ODOT contract 260293 bid tabulation
CUY-DMS & QWS FY2026 (SIGNALIZATION). Let by Ohio DOT on June 11, 2026, CUY. 3 bids received; low bid $998,118 by Ruhlin Company, -0.2% against the engineer's estimate of $1,000,000.
- Owner
- Ohio DOT
- Letting
- 11 JUN 2026
- Pay items
- 78
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ruhlin Company | $998,118 | Low | 0.0% |
| 2 | Perram Electric Inc | $1,233,133 | +24% | +23% |
| 3 | Miller Cable Company | $1,289,427 | +29% | +29% |
Engineer's estimate: $1,000,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ruhlin Company | 2. Perram Electric Inc | 3. Miller Cable Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $6,350.00 | $2,490.00 | $500.00 |
| 2 | Guardrail removed (202E38000) | FT | 64 | $5.00 | $5.00 | $5.00 |
| 3 | Excavation, as per plan (203E10001) | CY | 215 | $66.00 | $202.00 | $162.00 |
| 4 | Embankment, as per plan (203E20001) | CY | 173 | $44.00 | $162.00 | $108.00 |
| 5 | Subgrade compaction (204E10000) | SY | 510 | $20.00 | $8.00 | $5.00 |
| 6 | Guardrail, type MGS (606E15050) | FT | 75 | $64.00 | $64.00 | $64.00 |
| 7 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $2,520.00 | $2,420.00 | $2,420.00 |
| 8 | Bridge terminal assembly, type 2 (606E35100) | EACH | 1 | $1,265.00 | $1,265.00 | $1,265.00 |
| 9 | Soil analysis test (659E00100) | EACH | 2 | $100.00 | $610.00 | $200.00 |
| 10 | Topsoil (659E00300) | CY | 30 | $95.00 | $155.00 | $105.00 |
| 11 | Seeding and mulching (659E10000) | SY | 272 | $11.00 | $12.00 | $12.00 |
| 12 | Commercial fertilizer (659E20000) | TON | 0.04 | $900.00 | $1,500.00 | $1,500.00 |
| 13 | Lime (659E31000) | ACRE | 0.06 | $100.00 | $1,000.00 | $1,000.00 |
| 14 | Water (659E35000) | MGAL | 1 | $1.00 | $50.00 | $50.00 |
| 15 | Erosion control (832E30000) | EACH | 6,000 | $1.00 | $1.00 | $1.00 |
| 16 | Aggregate base (304E20000) | CY | 115 | $203.00 | $200.00 | $200.00 |
| 17 | No. 6 AWG 600 volt distribution cable (625E22990) | FT | 6,160 | $3.80 | $5.66 | $4.00 |
| 18 | No. 4 AWG 600 volt distribution cable (625E23000) | FT | 7,930 | $4.50 | $6.16 | $5.00 |
| 19 | No. 2 AWG 600 volt distribution cable (625E23100) | FT | 2,560 | $7.00 | $8.28 | $6.00 |
| 21 | Conduit cleaned and cables removed, as per plan (625E25911) | FT | 3,665 | $1.00 | $1.59 | $3.00 |
| 22 | Trench, 30" deep (625E29010) | FT | 523 | $30.00 | $20.25 | $18.00 |
| 23 | Pull box, 725.08, 18" (625E30700) | EACH | 1 | $1,837.00 | $3,475.00 | $1,150.00 |
| 24 | Pull box removed (625E31510) | EACH | 9 | $410.00 | $460.00 | $300.00 |
| 25 | Ground rod (625E32000) | EACH | 7 | $400.00 | $485.00 | $300.00 |
| 26 | Underground warning marking tape (625E36010) | FT | 523 | $2.50 | $1.90 | $3.00 |
| 27 | Pull box cleaned (625E39520) | EACH | 8 | $205.00 | $440.00 | $50.00 |
| 28 | Power service removed (625E75510) | EACH | 2 | $1,100.00 | $410.00 | $500.00 |
| 29 | Arc flash calculations and label, ITS cabinet (625E76000) | EACH | 4 | $1,100.00 | $2,000.00 | $3,625.00 |
| 30 | Arc flash calculations and label, power service (625E76000) | EACH | 2 | $1,100.00 | $2,000.00 | $3,625.00 |
| 31 | Ground mounted support, no. 3 post (630E03100) | FT | 33 | $22.00 | $23.20 | $22.00 |
| 32 | Ground mounted structural beam support, W10X22 (630E07500) | FT | 50.60 | $82.00 | $209.00 | $82.00 |
| 33 | Ground mounted structural beam support, W10X12 (630E07600) | FT | 39.10 | $59.00 | $351.00 | $59.00 |
| 34 | Sign post reflector (630E08600) | EACH | 4 | $45.00 | $225.00 | $45.00 |
| 35 | Breakaway structural beam connection (630E09000) | EACH | 4 | $865.00 | $935.00 | $865.00 |
| 36 | Sign attachment assembly (630E75000) | EACH | 4 | $480.00 | $1,668.00 | $480.00 |
| 37 | Sign, flat sheet (630E80100) | SF | 10.83 | $30.00 | $38.95 | $30.00 |
| 38 | Sign, ground mounted extrusheet (630E80200) | SF | 91 | $33.00 | $43.00 | $33.00 |
| 39 | Ground mounted structural beam support foundation (630E84500) | EACH | 4 | $1,460.00 | $530.00 | $1,460.00 |
| 40 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $20.00 | $205.00 | $20.00 |
| 41 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $20.00 | $205.00 | $20.00 |
| 42 | Removal of ground mounted structural beam support (630E86102) | EACH | 2 | $420.00 | $615.00 | $420.00 |
| 43 | Removal of structure mounted sign and disposal (630E86310) | EACH | 1 | $385.00 | $410.00 | $385.00 |
| 44 | Conduit riser, 2" diameter (632E70400) | EACH | 2 | $1,625.00 | $710.00 | $750.00 |
| 45 | Reuse of traffic control item: electric pullbox (632E90104) | EACH | 5 | $820.00 | $460.00 | $150.00 |
| 46 | Cabinet foundation, as per plan (633E67101) | EACH | 4 | $2,626.00 | $5,175.00 | $3,500.00 |
| 47 | Controller work pad (633E67200) | EACH | 4 | $3,830.00 | $7,810.00 | $3,200.00 |
| 48 | Pruning existing tree, 3 to 8-inch diameter (666E09000) | EACH | 3 | $262.00 | $1,975.00 | $750.00 |
| 50 | Fiber optic cable, 24 fiber (804E15010) | FT | 1,970 | $5.00 | $8.47 | $5.50 |
| 51 | Fiber termination panel, 24 fiber (804E34022) | EACH | 2 | $3,750.00 | $1,890.00 | $2,000.00 |
| 52 | Splice enclosure, in-line (804E37002) | EACH | 2 | $1,234.00 | $2,015.00 | $2,000.00 |
| 53 | ITS pull box with pad and standard lid assembly, 3 (809E01900) | EACH | 3 | $4,334.00 | $6,540.00 | $5,500.00 |
| 54 | 32" ITS pull box with pad and hinged lid assembly, type 2 (809E02002) | EACH | 3 | $5,473.00 | $7,540.00 | $6,000.00 |
| 55 | Tracer wire (809E10000) | FT | 790 | $1.00 | $1.90 | $3.00 |
| 56 | Conduit, 2" diameter, HDPE (809E23900) | FT | 618 | $12.00 | $11.85 | $18.00 |
| 57 | Conduit, 4", multicell, HDPE with 4 - 1" innerducts (809E24500) | FT | 126 | $15.00 | $18.00 | $28.00 |
| 58 | ITS power service, ground mounted, 120/240V, 100 amp (809E51100) | EACH | 1 | $9,500.00 | $8,385.00 | $12,500 |
| 59 | ITS power service, pole mounted, 240/480V, 100 amp (809E56100) | EACH | 1 | $5,500.00 | $8,120.00 | $13,500 |
| 60 | CCTV IP-camera system, fixed-view (809E60060) | EACH | 4 | $5,500.00 | $4,255.00 | $4,300.00 |
| 61 | Dynamic message sign (DMS), full-size walk-in (809E63000) | EACH | 3 | $110,000 | $100,350 | $114,500 |
| 62 | Dynamic message sign (DMS), front-access (809E63010) | EACH | 1 | $76,000 | $59,880 | $76,500 |
| 63 | Ethernet cable, outdoor-rated (809E64550) | FT | 550 | $2.50 | $4.20 | $3.00 |
| 64 | ITS cabinet - DMS (809E65040) | EACH | 4 | $17,455 | $10,190 | $12,500 |
| 65 | Step-down transformer, 3KVA (809E65100) | EACH | 1 | $5,500.00 | $11,255 | $12,500 |
| 66 | Step-down transformer, 7.5KVA (809E65110) | EACH | 1 | $11,600 | $16,855 | $14,500 |
| 67 | ITS device, misc.: maintenance of existing power S (809E65990) | EACH | 2 | $9,350.00 | $10,600 | $6,500.00 |
| 68 | ITS device, misc.: removal of existing DMS (809E65990) | EACH | 3 | $3,048.00 | $2,460.00 | $5,500.00 |
| 69 | ITS device, misc.: removal of existing ITS cabinet (809E65990) | EACH | 3 | $820.00 | $615.00 | $600.00 |
| 70 | Maintaining ITS during construction (809E70000) | LS | 1 | $3,990.00 | $2,140.00 | $32,000 |
| 71 | As-built construction plans (809E70050) | LS | 1 | $795.00 | $6,850.00 | $6,120.00 |
| 72 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 160 | $125.00 | $100.00 | $85.00 |
| 73 | Barrier reflector, type 1,one way (614E13310) | EACH | 4 | $8.00 | $20.00 | $15.00 |
| 74 | Barrier reflector, type 2, one way (614E13312) | EACH | 9 | $9.00 | $20.00 | $16.00 |
| 75 | Water (616E10000) | MGAL | 50 | $5.00 | $1.00 | $50.00 |
| 76 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,697.00 | $21,997 | $6,500.00 |
| 77 | Maintaining traffic (614E11000) | LS | 1 | $11,748 | $108,770 | $140,000 |
| 78 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,258.00 | $14,260 | $32,000 |
| 79 | Mobilization (624E10000) | LS | 1 | $49,000 | $60,000 | $85,000 |
| 100 | 32" ITS pull box with pad and standard lid assembly, type 2 (809E02000) | EACH | 6 | $3,588.00 | $7,503.00 | $6,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 11, 2026. Compiled by Mirage Metrics.