ODOT contract 260310 bid tabulation
CUY-SR 10-01.97 (FOUR LANE RESURFACING). Let by Ohio DOT on June 25, 2026, CUY. 4 bids received; low bid $4,357,635 by Ronyak Paving Inc, -3.2% against the engineer's estimate of $4,501,000.
- Owner
- Ohio DOT
- Letting
- 25 JUN 2026
- Pay items
- 132
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ronyak Paving Inc | $4,357,635 | Low | -3.0% |
| 2 | Perk Company Inc | $4,595,464 | +5.0% | +2.0% |
| 3 | Karvo Companies Inc | $4,975,297 | +14% | +11% |
| 4 | Shelly Company | $5,061,501 | +16% | +12% |
Engineer's estimate: $4,501,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ronyak Paving Inc | 2. Perk Company Inc | 3. Karvo Companies Inc | 4. Shelly Company |
|---|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 1,480 | $20.00 | $22.00 | $30.00 | $20.00 |
| 2 | Walk removed, as per plan (202E30001) | SF | 8,412 | $2.00 | $2.50 | $8.00 | $2.00 |
| 3 | Curb removed, as per plan (202E32001) | FT | 3,950 | $12.00 | $5.00 | $30.00 | $12.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 12 | $30.00 | $45.00 | $25.00 | $30.00 |
| 5 | Excavation (203E10000) | CY | 207 | $50.00 | $35.00 | $100.00 | $50.00 |
| 6 | Subgrade compaction (204E10000) | SY | 1,240 | $1.00 | $2.00 | $1.00 | $1.00 |
| 7 | Excavation of subgrade (204E13000) | CY | 25 | $75.00 | $45.00 | $15.00 | $75.00 |
| 8 | Granular embankment, as per plan (204E21001) | CY | 12 | $50.00 | $150.00 | $35.00 | $50.00 |
| 9 | Granular material, type B (204E30010) | CY | 25 | $50.00 | $150.00 | $75.00 | $50.00 |
| 10 | Geotextile fabric (204E50000) | SY | 50 | $3.00 | $3.50 | $2.00 | $3.00 |
| 11 | Geogrid (204E51000) | SY | 50 | $2.00 | $6.00 | $2.00 | $2.00 |
| 12 | 4" concrete walk, as per plan (608E10001) | SF | 4,159 | $12.00 | $16.50 | $15.00 | $12.00 |
| 13 | 6" concrete walk, as per plan (608E13001) | SF | 415 | $13.00 | $25.00 | $20.00 | $13.00 |
| 14 | Curb ramp, as per plan (608E52001) | SF | 3,790 | $25.00 | $28.50 | $25.00 | $25.00 |
| 15 | Walkway, misc.: colored & stamped concrete walk (608E98000) | SF | 150 | $50.00 | $60.00 | $25.00 | $50.00 |
| 16 | Walkway, misc.: paver replacement (608E98000) | SF | 150 | $25.00 | $60.00 | $50.00 | $25.00 |
| 17 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 17 | $700.00 | $1,300.00 | $1,250.00 | $700.00 |
| 18 | Monument, misc.:cuy county centerline monument box (623E40900) | EACH | 5 | $1,550.00 | $1,300.00 | $1,650.00 | $1,000.00 |
| 19 | Monument, misc.:cuy county monument box (623E40900) | EACH | 5 | $1,550.00 | $1,300.00 | $1,650.00 | $1,000.00 |
| 20 | Monument, misc.:monument referencing (623E40900) | EACH | 17 | $400.00 | $125.00 | $250.00 | $400.00 |
| 21 | Topsoil furnished and placed (653E10000) | CY | 90 | $90.00 | $75.00 | $100.00 | $90.00 |
| 22 | Erosion control, as per plan (832E30001) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 500 | $17.00 | $6.00 | $20.00 | $17.00 |
| 24 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 100 | $20.00 | $6.00 | $5.00 | $20.00 |
| 25 | 12" conduit, type B, as per plan (611E04401) | FT | 235 | $250.00 | $385.65 | $150.00 | $185.00 |
| 26 | 12" conduit, type B, as per plan (611E04401) | FT | 71 | $285.00 | $424.60 | $175.00 | $195.00 |
| 27 | 15" conduit, type B, as per plan (611E05901) | FT | 12 | $500.00 | $447.10 | $250.00 | $250.00 |
| 28 | Catch basin, no. 3A (611E98180) | EACH | 4 | $5,500.00 | $8,200.50 | $7,500.00 | $5,500.00 |
| 29 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 18 | $1,050.00 | $1,650.00 | $1,775.00 | $1,050.00 |
| 30 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 18 | $1,250.00 | $1,950.00 | $2,200.00 | $1,250.00 |
| 31 | Manhole, no. 3 (611E99574) | EACH | 1 | $7,700.00 | $11,330 | $7,500.00 | $7,700.00 |
| 32 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 7 | $1,075.00 | $1,650.00 | $1,500.00 | $1,075.00 |
| 33 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 21 | $1,225.00 | $1,950.00 | $2,000.00 | $1,225.00 |
| 34 | Special - miscellaneous metal (611E99820) | LB | 48,320 | $2.00 | $2.45 | $2.00 | $2.00 |
| 35 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 1,435 | $85.00 | $44.00 | $80.00 | $80.00 |
| 36 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 2,700 | $80.00 | $42.00 | $60.00 | $100.00 |
| 37 | Pavement repair, as per plan (253E02001) | CY | 1,100 | $450.00 | $238.00 | $200.00 | $400.00 |
| 38 | Pavement planing, asphalt concrete, as per PLAN3" (254E01001) | SY | 62,674 | $5.00 | $5.75 | $6.00 | $3.15 |
| 39 | Full depth pavement removal and rigid replacement, type 1, class QC MS, as per plan (255E15001) | SY | 100 | $435.00 | $325.00 | $300.00 | $330.00 |
| 40 | Full depth pavement sawing (255E20000) | FT | 250 | $6.00 | $7.50 | $5.00 | $5.50 |
| 41 | Aggregate base, as per plan (304E20001) | CY | 224 | $100.00 | $74.50 | $100.00 | $100.00 |
| 42 | 9" concrete base, class QC 1P (305E13010) | SY | 23 | $500.00 | $435.00 | $200.00 | $500.00 |
| 43 | Non-tracking tack coat (407E20000) | GAL | 3,453 | $3.00 | $3.20 | $3.00 | $2.75 |
| 44 | Aggregate, single chip seal, type A (422E11000) | SY | 62,765 | $1.00 | $2.25 | $0.50 | $2.00 |
| 45 | Emulsion, chip seal (422E25000) | GAL | 25,106 | $2.00 | $3.00 | $5.00 | $3.00 |
| 46 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 2,180 | $265.00 | $278.00 | $300.00 | $280.00 |
| 47 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 3,052 | $205.00 | $268.00 | $250.00 | $220.00 |
| 48 | 6" non-reinforced concrete pavement, class QC MS (452E10050) | SY | 40 | $85.00 | $165.00 | $100.00 | $85.00 |
| 49 | 8" non-reinforced concrete pavement, class QC MS (452E12050) | SY | 1,200 | $85.00 | $155.00 | $115.00 | $85.00 |
| 50 | Curb, type 2-B (609E16000) | FT | 297 | $25.00 | $77.00 | $60.00 | $25.00 |
| 51 | Curb, type 6, as per plan (609E26001) | FT | 3,528 | $40.00 | $10.00 | $35.00 | $40.00 |
| 52 | Longitudinal joint adhesive (875E10000) | LB | 5,796 | $3.00 | $3.00 | $1.00 | $4.00 |
| 53 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 88 | $700.00 | $1,100.00 | $1,200.00 | $700.00 |
| 54 | Water work, misc.: water manhole adjusted to grade (638E98000) | EACH | 1 | $1,000.00 | $1,850.00 | $1,200.00 | $1,000.00 |
| 55 | Ground mounted support, no. 3 post (630E03100) | FT | 30 | $150.00 | $15.00 | $10.00 | $15.00 |
| 56 | Sign hanger assembly, mast arm, as per plan (630E79101) | EACH | 2 | $550.00 | $550.00 | $525.00 | $550.00 |
| 57 | Sign support assembly, pole mounted (630E79500) | EACH | 8 | $105.00 | $105.00 | $125.00 | $105.00 |
| 58 | Sign, flat sheet (630E80100) | SF | 54 | $18.00 | $18.00 | $25.00 | $18.00 |
| 59 | Channelizing line, 8" (644E00400) | FT | 1,701 | $1.05 | $1.05 | $2.50 | $1.05 |
| 60 | Stop line (644E00500) | FT | 1,012 | $9.00 | $9.00 | $7.25 | $9.00 |
| 61 | Crosswalk line, 12" (644E00620) | FT | 366 | $4.50 | $4.50 | $6.00 | $4.50 |
| 62 | Crosswalk line, 12", as per plan (644E00621) | FT | 3,329 | $4.50 | $4.50 | $6.00 | $4.50 |
| 63 | Crosswalk line, 24", as per plan (644E00631) | FT | 3,340 | $8.50 | $8.50 | $7.25 | $8.50 |
| 64 | Transverse/diagonal line (644E00700) | FT | 157 | $8.50 | $8.50 | $7.25 | $8.50 |
| 65 | Island marking (644E00900) | SF | 60 | $4.50 | $4.50 | $7.25 | $4.50 |
| 66 | School symbol marking, 120" (644E01120) | EACH | 2 | $950.00 | $950.00 | $550.00 | $950.00 |
| 67 | Lane arrow (644E01300) | EACH | 62 | $105.00 | $105.00 | $125.00 | $105.00 |
| 68 | Dotted line, 4" (644E01500) | FT | 153 | $3.00 | $3.00 | $1.50 | $3.00 |
| 69 | Edge line, 4" (646E10000) | MI | 0.02 | $4,500.00 | $4,500.00 | $3,800.00 | $4,500.00 |
| 70 | Lane line, 4" (646E10100) | MI | 3.38 | $2,800.00 | $2,800.00 | $1,930.00 | $2,800.00 |
| 71 | Center line (646E10200) | MI | 2.61 | $5,100.00 | $5,100.00 | $4,424.00 | $5,100.00 |
| 72 | Conduit, 2", 725.051 (625E25408) | FT | 48 | $7.50 | $7.50 | $7.50 | $7.50 |
| 73 | Conduit, 3", 725.051 (625E25504) | FT | 5 | $9.50 | $9.50 | $9.50 | $9.50 |
| 74 | Conduit, jacked or drilled, 725.051, 3" (625E25906) | FT | 79 | $95.00 | $95.00 | $95.00 | $95.00 |
| 75 | Trench (625E29000) | FT | 53 | $15.00 | $15.00 | $15.00 | $15.00 |
| 76 | Pull box, 725.08, 18" (625E30700) | EACH | 4 | $950.00 | $950.00 | $950.00 | $950.00 |
| 77 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $1,250.00 | $1,250.00 | $1,250.00 | $1,250.00 |
| 78 | Pull box, misc.: adjust to grade (625E31600) | EACH | 6 | $400.00 | $400.00 | $400.00 | $400.00 |
| 79 | Ground rod, as per plan (625E32001) | EACH | 6 | $350.00 | $350.00 | $350.00 | $350.00 |
| 80 | Underground warning/marking tape, as per plan (625E36011) | FT | 53 | $3.50 | $3.50 | $3.50 | $3.50 |
| 81 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 2 | $675.00 | $675.00 | $675.00 | $675.00 |
| 82 | Pedestrian pushbutton, as per plan (632E26001) | EACH | 2 | $325.00 | $325.00 | $325.00 | $325.00 |
| 83 | Signal cable, 2 conductor, no. 14 AWG (632E40200) | FT | 164 | $1.60 | $1.60 | $1.60 | $1.60 |
| 84 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 186 | $1.85 | $1.85 | $1.85 | $1.85 |
| 85 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 456 | $2.25 | $2.25 | $2.25 | $2.25 |
| 86 | Signal support foundation (632E64010) | EACH | 2 | $7,200.00 | $7,200.00 | $7,200.00 | $7,200.00 |
| 87 | Pedestal foundation (632E64020) | EACH | 2 | $2,100.00 | $2,100.00 | $2,100.00 | $2,100.00 |
| 88 | Power cable, 2 conductor, no. 6 AWG (632E68200) | FT | 30 | $6.00 | $6.00 | $6.00 | $6.00 |
| 89 | Service cable, 3 conductor, no. 6 AWG (632E69800) | FT | 50 | $9.00 | $9.00 | $9.00 | $9.00 |
| 90 | Power service, as per plan (632E70001) | EACH | 1 | $3,100.00 | $3,100.00 | $3,100.00 | $3,100.00 |
| 91 | Conduit riser, 3" diameter (632E70600) | EACH | 1 | $350.00 | $350.00 | $350.00 | $350.00 |
| 92 | Signal support, type TC-81.22, design 4, as per plan (632E72111) | EACH | 2 | $15,420 | $15,420 | $15,420 | $15,420 |
| 93 | Pedestal, 14.4' tall, transformer base (632E89930) | EACH | 2 | $2,700.00 | $2,700.00 | $2,700.00 | $2,700.00 |
| 94 | Signalization, misc.: foundation test hole (632E90400) | EACH | 5 | $600.00 | $600.00 | $600.00 | $600.00 |
| 95 | Signalization, misc.: pedestrian hybrid beacon (632E90400) | EACH | 4 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 96 | Cabinet foundation, as per plan (633E67101) | EACH | 1 | $3,800.00 | $3,800.00 | $3,800.00 | $3,800.00 |
| 97 | Controller work pad, as per plan (633E67201) | EACH | 1 | $900.00 | $900.00 | $900.00 | $900.00 |
| 98 | Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001) | EACH | 1 | $8,800.00 | $8,800.00 | $8,800.00 | $8,800.00 |
| 99 | Controller item, misc.:controlled, actuated, 8 pha (633E99000) | EACH | 1 | $20,325 | $20,325 | $20,325 | $20,325 |
| 100 | Mulch (661E00500) | CY | 16 | $75.00 | $62.90 | $75.00 | $75.00 |
| 101 | Perennials hemerocallis 'going bananas' (going ban (661E14000) | EACH | 42 | $50.00 | $17.70 | $60.00 | $60.00 |
| 102 | Perennials liriope muscari 'royal purple' (royal P (661E14000) | EACH | 120 | $50.00 | $17.40 | $80.00 | $80.00 |
| 103 | Perennials nepeta X faassenii 'walkers low' (walke (661E14000) | EACH | 72 | $50.00 | $24.60 | $60.00 | $60.00 |
| 104 | Deciduous shrub, 12" height, rhus aromatica 'gro-L (661E19000) | EACH | 32 | $150.00 | $59.15 | $120.00 | $120.00 |
| 105 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 400 | $125.00 | $110.00 | $125.00 | $130.00 |
| 106 | Work zone lane line, class I, 4", 642 paint (614E20100) | MI | 4.46 | $600.00 | $600.00 | $725.00 | $600.00 |
| 107 | Work zone lane line, class III, 4", 642 paint (614E20550) | MI | 1.67 | $600.00 | $600.00 | $575.00 | $600.00 |
| 108 | Work zone center line, class I, 642 paint (614E21100) | MI | 6.76 | $1,300.00 | $1,300.00 | $1,500.00 | $1,300.00 |
| 109 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.61 | $15,700 | $15,700 | $13,500 | $15,700 |
| 110 | Work zone center line, class III, 642 paint (614E21550) | MI | 1.24 | $1,300.00 | $1,300.00 | $1,500.00 | $1,300.00 |
| 111 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 6.18 | $900.00 | $900.00 | $1,150.00 | $900.00 |
| 112 | Work zone edge line, class I, 4", 740.06, type I (614E22200) | MI | 0.94 | $8,300.00 | $8,300.00 | $10,000 | $8,300.00 |
| 113 | Work zone channelizing line, class I, 8", 642 paint (614E23200) | FT | 4,945 | $1.05 | $1.05 | $0.80 | $1.05 |
| 114 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 1,138 | $1.05 | $1.05 | $0.80 | $1.05 |
| 115 | Work zone dotted line, class III, 4", 642 paint (614E24610) | FT | 153 | $3.00 | $3.00 | $0.75 | $3.00 |
| 116 | Work zone transverse/diagonal line, class I, 642 paint (614E25200) | FT | 316 | $2.70 | $2.70 | $2.50 | $2.70 |
| 117 | Work zone stop line, class I, 642 paint (614E26200) | FT | 1,589 | $5.00 | $5.00 | $4.00 | $5.00 |
| 118 | Work zone stop line, class III, 642 paint (614E26610) | FT | 721 | $5.00 | $5.00 | $4.00 | $5.00 |
| 119 | Work zone crosswalk line, class I, 12", 642 paint (614E27050) | FT | 1,468 | $2.50 | $2.50 | $3.75 | $2.50 |
| 120 | Work zone crosswalk line, class III, 12", 642 paint (614E27250) | FT | 2,097 | $2.50 | $2.50 | $3.75 | $2.50 |
| 121 | Work zone arrow, class I, 642 paint (614E30200) | EACH | 190 | $75.00 | $75.00 | $65.00 | $75.00 |
| 122 | Work zone arrow, class I, 740.06, type I (614E30400) | EACH | 5 | $120.00 | $120.00 | $250.00 | $120.00 |
| 123 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 31 | $75.00 | $75.00 | $65.00 | $75.00 |
| 124 | Work zone island marking, class I (614E32700) | SF | 150 | $2.00 | $2.00 | $5.00 | $2.00 |
| 125 | Work zone island marking, class III, 642 paint (614E32800) | SF | 30 | $2.00 | $2.00 | $5.00 | $2.00 |
| 126 | Water (616E10000) | MGAL | 10 | $10.00 | $1.00 | $5.00 | $20.00 |
| 127 | Calcium chloride (616E20000) | TON | 1 | $1.00 | $300.00 | $25.00 | $100.00 |
| 128 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,985 | $45,500 | $50,000 | $25,000 |
| 129 | Maintaining traffic (614E11000) | LS | 1 | $300,000 | $274,069 | $349,000 | $871,500 |
| 130 | Field office, type B, as per plan (619E16011) | MNTH | 12 | $1,500.00 | $2,500.00 | $3,000.00 | $5,000.00 |
| 131 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $20,950 | $12,500 | $35,000 | $25,000 |
| 132 | Mobilization (624E10000) | LS | 1 | $121,000 | $250,000 | $415,000 | $200,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 25, 2026. Compiled by Mirage Metrics.