ODOT contract 260450 bid tabulation
SHE-SR 119-03.60 (BRIDGE REPAIR). Let by Ohio DOT on October 1, 2026, SHE. 4 bids received; low bid $515,000 by Brumbaugh Construction Inc, -10% against the engineer's estimate of $575,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 53
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Brumbaugh Construction Inc | $515,000 | Low | -10% |
| 2 | BCC Ohio Inc | $533,901 | +4.0% | -7.0% |
| 3 | Eagle Bridge Co | $541,982 | +5.0% | -6.0% |
| 4 | Complete General Construction Company | $625,400 | +21% | +9.0% |
Engineer's estimate: $575,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Brumbaugh Construction Inc | 2. BCC Ohio Inc | 3. Eagle Bridge Co | 4. Complete General Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,000.00 | $1,032.00 | $250.00 | $1,500.00 |
| 2 | Pavement removed (202E23000) | SY | 200 | $12.00 | $10.53 | $25.00 | $17.00 |
| 3 | Wearing course removed (202E23500) | SY | 1,160 | $10.00 | $6.70 | $12.00 | $10.00 |
| 4 | Guardrail removed, as per plan (202E38001) | FT | 625 | $5.00 | $2.52 | $4.00 | $2.40 |
| 5 | Removal misc.: removal of bridge ID sign and reere (202E98100) | EACH | 1 | $250.00 | $127.93 | $175.00 | $295.00 |
| 6 | Subgrade compaction (204E10000) | SY | 216 | $1.50 | $2.20 | $10.00 | $4.50 |
| 7 | Linear grading (209E60200) | STA | 8 | $225.00 | $193.50 | $150.00 | $1,200.00 |
| 8 | Guardrail, type MGS (606E15050) | FT | 200 | $23.00 | $24.36 | $23.00 | $23.20 |
| 9 | Anchor assembly, MGS type E (606E26150) | EACH | 4 | $2,700.00 | $2,667.00 | $2,600.00 | $2,540.00 |
| 10 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 4 | $2,400.00 | $2,703.75 | $2,750.00 | $2,575.00 |
| 11 | Seeding and mulching (659E10000) | SY | 678 | $5.00 | $3.18 | $5.00 | $4.50 |
| 12 | Repair seeding and mulching (659E14000) | SY | 34 | $1.00 | $2.63 | $2.00 | $2.50 |
| 13 | Commercial fertilizer (659E20000) | TON | 0.09 | $900.00 | $1,050.00 | $1,250.00 | $1,000.00 |
| 14 | Water (659E35000) | MGAL | 4 | $5.00 | $1.05 | $1.00 | $1.00 |
| 15 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 34 | $450.00 | $420.00 | $400.00 | $500.00 |
| 17 | Aggregate base (304E20000) | CY | 32 | $75.00 | $183.30 | $200.00 | $140.00 |
| 18 | Tack coat (407E10000) | GAL | 149 | $8.00 | $2.57 | $2.45 | $5.00 |
| 19 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 65 | $490.00 | $446.25 | $425.00 | $475.00 |
| 20 | Compacted aggregate (617E10100) | CY | 30 | $80.00 | $157.50 | $200.00 | $145.00 |
| 21 | Raised pavement marker removed (621E54000) | EACH | 5 | $50.00 | $20.64 | $35.00 | $44.00 |
| 22 | Barrier reflector, type 2, (BI-directional) (626E00110) | EACH | 8 | $15.00 | $13.48 | $12.50 | $12.50 |
| 23 | Sign, flat sheet, as per plan (630E80101) | SF | 1 | $100.00 | $131.75 | $75.00 | $75.00 |
| 24 | Edge line, 6" (646E10010) | MI | 0.18 | $25,000 | $15,540 | $14,800 | $14,800 |
| 25 | Center line (646E10200) | MI | 0.09 | $15,000 | $15,540 | $14,800 | $14,800 |
| 26 | Detour signing (614E12420) | LS | 1 | $7,500.00 | $7,560.00 | $10,000 | $9,000.00 |
| 27 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $30,000 | $37,786 | $45,000 | $45,000 |
| 28 | Wearing course removed (202E23500) | SY | 265 | $17.00 | $9.26 | $12.00 | $20.00 |
| 29 | Bridge railing removed (202E38500) | FT | 125 | $25.00 | $6.72 | $15.00 | $7.00 |
| 30 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $15,000 | $24,952 | $7,500.00 | $10,000 |
| 31 | Unclassified excavation (503E21300) | LS | 1 | $7,500.00 | $10,320 | $8,000.00 | $16,000 |
| 32 | Special - pile encasement (507E71200) | FT | 140 | $325.00 | $319.26 | $275.00 | $295.00 |
| 33 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $6.00 | $2.75 | $1.50 | $4.00 |
| 34 | Uncoated steel reinforcement (509E25000) | LB | 4,367 | $2.00 | $2.08 | $2.25 | $2.00 |
| 35 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 112 | $18.00 | $29.88 | $45.00 | $19.00 |
| 36 | Class QC2 concrete, superstructure (511E34410) | CY | 20 | $2,500.00 | $2,096.06 | $1,750.00 | $3,900.00 |
| 37 | 1/2" preformed expansion joint filler (516E13200) | SF | 40 | $10.00 | $5.58 | $12.00 | $12.00 |
| 38 | 2" deep joint sealer, as per plan (516E31011) | FT | 83 | $20.00 | $29.12 | $25.00 | $28.00 |
| 39 | Railing (three steel tube bridge railing) (517E70100) | FT | 128 | $525.00 | $506.63 | $483.00 | $483.00 |
| 40 | Special - steel drip strip (518E22300) | FT | 144 | $15.00 | $20.91 | $18.00 | $23.00 |
| 41 | Patching concrete structure, as per plan (519E11101) | SF | 12 | $400.00 | $348.00 | $300.00 | $300.00 |
| 42 | Special - structures -abutment refacing with galva (530E00600) | SF | 186 | $130.00 | $170.53 | $300.00 | $200.00 |
| 43 | Structure grounding system (625E33000) | EACH | 1 | $9,000.00 | $11,070 | $8,500.00 | $20,000 |
| 44 | Galvanic anode protection, as per plan (844E20001) | EACH | 112 | $50.00 | $48.31 | $40.00 | $80.00 |
| 45 | Superplasticized dense concrete overlay using hydrodemolition (848E10200) | SY | 266 | $125.00 | $128.63 | $160.00 | $150.00 |
| 46 | Surface preparation using hydrodemolition, as per plan (848E20001) | SY | 227 | $150.00 | $144.95 | $155.00 | $225.00 |
| 47 | Superplasticized dense concrete overlay (variable thickness), material only (848E30200) | CY | 10 | $400.00 | $637.50 | $420.00 | $385.00 |
| 48 | Hand chipping (848E50000) | SY | 10 | $1,000.00 | $258.00 | $125.00 | $90.00 |
| 49 | Test slab (848E50100) | LS | 1 | $2,500.00 | $4,083.00 | $1,250.00 | $1,200.00 |
| 50 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,000.00 | $6,991.38 | $7,500.00 | $6,000.00 |
| 51 | Maintaining traffic (614E11000) | LS | 1 | $1,500.00 | $2,554.20 | $2,000.00 | $8,000.00 |
| 52 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,000.00 | $3,915.00 | $1,500.00 | $6,000.00 |
| 53 | Mobilization (624E10000) | LS | 1 | $14,734 | $27,041 | $25,000 | $30,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.