ODOT contract 260294 bid tabulation
D05-FY2027 Bridge Rehab East (BRIDGE REPAIR). Let by Ohio DOT on June 11, 2026, District 5. 5 bids received; low bid $824,858 by Twin Rivers Construction Co, -28% against the engineer's estimate of $1,151,000.
- Owner
- Ohio DOT
- Letting
- 11 JUN 2026
- Pay items
- 46
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Twin Rivers Construction Co | $824,858 | Low | -28% |
| 2 | Aad Contracting Inc | $874,700 | +6.0% | -24% |
| 3 | BCC Ohio Inc | $878,204 | +6.0% | -24% |
| 4 | Catts Construction Inc | $982,749 | +19% | -15% |
| 5 | Legend Painting Inc | $1,998,501 | +142% | +74% |
Engineer's estimate: $1,151,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Twin Rivers Construction Co | 2. Aad Contracting Inc | 3. BCC Ohio Inc | 4. Catts Construction Inc | 5. Legend Painting Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $15,000 | $10,000 | $14,448 | $35,029 | $2,000.00 |
| 2 | Erosion control (832E30000) | EACH | 20,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 3 | Edge line, 6", type 1 (642E00104) | MI | 0.72 | $6,925.00 | $4,000.00 | $6,714.75 | $7,875.00 | $6,395.00 |
| 4 | Center line, type 1 (642E00300) | MI | 0.44 | $11,250 | $4,000.00 | $8,951.25 | $10,390 | $8,525.00 |
| 5 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 300 | $90.00 | $30.00 | $75.00 | $110.00 | $150.00 |
| 6 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $300.00 | $150.00 | $966.00 | $150.00 | $750.00 |
| 7 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,000.00 | $300.00 | $1,100.00 | $1,400.00 | $1,240.98 |
| 8 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.44 | $10,695 | $5,000.00 | $10,695 | $13,035 | $22,750 |
| 9 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.72 | $6,625.00 | $5,000.00 | $6,625.00 | $8,100.00 | $18,990 |
| 10 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 1,038 | $15.50 | $15.75 | $17.36 | $13.55 | $26.46 |
| 11 | Patching concrete bridge deck - type B (519E12300) | SY | 21 | $700.00 | $900.00 | $883.50 | $800.00 | $2,474.00 |
| 12 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 748 | $15.50 | $15.75 | $17.36 | $13.55 | $26.46 |
| 13 | Patching concrete structure, as per plan (519E11101) | SF | 135 | $200.00 | $250.00 | $147.00 | $225.00 | $375.00 |
| 14 | Patching concrete structure, as per plan (519E11101) | SF | 29 | $200.00 | $180.00 | $262.20 | $225.00 | $375.00 |
| 15 | Patching concrete bridge deck - type B (519E12300) | SY | 75 | $685.00 | $900.00 | $819.00 | $800.00 | $2,380.00 |
| 16 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 687 | $15.50 | $15.75 | $17.36 | $13.55 | $26.46 |
| 17 | Patching concrete structure, as per plan (519E11101) | SF | 215 | $200.00 | $250.00 | $147.00 | $225.00 | $375.00 |
| 18 | Patching concrete bridge deck - type B (519E12300) | SY | 69 | $685.00 | $900.00 | $819.00 | $975.00 | $2,380.00 |
| 19 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 506 | $15.50 | $15.75 | $17.36 | $13.55 | $26.46 |
| 21 | Patching concrete bridge deck - type B (519E12300) | SY | 25 | $700.00 | $900.00 | $937.68 | $975.00 | $2,380.00 |
| 22 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 134 | $16.00 | $15.75 | $22.00 | $13.55 | $26.46 |
| 23 | Patching concrete bridge deck - type B (519E12300) | SY | 3 | $1,000.00 | $900.00 | $883.50 | $975.00 | $2,380.00 |
| 24 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 105 | $16.00 | $15.75 | $22.00 | $13.55 | $26.46 |
| 26 | Patching concrete bridge deck - type B (519E12300) | SY | 5 | $1,000.00 | $900.00 | $883.50 | $975.00 | $2,380.00 |
| 28 | Patching concrete structure, as per plan (519E11101) | SF | 4 | $550.00 | $1,000.00 | $451.20 | $500.00 | $1,500.00 |
| 31 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 1,039 | $15.50 | $15.75 | $17.36 | $13.55 | $26.46 |
| 32 | Patching concrete bridge deck - type B (519E12300) | SY | 104 | $685.00 | $900.00 | $819.00 | $975.00 | $2,380.00 |
| 33 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 578 | $16.00 | $15.75 | $17.36 | $13.55 | $26.46 |
| 34 | 2" deep joint sealer, as per plan (516E31011) | FT | 75 | $25.00 | $25.00 | $35.24 | $25.00 | $750.00 |
| 35 | Patching concrete bridge deck - type B (519E12300) | SY | 58 | $685.00 | $900.00 | $819.00 | $800.00 | $2,380.00 |
| 36 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 1,688 | $15.50 | $15.75 | $17.36 | $13.55 | $26.46 |
| 37 | Patching concrete bridge deck - type B (519E12300) | SY | 34 | $695.00 | $900.00 | $883.50 | $975.00 | $2,380.00 |
| 38 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 348 | $15.60 | $15.75 | $22.00 | $13.55 | $22.00 |
| 39 | 2" deep joint sealer, as per plan (516E31011) | FT | 80 | $25.00 | $25.00 | $35.24 | $25.00 | $750.00 |
| 40 | Patching concrete bridge deck - type B (519E12300) | SY | 17 | $700.00 | $900.00 | $883.50 | $975.00 | $2,380.00 |
| 41 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 258 | $16.00 | $15.75 | $22.00 | $13.55 | $26.46 |
| 42 | 2" deep joint sealer, as per plan (516E31011) | FT | 68 | $25.00 | $25.00 | $35.24 | $25.00 | $750.00 |
| 43 | Patching concrete bridge deck - type B (519E12300) | SY | 26 | $700.00 | $900.00 | $883.50 | $975.00 | $2,380.00 |
| 44 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 836 | $15.75 | $15.75 | $17.36 | $13.55 | $26.46 |
| 45 | Removal misc.: polymer modified asphalt expansion (202E98000) | LS | 1 | $3,000.00 | $2,300.00 | $3,262.50 | $5,000.00 | $45,000 |
| 46 | Sealing concrete bridge decks with HMWM resin, as per plan (512E10301) | SY | 401 | $15.60 | $15.75 | $22.00 | $13.55 | $26.46 |
| 47 | Patching concrete bridge deck - type B (519E12300) | SY | 20 | $700.00 | $900.00 | $883.50 | $975.00 | $2,380.00 |
| 48 | Polymer modified asphalt expansion joint system (846E00110) | CF | 23 | $927.70 | $500.00 | $592.50 | $550.00 | $750.00 |
| 49 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $17,500 | $4,000.00 | $10,595 | $10,127 | $30,000 |
| 50 | Maintaining traffic (614E11000) | LS | 1 | $100,000 | $137,000 | $80,558 | $102,000 | $100,000 |
| 51 | Mobilization (624E10000) | LS | 1 | $55,000 | $20,000 | $66,994 | $100,000 | $60,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 11, 2026. Compiled by Mirage Metrics.