ODOT contract 260321 bid tabulation
MAH-LG FY2027 (LIGHTING). Let by Ohio DOT on June 25, 2026, MAH. 4 bids received; low bid $1,026,569 by Cornerstone Electric Inc, -4.6% against the engineer's estimate of $1,076,000.
- Owner
- Ohio DOT
- Letting
- 25 JUN 2026
- Pay items
- 43
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cornerstone Electric Inc | $1,026,569 | Low | -5.0% |
| 2 | Ruhlin Company | $1,383,553 | +35% | +29% |
| 3 | Perram Electric Inc | $1,432,132 | +40% | +33% |
| 4 | Miller Cable Company | $2,296,494 | +124% | +113% |
Engineer's estimate: $1,076,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cornerstone Electric Inc | 2. Ruhlin Company | 3. Perram Electric Inc | 4. Miller Cable Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $100.00 | $1,500.00 | $3,710.00 | $4,000.00 |
| 2 | Special - as-built construction plans (690E91000) | LS | 1 | $1,000.00 | $1,256.00 | $5,450.00 | $6,850.00 |
| 3 | Special - surveying control verification (690E98400) | LS | 1 | $1,000.00 | $700.00 | $3,080.00 | $3,750.00 |
| 4 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 5 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 36 | $50.00 | $197.00 | $738.00 | $300.00 |
| 6 | 4" conduit, type C (611E00200) | FT | 200 | $5.00 | $25.00 | $21.05 | $46.00 |
| 7 | 4" conduit, type E, as per plan (611E00401) | FT | 400 | $5.00 | $25.00 | $21.55 | $43.00 |
| 8 | Precast reinforced concrete outlet (611E99710) | EACH | 20 | $200.00 | $330.00 | $771.00 | $1,400.00 |
| 9 | Connection, fused pull apart (625E00450) | EACH | 12 | $125.00 | $195.00 | $180.00 | $285.00 |
| 10 | Connection, unfused permanent (625E00480) | EACH | 57 | $125.00 | $135.00 | $152.00 | $285.00 |
| 11 | Light pole, conventional, AT15B35 (625E10490) | EACH | 6 | $3,500.00 | $3,525.00 | $3,230.00 | $6,600.00 |
| 12 | Light tower, BBB100 (625E12200) | EACH | 14 | $27,000 | $30,250 | $26,965 | $35,500 |
| 13 | Light pole foundation, 24" X 10' deep (625E14200) | EACH | 6 | $1,500.00 | $1,950.00 | $3,755.00 | $6,300.00 |
| 14 | Light tower foundation, 36" X 25' deep (625E15200) | EACH | 14 | $10,000 | $14,250 | $17,715 | $20,250 |
| 15 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 2,098 | $4.00 | $4.60 | $4.92 | $9.00 |
| 16 | No. 2 AWG 2400 volt distribution cable (625E23300) | FT | 687 | $6.00 | $6.80 | $6.15 | $11.00 |
| 17 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 5,937 | $12.00 | $19.00 | $14.83 | $19.00 |
| 18 | 1-1/2" duct cable with three no. 2 AWG 2400 volt cables (625E24330) | FT | 1,588 | $16.00 | $24.00 | $18.80 | $24.00 |
| 19 | Conduit, jacked or drilled, 725.04, 3" (625E25902) | FT | 785 | $61.00 | $95.00 | $66.00 | $150.00 |
| 20 | Luminaire, conventional, solid state (LED) (10000- (625E26252) | EACH | 6 | $350.00 | $475.00 | $475.00 | $700.00 |
| 21 | Luminaire, high mast, solid state (LED) (60000-650 (625E26262) | EACH | 42 | $1,200.00 | $1,565.00 | $1,273.00 | $1,600.00 |
| 22 | Trench (625E29000) | FT | 7,225 | $7.00 | $11.00 | $10.16 | $31.00 |
| 23 | Pull box, 725.08, 24" (625E30706) | EACH | 20 | $1,500.00 | $1,525.00 | $2,200.00 | $2,800.00 |
| 24 | Pull box removed (625E31510) | EACH | 37 | $200.00 | $350.00 | $103.00 | $1,000.00 |
| 25 | Ground rod (625E32000) | EACH | 34 | $200.00 | $350.00 | $320.00 | $550.00 |
| 26 | Power service, as per plan (625E34001) | EACH | 1 | $10,000 | $14,815 | $10,430 | $20,500 |
| 27 | Underground warning/marking tape, as per plan (625E36011) | FT | 7,225 | $0.48 | $2.00 | $1.36 | $6.00 |
| 28 | Special - maintain existing lighting (625E40000) | LS | 1 | $200.00 | $12,300 | $3,710.00 | $106,000 |
| 29 | Special - replacement of existing lighting unit (625E40010) | EACH | 2 | $50.00 | $250.00 | $1,050.00 | $4,400.00 |
| 30 | Light pole removed (625E75400) | EACH | 58 | $200.00 | $250.00 | $401.00 | $1,600.00 |
| 31 | Light pole removed, as per plan (625E75401) | EACH | 3 | $1,000.00 | $350.00 | $935.00 | $2,200.00 |
| 32 | Light pole removed for storage, as per plan (625E75403) | EACH | 30 | $250.00 | $350.00 | $805.00 | $1,600.00 |
| 33 | Light pole foundation removed (625E75500) | EACH | 88 | $200.00 | $240.00 | $702.00 | $800.00 |
| 34 | Power service removed (625E75510) | EACH | 1 | $3,000.00 | $900.00 | $1,605.00 | $2,400.00 |
| 35 | Arc flash calculations and label, US-224 (625E76000) | EACH | 1 | $1,000.00 | $1,250.00 | $2,000.00 | $4,600.00 |
| 36 | Lighting, misc.: remove underpass lighting (625E98200) | LS | 1 | $5,000.00 | $2,100.00 | $4,010.00 | $12,000 |
| 37 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $75.00 | $105.00 | $120.00 | $85.00 |
| 38 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $750.00 | $900.00 | $1,050.00 | $1,750.00 |
| 39 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $6,590.00 | $19,510 | $7,500.00 |
| 40 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $13,500 | $40,770 | $123,000 |
| 41 | Field office, type B (619E16010) | MNTH | 12 | $1,000.00 | $3,500.00 | $1,500.00 | $2,000.00 |
| 42 | Construction layout stakes and surveying (623E10000) | LS | 1 | $9,000.00 | $3,900.00 | $5,000.00 | $9,250.00 |
| 43 | Mobilization (624E10000) | LS | 1 | $25,000 | $69,178 | $69,900 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 25, 2026. Compiled by Mirage Metrics.