ODOT contract 260363 bid tabulation

HAS-Bridge St Bridge Replacement (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on August 13, 2026, HAS. 5 bids received; low bid $2,087,391 by J D Williamson Construction Co Inc, -2.0% against the engineer's estimate of $2,130,000.

Owner
Ohio DOT
Letting
13 AUG 2026
Pay items
101
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1J D Williamson Construction Co Inc$2,087,391Low-2.0%
2Alan Stone Co Inc$2,379,357+14%+12%
3Shelly & Sands Inc$2,388,859+14%+12%
4Sunesis Construction Co$2,394,393+15%+12%
5Stanley Miller Construction Company$2,408,305+15%+13%
ODOT contract 260363: bids by rank

Engineer's estimate: $2,130,000.

Bid tabulation

LinePay itemUnitQuantity1. J D Williamson Construction Co Inc2. Alan Stone Co Inc3. Shelly & Sands Inc4. Sunesis Construction Co5. Stanley Miller Construction Company
1Clearing and grubbing (201E11000)LS1$16,000$55,000$30,000$23,511$14,334
2Pavement removed (202E23000)SY416$11.00$35.00$9.00$12.87$110.00
3Walk removed (202E30000)SF202$4.00$20.00$4.00$3.63$7.00
4Curb removed (202E32000)FT87$9.00$20.00$15.00$8.42$10.00
5Pipe removed, 24" and under (202E35100)FT44$12.00$35.00$25.00$32.86$134.00
6Catch basin removed (202E58100)EACH1$420.00$500.00$330.00$732.87$600.00
7Excavation (203E10000)CY77$25.00$65.00$30.00$30.84$51.00
8Embankment (203E20000)CY89$20.00$45.00$28.00$38.68$125.00
9Subgrade compaction (204E10000)SY555$5.00$10.00$7.00$6.81$2.00
10Proof rolling (204E45000)HR1$350.00$270.00$292.00$385.40$150.00
11Guardrail, type MGS (606E15050)FT25$31.50$35.00$30.00$46.72$32.25
12Anchor assembly, MGS type B (606E26050)EACH1$2,830.00$3,100.00$2,700.00$2,688.61$2,758.00
13Anchor assembly, MGS type T (606E26550)EACH1$1,465.00$1,600.00$1,400.00$1,530.59$1,556.00
14MGS bridge terminal assembly, type TST-2 (606E34600)EACH1$2,830.00$3,100.00$2,700.00$2,990.70$2,861.00
15MGS bridge terminal assembly, type TST-2, as per plan (606E34601)EACH1$2,880.00$3,200.00$2,750.00$3,171.96$2,862.00
16MGS bridge terminal assembly, type 1 (606E35002)EACH1$2,600.00$2,900.00$2,500.00$2,738.96$2,778.00
174" concrete walk (608E10000)SF174$15.00$40.00$35.00$27.21$20.00
18Monument assembly, type C (623E38500)EACH2$2,050.00$2,500.00$2,750.00$1,384.59$1,800.00
19Reference monument, type A (623E40500)EACH1$1,050.00$3,600.00$1,330.00$1,384.58$1,800.00
20Right-of-way monument, type B (623E40520)EACH17$170.00$110.00$150.00$186.29$188.00
21Soil analysis test (659E00100)EACH2$150.00$150.00$150.00$135.94$200.00
22Topsoil (659E00300)CY64$80.00$80.00$86.00$39.06$151.00
23Seeding and mulching (659E10000)SY581$2.00$10.00$6.00$8.76$7.00
24Repair seeding and mulching (659E14000)SY29$1.00$10.00$6.00$2.52$10.00
25Inter-seeding (659E15000)SY29$1.00$10.00$6.00$0.10$10.00
26Commercial fertilizer (659E20000)TON0.13$450.00$580.00$1,250.00$1,067.38$600.00
27Lime (659E31000)ACRE0.12$30.00$170.00$150.00$50.33$500.00
28Water (659E35000)MGAL5$5.00$1.00$1.00$1.01$1.00
29Erosion control (832E30000)EACH10,000$1.00$1.00$1.00$1.00$1.00
30Concrete masonry (602E20000)CY0.33$3,700.00$3,200.00$2,750.00$4,880.61$2,694.00
3118" conduit, type C (611E07600)FT30$110.00$110.00$166.00$272.31$175.00
32Manhole adjusted to grade (611E99654)EACH2$1,200.00$1,200.00$1,425.00$503.63$1,056.00
33Pavement planing, asphalt concrete, 1.25" depth (254E01000)SY202$42.00$60.00$19.50$40.28$82.00
34Asphalt concrete base, PG64-22, (449) (301E56000)CY33$835.00$530.00$575.00$805.58$1,000.00
35Aggregate base (304E20000)CY96$125.00$160.00$136.00$157.25$170.00
36Non-tracking tack coat (407E20000)GAL53$5.00$5.00$3.50$4.53$4.50
37Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY17$890.00$850.00$625.00$855.92$1,145.00
38Asphalt concrete intermediate course, type 1, (449) (441E70200)CY14$865.00$970.00$600.00$830.75$1,457.00
39Curb, type 6 (609E26000)FT20$38.00$440.00$118.00$186.73$50.00
408" water main polyvinyl chloride pipe and fittings, AWWA C900, DR18, as per plan (638E01721)FT67$400.00$240.00$462.00$421.00$158.00
41Valve box adjusted to grade (638E10800)EACH3$455.00$420.00$500.00$336.00$630.00
42Barrier reflector, type 2, bidirectional (626E00110)EACH9$14.00$15.00$13.00$14.10$14.50
43Ground mounted support, no. 3 post (630E03100)FT42$20.00$25.00$20.00$55.38$61.00
44Street name sign support, no. 3 post (630E08520)FT14$22.00$25.00$21.00$55.38$61.00
45Sign support assembly, bridge mounted, type 1 (630E79600)EACH1$1,570.00$1,900.00$1,500.00$251.74$278.00
46Sign, flat sheet (630E80100)SF12$31.00$35.00$30.00$65.45$73.00
47Sign, double faced, street name (630E80500)EACH2$265.00$310.00$250.00$251.75$278.00
48Removal of ground mounted sign and disposal (630E84900)EACH6$30.00$35.00$30.00$151.05$167.00
49Removal of ground mounted post support and disposal (630E86002)EACH4$30.00$35.00$30.00$151.05$167.00
50Edge line, 6" (646E10010)MI0.09$24,000$42,000$23,000$27,994$25,741
51Center line (646E10200)MI0.05$41,500$74,000$40,000$27,994$44,445
52Traffic compacted surface, type A (410E10000)CY25$140.00$180.00$155.00$251.90$78.00
53Law enforcement officer with patrol car for assistance (614E11110)HR16$80.00$110.00$110.00$125.87$125.00
54Special - work zone traffic signal (614E11300)EACH4$5,800.00$12,000$4,400.00$6,671.18$5,250.00
55Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384)EACH4$2,300.00$3,000.00$2,250.00$2,059.26$4,225.00
56Asphalt concrete for maintaining traffic (614E13000)CY15$180.00$540.00$470.00$745.33$223.00
57Barrier reflector, type 1, bidirectional (614E13310)EACH8$10.00$50.00$18.00$6.55$49.00
58Object marker, two way (614E13360)EACH8$18.00$55.00$26.00$22.66$50.00
59Work zone edge line, class I, 6", 740.06, type I (614E22210)MI0.04$26,500$29,000$25,500$16,430$28,334
60Work zone stop line, class I, 740.06, type I (614E26400)FT39$15.00$15.00$14.00$8.16$156.56
61Portable barrier, unanchored (622E41100)FT340$20.00$30.00$30.00$63.59$81.00
62Special - misc.: work involving asbestos containin (690E98400)LS1$100.00$140.00$145.00$1,006.97$500.00
63Structure removed, over 20 foot span, as per plan (202E11003)LS1$175,000$96,000$146,000$232,132$209,222
64Wearing course removed (202E23500)SY192$1.00$60.00$18.00$20.43$33.00
65Cofferdams and excavation bracing (503E11100)LS1$80,000$25,000$82,000$30,289$21,222
66Cofferdams and excavation bracing, as per plan (503E11101)LS1$65,000$64,000$85,000$89,755$64,223
67Cofferdams and excavation bracing, as per plan (503E11101)LS1$75,000$57,000$66,000$109,460$60,444
68Cofferdams and excavation bracing, as per plan (503E11101)LS1$42,000$38,000$40,000$63,696$60,444
69Unclassified excavation (503E21100)CY387$170.00$40.00$173.00$293.59$183.00
70Pile driving equipment mobilization (505E11100)LS1$30,000$47,000$52,000$7,782.25$68,778
71Steel piles HP14X73, furnished (507E00300)FT1,390$77.00$85.00$76.00$103.65$77.51
72Steel piles HP14X73, driven (507E00350)FT1,220$30.00$50.00$35.00$28.49$20.00
73Prebored holes (507E92200)FT170$20.00$150.00$625.00$2.91$60.00
74Steel points or shoes (507E93300)EACH34$165.00$180.00$168.00$341.45$173.00
75Epoxy coated steel reinforcement (509E10000)LB22,928$1.90$2.00$2.40$2.56$2.33
76Class QC2 concrete with QC/QA, superstructure, as per plan (511E31613)CY74$1,470.00$2,100.00$2,600.00$1,756.48$1,354.00
77Class QC1 concrete with QC/QA, abutment not including footing (511E44112)CY73$990.00$1,400.00$2,450.00$1,354.28$974.00
78Class QC1 concrete with QC/QA, footing (511E46512)CY86$550.00$990.00$1,325.00$664.38$591.00
79Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY196$30.00$40.00$40.00$40.28$56.00
80Type 2 waterproofing (512E33000)SY29$45.00$75.00$72.00$38.84$79.00
81Prestressed concrete composite box beam bridge members, level 1, CB33-48, as per plan (515E12091)EACH8$44,500$54,000$26,500$45,734$46,389
822" preformed expansion joint filler (516E13900)SF21$10.00$4.50$15.00$7.76$8.50
83Semi-integral abutment expansion joint seal (516E14020)FT91$50.00$55.00$43.53$43.83$43.00
841/8" preformed bearing pad, type CDP (516E41100)EACH32$70.00$80.00$18.00$43.73$19.00
85Elastomeric bearing with internal laminates and load plate, as per plan (516E44101)EACH32$820.00$900.00$985.00$1,129.62$1,118.00
86Railing (twin steel tube), as per plan (517E70001)FT178$580.00$640.00$545.00$538.73$618.00
87Railing (twin steel tube), as per plan (517E70001)FT26$500.00$480.00$410.00$698.84$492.00
88Porous backfill with geotextile fabric (518E21200)CY66$155.00$210.00$176.00$145.91$329.00
896" perforated corrugated plastic pipe (518E40000)FT108$22.00$10.00$12.00$7.14$19.00
906" non-perforated corrugated plastic pipe, including specials (518E40010)FT60$22.00$15.00$18.00$35.28$19.00
91Reinforced concrete approach slabs with QC/QA (T=1 (526E25011)SY89$520.00$480.00$560.00$507.28$496.00
92Reinforced concrete approach slabs with QC/QA (T=1 (526E30011)SY107$530.00$680.00$540.00$508.53$519.00
93Type A installation (526E90010)FT64$260.00$480.00$305.00$258.20$253.00
94Special - structural survey and monitoring of vibration (530E14000)LS1$14,500$16,000$12,000$7,406.27$14,000
95Rock channel protection, type C with filter (601E32200)CY220$190.00$170.00$120.00$179.08$222.00
96Structure grounding system (625E33000)EACH1$13,000$34,000$12,500$16,551$5,000.00
97Premium for contract performance bond and for payment bond (103E05000)LS1$20,000$20,000$13,000$0.01$22,700
98Maintaining traffic (614E11000)LS1$8,000.00$50,000$6,500.00$7,219.40$59,445
99Field office, type B (619E16010)MNTH14$1,450.00$1,400.00$4,000.00$2,167.14$1,500.00
100Construction layout stakes and surveying (623E10000)LS1$22,000$30,000$36,000$38,204$108,778
101Mobilization (624E10000)LS1$105,000$100,000$124,800$114,404$98,678
ODOT contract 260363: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 13, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy