ODOT contract 260272 bid tabulation
POR-US 224/SR 303-08.29/19.51 (CULVERT REPLACEMENT). Let by Ohio DOT on May 21, 2026, POR. 3 bids received; low bid $707,216 by BCC Ohio Inc, -5.1% against the engineer's estimate of $745,000.
- Owner
- Ohio DOT
- Letting
- 21 MAY 2026
- Pay items
- 70
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BCC Ohio Inc | $707,216 | Low | -5.0% |
| 2 | Shelly & Sands Inc | $796,012 | +13% | +7.0% |
| 3 | Eclipse Co LLC | $804,361 | +14% | +8.0% |
Engineer's estimate: $745,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. BCC Ohio Inc | 2. Shelly & Sands Inc | 3. Eclipse Co LLC |
|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 205 | $9.62 | $42.00 | $46.15 |
| 2 | Guardrail removed (202E38000) | FT | 285 | $2.10 | $2.00 | $2.00 |
| 3 | Fence removed (202E75000) | FT | 37 | $6.45 | $7.00 | $7.00 |
| 4 | Removal misc.: inspection well (202E98100) | EACH | 1 | $1,141.50 | $500.00 | $693.03 |
| 5 | Removal misc.: conduit (202E98200) | FT | 10 | $25.80 | $45.00 | $113.51 |
| 6 | Excavation (203E10000) | CY | 190 | $25.80 | $38.00 | $55.32 |
| 7 | Embankment (203E20000) | CY | 361 | $26.23 | $45.00 | $77.07 |
| 8 | Embankment, as per plan (203E20001) | CY | 3 | $207.00 | $150.00 | $308.88 |
| 9 | Subgrade compaction (204E10000) | SY | 172 | $2.58 | $18.00 | $8.35 |
| 10 | Proof rolling (204E45000) | HR | 2 | $536.88 | $500.00 | $322.74 |
| 11 | Guardrail, type MGS (606E15050) | FT | 125 | $26.67 | $26.00 | $25.40 |
| 12 | Guardrail, type MGS with long posts (606E15100) | FT | 100 | $33.81 | $33.00 | $32.20 |
| 13 | Guardrail, type MGS, 25' long-span (606E17350) | FT | 25 | $31.29 | $30.00 | $29.80 |
| 14 | Anchor assembly, type E (606E26100) | EACH | 1 | $3,066.00 | $3,000.00 | $2,920.00 |
| 15 | Fence rebuilt (607E23100) | FT | 37 | $66.15 | $63.00 | $63.00 |
| 16 | Special - as-built construction plans (690E91000) | LS | 1 | $2,940.00 | $5,000.00 | $7,500.00 |
| 17 | Special - survey control verification (690E98400) | LS | 1 | $2,730.00 | $4,500.00 | $7,500.00 |
| 18 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 2 | $143.25 | $270.00 | $682.99 |
| 19 | Dumped rock fill, type B (601E26000) | CY | 200 | $179.10 | $170.00 | $179.49 |
| 20 | Rock channel protection, type C with filter (601E32200) | CY | 1 | $453.00 | $565.00 | $925.68 |
| 21 | Soil analysis test (659E00100) | EACH | 4 | $137.25 | $150.00 | $60.00 |
| 22 | Topsoil (659E00300) | CY | 101 | $104.74 | $125.00 | $97.92 |
| 23 | Seeding and mulching (659E10000) | SY | 900 | $3.18 | $5.25 | $3.00 |
| 24 | Commercial fertilizer (659E20000) | TON | 0.13 | $1,308.46 | $1,250.00 | $850.00 |
| 25 | Lime (659E31000) | ACRE | 0.19 | $42.00 | $40.00 | $2.00 |
| 26 | Water (659E35000) | MGAL | 4.90 | $0.99 | $1.00 | $0.50 |
| 27 | Erosion control (832E30000) | EACH | 6,000 | $1.00 | $1.00 | $1.00 |
| 28 | 6" unclassified pipe underdrains (605E13300) | FT | 20 | $47.10 | $35.00 | $20.27 |
| 29 | Aggregate drains (605E31100) | FT | 20 | $22.50 | $30.00 | $122.61 |
| 30 | 6" conduit, type F (611E01500) | FT | 20 | $51.98 | $30.00 | $126.42 |
| 31 | 12" conduit, type B (611E04400) | FT | 10 | $99.30 | $140.00 | $290.65 |
| 32 | 12" conduit, type E (611E05100) | FT | 10 | $99.30 | $140.00 | $302.21 |
| 33 | 12" conduit, type F (611E05200) | FT | 10 | $99.30 | $140.00 | $302.21 |
| 34 | Conduit, misc.: type C for drainage discharge cont (611E97400) | FT | 10 | $155.10 | $50.00 | $99.55 |
| 35 | Conduit, misc.: type E for drainage discharge cont (611E97400) | FT | 10 | $155.10 | $50.00 | $99.55 |
| 36 | Conduit, misc.: type F for drainage discharge cont (611E97400) | FT | 10 | $155.10 | $50.00 | $99.55 |
| 37 | Precast reinforced concrete outlet (611E99710) | EACH | 1 | $429.00 | $590.00 | $4,203.82 |
| 38 | Inspection well (611E99720) | EACH | 1 | $1,357.50 | $1,740.00 | $3,119.77 |
| 39 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 56 | $411.60 | $448.00 | $810.00 |
| 40 | Aggregate base (304E20000) | CY | 28 | $150.75 | $135.00 | $161.96 |
| 41 | Non-tracking tack coat (407E20000) | GAL | 46 | $3.26 | $3.05 | $5.00 |
| 42 | Prime coat (408E10000) | GAL | 5 | $52.50 | $3.50 | $50.00 |
| 43 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 19 | $862.05 | $652.00 | $810.00 |
| 44 | Compacted aggregate (617E10100) | CY | 15 | $150.75 | $498.00 | $200.00 |
| 45 | RPM (621E00100) | EACH | 2 | $997.50 | $965.00 | $1,375.00 |
| 46 | Raised pavement marker removed (621E54000) | EACH | 2 | $20.64 | $50.00 | $165.61 |
| 47 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $52.50 | $50.00 | $29.00 |
| 48 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $52.50 | $65.00 | $53.00 |
| 49 | Edge line, 6" (646E10010) | MI | 0.04 | $68,250 | $70,000 | $53,875 |
| 50 | Center line (646E10200) | MI | 0.02 | $78,750 | $81,000 | $71,995 |
| 51 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 30 | $89.25 | $107.00 | $100.00 |
| 52 | Detour signing (614E12420) | LS | 1 | $8,610.00 | $10,000 | $9,267.02 |
| 53 | Detour signing (614E12420) | LS | 1 | $6,367.20 | $8,000.00 | $7,064.50 |
| 54 | Work zone marking sign (614E12460) | EACH | 4 | $89.41 | $92.00 | $85.15 |
| 55 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $938.31 | $960.00 | $893.71 |
| 56 | Work zone channelizing line, class I, 8" (614E23000) | FT | 100 | $15.70 | $17.00 | $14.95 |
| 57 | Structure removed (202E11000) | LS | 1 | $10,995 | $20,000 | $16,238 |
| 58 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $16,002 | $33,000 | $60,398 |
| 59 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 100 | $45.24 | $59.00 | $17.31 |
| 60 | Type 2 waterproofing (512E33000) | SY | 490 | $30.23 | $25.00 | $42.58 |
| 61 | Type 3 waterproofing (512E33010) | SY | 207 | $51.60 | $49.00 | $72.49 |
| 62 | Riprap, type D (601E11000) | SY | 40 | $407.42 | $550.00 | $179.67 |
| 63 | Rock channel protection, type B with filter (601E32100) | CY | 74 | $182.40 | $190.00 | $138.48 |
| 64 | Concrete masonry, as per plan (602E20001) | CY | 42 | $1,680.55 | $2,300.00 | $756.25 |
| 65 | 12' X 12' conduit, type A, 706.05 (611E96220) | FT | 116 | $2,423.05 | $2,400.00 | $2,226.62 |
| 66 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,731.00 | $5,479.00 | $9,847.90 |
| 67 | Maintaining traffic (614E11000) | LS | 1 | $19,391 | $3,500.00 | $8,432.46 |
| 68 | Field office, type B (619E16010) | MNTH | 6 | $3,196.00 | $3,500.00 | $1,076.79 |
| 69 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,440.00 | $17,467 | $6,078.19 |
| 70 | Mobilization (624E10000) | LS | 1 | $29,068 | $40,000 | $85,269 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 21, 2026. Compiled by Mirage Metrics.