ODOT contract 260103 bid tabulation
D01-BM FY26 (BRIDGE REPAIR). Let by Ohio DOT on February 19, 2026, District 1. 4 bids received; low bid $815,072 by BCC Ohio Inc, -9.4% against the engineer's estimate of $900,000.
- Owner
- Ohio DOT
- Letting
- 19 FEB 2026
- Pay items
- 57
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BCC Ohio Inc | $815,072 | Low | -9.0% |
| 2 | Complete General Construction Company | $872,698 | +7.0% | -3.0% |
| 3 | Ohio Concrete Maintenance LLC | $873,898 | +7.0% | -3.0% |
| 4 | Eagle Bridge Co | $1,032,446 | +27% | +15% |
Engineer's estimate: $900,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. BCC Ohio Inc | 2. Complete General Construction Company | 3. Ohio Concrete Maintenance LLC | 4. Eagle Bridge Co |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,580.00 | $5,000.00 | $5,000.00 | $10,000 |
| 2 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 3 | Pavement removed (202E23000) | SY | 85 | $14.57 | $40.00 | $100.00 | $45.00 |
| 4 | Subgrade compaction (204E10000) | SY | 85 | $5.16 | $6.00 | $12.00 | $20.00 |
| 5 | Partial depth pavement repair (441) (251E01000) | SY | 889 | $63.00 | $60.00 | $70.00 | $57.00 |
| 6 | Pavement repair (253E02000) | CY | 15 | $892.50 | $850.00 | $925.00 | $435.00 |
| 7 | 15" non-reinforced concrete pavement, class QC 1P (452E18010) | SY | 85 | $216.45 | $250.00 | $280.00 | $300.00 |
| 8 | Pavement planing, asphalt concrete, 1 1/2" (254E01000) | SY | 1,907 | $7.35 | $7.00 | $7.75 | $6.75 |
| 9 | Non-tracking tack coat (407E20000) | GAL | 153 | $1.05 | $1.00 | $1.25 | $3.00 |
| 10 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 79 | $472.50 | $450.00 | $500.00 | $445.00 |
| 11 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 15 | $88.20 | $95.00 | $120.00 | $140.00 |
| 12 | Increased barrier delineation (614E11630) | FT | 200 | $1.85 | $2.00 | $3.00 | $1.75 |
| 13 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 2 | $2,184.00 | $2,500.00 | $3,750.00 | $2,281.00 |
| 14 | Barrier reflector, type 1 (one way) (614E13310) | EACH | 22 | $13.37 | $13.00 | $12.00 | $12.00 |
| 15 | Object marker, one way (614E13350) | EACH | 22 | $21.93 | $21.00 | $23.00 | $20.00 |
| 16 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $1,006.58 | $960.00 | $1,200.00 | $1,000.00 |
| 17 | Work zone center line, class II (614E21400) | MI | 0.80 | $2,730.00 | $2,600.00 | $1,400.00 | $2,600.00 |
| 18 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 2.25 | $10,660 | $10,153 | $13,500 | $10,000 |
| 19 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 2,860 | $1.03 | $1.00 | $5.00 | $1.50 |
| 20 | Water (616E10000) | MGAL | 6 | $2.48 | $115.00 | $20.00 | $20.00 |
| 21 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 5,720 | $1.21 | $1.00 | $1.75 | $2.25 |
| 22 | Portable barrier, unanchored (622E41100) | FT | 1,056 | $30.07 | $29.00 | $30.00 | $25.00 |
| 23 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 4 | $654.15 | $725.00 | $900.00 | $850.00 |
| 24 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 43 | $43.56 | $75.00 | $75.00 | $75.00 |
| 25 | Patching concrete structure, as per plan (519E11101) | SF | 180 | $55.90 | $250.00 | $125.00 | $195.00 |
| 26 | Rock channel protection, type B without filter (601E34100) | CY | 65 | $194.48 | $185.00 | $175.00 | $350.00 |
| 27 | Approach slab removed (202E22900) | SY | 133 | $95.04 | $80.00 | $60.00 | $80.00 |
| 28 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 947 | $1.83 | $2.69 | $2.00 | $2.50 |
| 29 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 190 | $29.88 | $20.00 | $25.00 | $40.00 |
| 30 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 20 | $42.66 | $100.00 | $150.00 | $100.00 |
| 31 | 1/2" preformed expansion joint filler (516E13200) | SF | 39 | $7.41 | $13.00 | $20.00 | $7.00 |
| 32 | 2" deep joint sealer (516E31010) | FT | 112 | $24.99 | $25.00 | $10.00 | $15.00 |
| 33 | Special - steel drip strip (518E22300) | FT | 150 | $18.76 | $25.00 | $27.00 | $20.00 |
| 34 | Patching concrete structure, as per plan (519E11101) | SF | 26 | $155.13 | $300.00 | $150.00 | $275.00 |
| 35 | Special - patching concrete structure: abutment BA (519E11900) | CY | 5 | $4,757.69 | $5,900.00 | $4,000.00 | $9,000.00 |
| 36 | Reinforced concrete approach slabs (T=15") (526E25000) | SY | 133 | $452.39 | $450.00 | $375.00 | $500.00 |
| 37 | Superplasticized dense concrete overlay using hydrodemolition, as per plan (848E10201) | SY | 267 | $177.50 | $160.00 | $179.00 | $300.00 |
| 38 | Surface preparation using hydrodemolition (848E20000) | SY | 267 | $228.03 | $190.00 | $288.00 | $250.00 |
| 39 | Superplasticized dense concrete overlay (variable thickness), material only, as per plan (848E30201) | CY | 5 | $525.00 | $250.00 | $400.00 | $275.00 |
| 40 | Hand chipping (848E50000) | SY | 80 | $193.01 | $95.00 | $130.00 | $90.00 |
| 41 | Test slab (848E50100) | LS | 1 | $3,537.00 | $1,800.00 | $600.00 | $500.00 |
| 42 | Full-depth repair (848E50200) | CY | 5 | $783.00 | $950.00 | $500.00 | $500.00 |
| 43 | Existing concrete overlay removed (T = 2") (848E50320) | SY | 267 | $49.82 | $35.00 | $42.00 | $55.00 |
| 44 | Special - pile encasement (507E71200) | FT | 176 | $275.94 | $300.00 | $250.00 | $325.00 |
| 45 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 31 | $42.66 | $75.00 | $75.00 | $75.00 |
| 46 | Patching concrete structure, as per plan (519E11101) | SF | 42 | $96.03 | $300.00 | $150.00 | $225.00 |
| 47 | Special - pile encasement (507E71200) | FT | 176 | $275.94 | $300.00 | $250.00 | $325.00 |
| 48 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 38 | $42.66 | $75.00 | $75.00 | $75.00 |
| 49 | Patching concrete structure, as per plan (519E11101) | SF | 14 | $155.13 | $350.00 | $200.00 | $425.00 |
| 50 | Patching concrete structures with trowelable mortar (843E50000) | SF | 52 | $155.13 | $200.00 | $150.00 | $230.00 |
| 51 | Special - pile encasement (507E71200) | FT | 192 | $275.15 | $300.00 | $275.00 | $315.00 |
| 52 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 38 | $42.66 | $75.00 | $75.00 | $75.00 |
| 53 | Concrete repair by epoxy injection (512E10600) | FT | 20 | $100.35 | $300.00 | $100.00 | $160.00 |
| 54 | Patching concrete structure, as per plan (519E11101) | SF | 25 | $155.13 | $300.00 | $150.00 | $300.00 |
| 55 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,062 | $8,000.00 | $15,000 | $20,000 |
| 56 | Maintaining traffic (614E11000) | LS | 1 | $63,545 | $85,000 | $40,000 | $130,000 |
| 57 | Mobilization (624E10000) | LS | 1 | $54,476 | $40,000 | $85,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 19, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way