| 46 | Bridge railing removed (202E38500) | FT | 200 | $10.00 | $15.00 | $15.00 | $21.50 |
| 47 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $25,000 | $40,000 | $500.00 | $150,000 |
| 48 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $60,000 | $90,000 | $69,000 | $62,200 |
| 49 | Pile driving equipment mobilization (505E11100) | LS | 1 | $15,000 | $22,000 | $38,000 | $13,300 |
| 50 | Steel piles HP10X42, furnished (507E00100) | FT | 945 | $65.00 | $40.00 | $45.00 | $52.75 |
| 51 | Steel piles HP10X42, driven (507E00150) | FT | 855 | $10.00 | $50.00 | $40.00 | $240.00 |
| 52 | Steel piles HP12X53, furnished (507E00200) | FT | 720 | $75.00 | $50.00 | $60.00 | $66.60 |
| 53 | Steel piles HP12X53, driven (507E00250) | FT | 660 | $15.00 | $48.00 | $35.00 | $250.00 |
| 54 | Special - pile encasement (507E71200) | FT | 216 | $230.00 | $180.00 | $120.00 | $300.00 |
| 55 | Steel points or shoes (507E93300) | EACH | 30 | $145.00 | $140.00 | $130.00 | $350.00 |
| 56 | Galvanized steel reinforcement (509E26000) | LB | 65,152 | $2.20 | $3.00 | $3.00 | $2.50 |
| 57 | Class QC2 concrete with QC/QA, superstructure (511E33312) | CY | 250 | $1,400.00 | $1,350.00 | $2,000.00 | $1,650.00 |
| 58 | Class QC1 concrete, abutment not including footing (511E44110) | CY | 46 | $1,200.00 | $1,512.00 | $930.00 | $1,265.00 |
| 59 | Class QC1 concrete, footing (511E46510) | CY | 39 | $800.00 | $1,210.00 | $590.00 | $1,035.00 |
| 60 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 123 | $20.00 | $20.00 | $15.00 | $48.00 |
| 61 | Type 2 waterproofing (512E33000) | SY | 13 | $68.00 | $68.00 | $35.00 | $75.00 |
| 62 | 1/2" preformed expansion joint filler, as per plan (516E13201) | SF | 60 | $14.00 | $12.00 | $1.00 | $15.00 |
| 63 | 1" preformed expansion joint filler, as per plan (516E13601) | SF | 86 | $17.00 | $12.00 | $2.50 | $15.00 |
| 64 | Integral abutment expansion joint seal (516E14014) | FT | 95 | $55.00 | $55.00 | $40.00 | $58.50 |
| 65 | Structural joint or joint sealer, misc.:waterstop (516E14600) | FT | 73 | $400.00 | $600.00 | $250.00 | $430.00 |
| 66 | 2" deep joint sealer, as per plan (516E31011) | FT | 73 | $27.00 | $27.00 | $100.00 | $38.60 |
| 67 | Railing (three steel tube bridge railing) (517E70100) | FT | 214 | $505.00 | $470.00 | $550.00 | $517.50 |
| 68 | Porous backfill with geotextile fabric (518E21200) | CY | 63 | $112.00 | $175.00 | $140.00 | $170.00 |
| 69 | Special - steel drip strip (518E22300) | FT | 244 | $22.00 | $16.00 | $25.00 | $27.70 |
| 70 | 6" perforated corrugated plastic pipe (518E40000) | FT | 118 | $9.00 | $8.00 | $25.00 | $30.00 |
| 71 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 60 | $24.00 | $8.00 | $15.00 | $50.00 |
| 72 | Reinforced concrete approach slabs (T=13"), as per plan (526E15001) | SY | 160 | $440.00 | $735.00 | $430.00 | $540.00 |
| 73 | Special - structural survey and monitoring of vibration (530E14000) | LS | 1 | $21,000 | $5,898.00 | $15,000 | $10,000 |
| 74 | Structure grounding system (625E33000) | EACH | 4 | $5,000.00 | $6,000.00 | $14,250 | $10,000 |
| 75 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $13,000 | $11,000 | $25,000 | $25,000 |
| 76 | Maintaining traffic (614E11000) | LS | 1 | $10,000 | $1,767.00 | $18,000 | $23,700 |
| 77 | Field office, type A (619E16000) | MNTH | 3 | $3,300.00 | $7,500.00 | $1,000.00 | $2,300.00 |
| 78 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $25,000 | $29,000 | $35,000 | $25,000 |
| 79 | Mobilization (624E10000) | LS | 1 | $100,000 | $103,926 | $156,000 | $205,000 |
| 80 | Special - calendar days of contract time for opening to traffic (unit price field should reflect number of days bid) (614E15000) | DLR | 2,500 | $70.00 | $70.00 | $70.00 | $70.00 |
| 100 | Excavation (203E10000) | CY | 1,077 | $38.00 | $40.00 | $35.00 | $45.20 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 25, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.