| 1 | Wearing course removed (202E23500) | SY | 6,258 | $12.00 | $8.50 |
| 2 | Walk removed (202E30000) | SF | 1,193 | $8.00 | $9.00 |
| 3 | Curb removed (202E32000) | FT | 81 | $16.50 | $25.00 |
| 4 | Mailbox removed, as per plan (202E53101) | EACH | 1 | $450.00 | $200.00 |
| 5 | Removal misc.: landscaping timber (202E98200) | FT | 22 | $80.00 | $40.00 |
| 6 | Excavation (203E10000) | CY | 14 | $125.00 | $135.00 |
| 7 | Preparing subgrade for shoulder paving, as per plan (209E72051) | MI | 19.82 | $2,500.00 | $2,500.00 |
| 8 | 4" concrete walk (608E10000) | SF | 265 | $12.00 | $21.50 |
| 9 | Curb ramp, as per plan (608E52001) | SF | 990 | $30.00 | $40.00 |
| 10 | Detectable warning (608E53020) | SF | 16 | $75.00 | $60.00 |
| 11 | Curb, type 6 (609E26000) | FT | 132 | $45.00 | $65.00 |
| 12 | Topsoil furnished and placed, as per plan (653E10001) | CY | 11 | $180.00 | $250.00 |
| 13 | Seeding and mulching, class 1 (659E00500) | SY | 94 | $32.00 | $15.00 |
| 14 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 |
| 15 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 7 | $1,500.00 | $2,600.00 |
| 16 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 1 | $3,000.00 | $3,500.00 |
| 17 | Manhole adjusted to grade (611E99654) | EACH | 16 | $1,500.00 | $1,900.00 |
| 18 | Valve box adjusted to grade (638E10800) | EACH | 9 | $1,200.00 | $1,000.00 |
| 19 | Pavement repair (253E02000) | CY | 2,750 | $325.00 | $410.00 |
| 20 | Pavement planing, asphalt concrete, 1.25" (254E01000) | SY | 1,392 | $4.00 | $8.00 |
| 21 | Pavement planing, asphalt concrete, 1.50" (254E01000) | SY | 129,722 | $2.10 | $2.10 |
| 22 | Pavement planing, asphalt concrete, 2.25" (254E01000) | SY | 17,150 | $2.25 | $3.10 |
| 23 | Non-tracking tack coat (407E20000) | GAL | 19,460 | $3.50 | $3.50 |
| 24 | Prime coat, as per plan (408E10001) | GAL | 8,165 | $5.00 | $5.00 |
| 25 | Sawing and sealing asphalt concrete pavement joints (409E30000) | FT | 152 | $30.50 | $32.00 |
| 26 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 5,253 | $250.00 | $260.00 |
| 27 | Asphalt concrete intermediate course, type 1, (448), as per plan (441E50201) | CY | 4,075 | $235.00 | $250.00 |
| 28 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 249 | $475.00 | $475.00 |
| 29 | 2" deep joint sealer, as per plan (516E31011) | FT | 44 | $40.00 | $35.00 |
| 30 | Compacted aggregate, as per plan (617E10101) | CY | 1,128 | $90.00 | $90.00 |
| 31 | RPM (621E00100) | EACH | 757 | $37.00 | $45.00 |
| 32 | Raised pavement marker removed (621E54000) | EACH | 757 | $8.00 | $9.00 |
| 33 | Edge line, 6" (644E00104) | MI | 20.08 | $3,895.00 | $3,895.00 |
| 34 | Center line (644E00300) | MI | 10.46 | $4,515.00 | $4,515.00 |
| 35 | Channelizing line, 8" (644E00400) | FT | 315 | $2.90 | $2.90 |
| 36 | Stop line (644E00500) | FT | 743 | $10.65 | $10.65 |
| 37 | Crosswalk line, 12" (644E00620) | FT | 750 | $4.50 | $4.50 |
| 38 | Railroad symbol marking (644E01000) | EACH | 4 | $850.00 | $850.00 |
| 39 | School symbol marking, 96" (644E01110) | EACH | 2 | $850.00 | $850.00 |
| 40 | Parking lot stall marking (644E01200) | FT | 1,435 | $2.50 | $2.50 |
| 41 | Yield line (644E20800) | FT | 22 | $14.85 | $14.85 |
| 42 | Dynamic envelope crosshatch marking (644E43000) | SF | 899 | $4.00 | $4.00 |
| 43 | Edge line, 6" (646E10010) | MI | 0.18 | $18,650 | $18,650 |
| 44 | Center line (646E10200) | MI | 0.09 | $31,500 | $31,500 |
| 45 | Handicap symbol marking, type B125 (647E20212) | EACH | 1 | $200.00 | $200.00 |
| 46 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $85.00 | $95.00 |
| 47 | Work zone marking sign (614E12460) | EACH | 59 | $92.00 | $92.00 |
| 48 | Asphalt concrete for maintaining traffic (614E13000) | CY | 3 | $510.00 | $650.00 |
| 49 | Work zone center line, class III, 642 paint (614E21550) | MI | 21.06 | $800.00 | $850.00 |
| 50 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 630 | $3.00 | $3.00 |
| 51 | Work zone stop line, class III, 642 paint (614E26610) | FT | 352 | $5.50 | $5.50 |
| 52 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $1,550.00 | $7,500.00 |
| 53 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $16,599 | $25,000 |
| 54 | Maintaining traffic (614E11000) | LS | 1 | $375,000 | $275,000 |
| 55 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $7,500.00 |
| 56 | Mobilization (624E10000) | LS | 1 | $125,000 | $200,000 |