ODOT contract 260425 bid tabulation
HAM-IR 71-02.26/02.94/03.44 (BRIDGE REPAIR). Let by Ohio DOT on October 1, 2026, HAM. 5 bids received; low bid $5,667,659 by Sunesis Construction Co, +40% against the engineer's estimate of $4,050,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 94
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sunesis Construction Co | $5,667,659 | Low | +40% |
| 2 | Corrosion Resistance LTD | $5,688,083 | 0.0% | +40% |
| 3 | Eagle Bridge Co | $5,856,276 | +3.0% | +45% |
| 4 | Prus Construction Company | $6,327,238 | +12% | +56% |
| 5 | Elite Contractors Inc | $6,457,509 | +14% | +59% |
Engineer's estimate: $4,050,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sunesis Construction Co | 2. Corrosion Resistance LTD | 3. Eagle Bridge Co | 4. Prus Construction Company | 5. Elite Contractors Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 2 | Edge line, 6", type 1 (642E00104) | MI | 0.54 | $4,590.00 | $4,590.00 | $4,590.00 | $5,280.00 | $4,590.00 |
| 3 | Lane line, 4", type 1 (642E00200) | MI | 0.75 | $2,155.00 | $2,155.00 | $2,155.00 | $2,480.00 | $2,155.00 |
| 4 | Center line, type 1 (642E00300) | MI | 0.19 | $5,810.00 | $5,810.00 | $5,810.00 | $6,680.00 | $5,810.00 |
| 5 | Channelizing line, 8", type 1 (642E00400) | FT | 200 | $4.00 | $4.00 | $4.00 | $4.50 | $4.00 |
| 6 | Removal of pavement marking (642E30030) | MI | 1.15 | $6,147.00 | $6,147.34 | $6,250.00 | $7,070.00 | $6,147.34 |
| 7 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 960 | $111.74 | $125.00 | $145.00 | $150.00 | $100.00 |
| 8 | Increased barrier delineation (614E11630) | FT | 560 | $1.86 | $1.86 | $2.25 | $2.15 | $1.86 |
| 9 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 5 | $1,901.11 | $1,949.98 | $2,000.00 | $2,250.00 | $1,949.98 |
| 10 | Work zone impact attenuator, 24" wide hazards, (unidirectional), as per plan (614E12381) | EACH | 1 | $2,181.55 | $2,237.35 | $2,500.00 | $2,575.00 | $2,237.35 |
| 11 | Barrier reflector, type 1, one-way (614E13310) | EACH | 36 | $11.41 | $11.41 | $15.00 | $13.00 | $11.41 |
| 12 | Object marker, one way (614E13350) | EACH | 36 | $18.00 | $22.91 | $24.00 | $26.35 | $22.91 |
| 13 | Portable changeable message sign, as per plan (614E18601) | SNMT | 36 | $895.00 | $883.75 | $800.00 | $1,000.00 | $883.75 |
| 14 | Work zone lane line, class I, 4", 740.06, type I (614E20200) | MI | 0.06 | $7,319.00 | $7,319.00 | $11,250 | $8,420.00 | $7,319.00 |
| 15 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.06 | $16,635 | $16,635 | $24,000 | $19,125 | $16,635 |
| 16 | Work zone edge line, class I, 4", 740.06, type I (614E22200) | MI | 0.07 | $11,402 | $11,402 | $18,000 | $13,125 | $11,402 |
| 17 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.48 | $13,974 | $13,974 | $20,000 | $16,100 | $13,974 |
| 18 | Work zone dotted line, class I, 4", 740.06, type I (614E24400) | FT | 722 | $1.56 | $1.56 | $2.25 | $1.85 | $1.56 |
| 19 | Portable barrier, unanchored (622E41100) | FT | 1,530 | $38.38 | $38.38 | $60.00 | $44.00 | $38.38 |
| 20 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $9,757.11 | $15,000 | $20,000 | $5,725.00 | $15,000 |
| 21 | Walk removed, as per plan (202E30001) | SF | 150 | $25.67 | $20.00 | $20.00 | $6.50 | $20.00 |
| 22 | Concrete, misc.: curb repair (511E81100) | FT | 3 | $783.79 | $715.00 | $715.00 | $290.00 | $715.00 |
| 23 | Treating of concrete bridge deck with SRS, as per plan (512E10401) | SY | 1,549 | $9.65 | $10.00 | $10.00 | $27.00 | $10.00 |
| 24 | Concrete repair by epoxy injection (512E10600) | FT | 80 | $212.39 | $160.00 | $160.00 | $225.00 | $160.00 |
| 25 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 2,089 | $17.00 | $17.00 | $17.00 | $21.00 | $10.00 |
| 26 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 1,590 | $26.50 | $26.50 | $26.50 | $77.00 | $26.50 |
| 27 | Surface preparation of existing structural steel, as per plan (514E00051) | SF | 34,051 | $20.29 | $12.55 | $20.00 | $23.00 | $21.00 |
| 28 | Field painting of existing structural steel, prime coat (514E00056) | SF | 34,051 | $13.00 | $3.70 | $13.00 | $15.00 | $7.00 |
| 29 | Field painting structural steel, intermediate coat (514E00060) | SF | 34,051 | $3.00 | $5.55 | $3.00 | $3.50 | $7.00 |
| 30 | Field painting structural steel, finish coat (514E00066) | SF | 34,051 | $2.00 | $5.55 | $2.00 | $2.35 | $7.00 |
| 31 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 35 | $150.00 | $85.00 | $150.00 | $172.50 | $100.00 |
| 32 | Final inspection repair (514E10000) | EACH | 11 | $250.00 | $500.00 | $250.00 | $287.50 | $200.00 |
| 33 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $44,162 | $75,000 | $85,000 | $41,175 | $75,000 |
| 34 | Scupper, misc.: grate replacement (518E12500) | EACH | 1 | $973.88 | $1,250.00 | $1,250.00 | $1,075.00 | $1,250.00 |
| 35 | Structure drainage, misc.: bridge drainage system (518E63300) | LS | 1 | $13,810 | $50,000 | $52,500 | $13,750 | $50,000 |
| 36 | Structure drainage, misc.: scupper and drainage PI (518E63300) | LS | 1 | $7,574.97 | $20,000 | $25,000 | $6,300.00 | $20,000 |
| 37 | Patching concrete structure, as per plan (519E11101) | SF | 132 | $543.32 | $205.00 | $205.00 | $108.00 | $205.00 |
| 38 | Patching concrete bridge deck - type B (519E12300) | SY | 39 | $1,667.24 | $800.00 | $850.00 | $750.00 | $800.00 |
| 39 | Approach slabs, misc.: joint sealer (526E98200) | FT | 144 | $16.16 | $105.00 | $110.00 | $85.00 | $105.00 |
| 40 | Special - structures: sidewalk joint repair (530E00200) | LS | 1 | $2,480.00 | $6,000.00 | $7,500.00 | $1,500.00 | $6,000.00 |
| 41 | Fence, misc.: fence repairs (607E98100) | EACH | 125 | $379.33 | $223.00 | $223.00 | $395.00 | $223.00 |
| 42 | 4" concrete walk, as per plan (608E10001) | SF | 150 | $25.33 | $40.00 | $45.00 | $23.50 | $40.00 |
| 43 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $26,950 | $25,000 | $27,500 | $11,365 | $25,000 |
| 44 | Portions of structure removed, as per plan (202E11201) | LS | 1 | $77,628 | $65,000 | $75,000 | $4,750.00 | $65,000 |
| 45 | Walk removed, as per plan (202E30001) | SF | 213 | $15.49 | $15.00 | $15.00 | $5.00 | $15.00 |
| 46 | Removal misc.: sign support attachments, electrica (202E98000) | LS | 1 | $5,490.89 | $12,500 | $13,500 | $5,625.00 | $12,500 |
| 47 | Removal misc.: utility conduits (202E98000) | LS | 1 | $3,238.08 | $1.00 | $1.00 | $15,000 | $1.00 |
| 48 | Concrete, misc.: curb repair (511E81100) | FT | 5 | $496.95 | $550.00 | $550.00 | $345.00 | $550.00 |
| 49 | Treating of concrete bridge deck with SRS, as per plan (512E10401) | SY | 1,591 | $9.65 | $10.00 | $10.00 | $23.75 | $10.00 |
| 50 | Concrete repair by epoxy injection (512E10600) | FT | 46 | $244.06 | $180.00 | $180.00 | $257.00 | $180.00 |
| 51 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 1,497 | $17.00 | $17.00 | $17.00 | $18.50 | $17.00 |
| 52 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 1,477 | $26.50 | $26.50 | $26.50 | $77.00 | $26.50 |
| 53 | Surface preparation of existing structural steel, as per plan (514E00051) | SF | 32,456 | $11.02 | $13.20 | $11.00 | $13.00 | $21.00 |
| 54 | Field painting of existing structural steel, prime coat (514E00056) | SF | 32,456 | $8.00 | $3.80 | $8.00 | $9.25 | $7.00 |
| 55 | Field painting structural steel, intermediate coat (514E00060) | SF | 32,456 | $3.00 | $5.60 | $3.00 | $3.50 | $7.00 |
| 56 | Field painting structural steel, finish coat (514E00066) | SF | 32,456 | $2.00 | $5.75 | $2.00 | $2.35 | $7.00 |
| 57 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 31 | $150.00 | $70.00 | $150.00 | $172.50 | $100.00 |
| 58 | Final inspection repair (514E10000) | EACH | 9 | $250.00 | $500.00 | $250.00 | $287.50 | $200.00 |
| 59 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44301) | EACH | 12 | $3,978.94 | $2,750.00 | $3,000.00 | $2,475.00 | $2,750.00 |
| 60 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $38,547 | $65,000 | $75,000 | $67,750 | $65,000 |
| 61 | Structure drainage, misc.: scupper and drainage PI (518E63300) | LS | 1 | $7,574.97 | $12,500 | $15,000 | $6,300.00 | $12,500 |
| 62 | Patching concrete structure, as per plan (519E11101) | SF | 254 | $439.42 | $200.00 | $200.00 | $108.00 | $200.00 |
| 63 | Patching concrete bridge deck - type B (519E12300) | SY | 4 | $2,332.60 | $1,250.00 | $1,350.00 | $925.00 | $1,250.00 |
| 64 | Crushed aggregate slope protection (601E20010) | CY | 100 | $595.21 | $180.00 | $180.00 | $175.00 | $180.00 |
| 65 | 4" concrete walk, as per plan (608E10001) | SF | 213 | $23.00 | $30.00 | $30.00 | $17.50 | $30.00 |
| 66 | Special - asbestos abatement: work involving asbes (690E71000) | LS | 1 | $13,113 | $300.00 | $300.00 | $2,875.00 | $300.00 |
| 67 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $11,878 | $17,500 | $20,000 | $5,700.00 | $17,500 |
| 68 | Portions of structure removed, as per plan (202E11201) | LS | 1 | $89,837 | $75,000 | $85,000 | $7,275.00 | $75,000 |
| 69 | Walk removed, as per plan (202E30001) | SF | 661 | $16.62 | $10.00 | $10.00 | $4.35 | $10.00 |
| 70 | Treating of concrete bridge deck with SRS, as per plan (512E10401) | SY | 1,565 | $9.65 | $10.00 | $10.00 | $26.50 | $10.00 |
| 71 | Concrete repair by epoxy injection (512E10600) | FT | 48 | $236.12 | $160.00 | $160.00 | $245.00 | $160.00 |
| 72 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 1,529 | $17.00 | $17.00 | $17.00 | $18.00 | $17.00 |
| 73 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 942 | $26.50 | $26.50 | $26.50 | $82.00 | $26.50 |
| 74 | Surface preparation of existing structural steel, as per plan (514E00051) | SF | 30,170 | $18.00 | $14.15 | $18.00 | $20.75 | $21.00 |
| 75 | Field painting of existing structural steel, prime coat (514E00056) | SF | 30,170 | $10.00 | $4.00 | $10.00 | $11.50 | $7.00 |
| 76 | Field painting structural steel, intermediate coat (514E00060) | SF | 30,170 | $3.00 | $6.10 | $3.00 | $3.50 | $7.00 |
| 77 | Field painting structural steel, finish coat (514E00066) | SF | 30,170 | $2.00 | $6.15 | $2.00 | $2.35 | $7.00 |
| 78 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 30 | $150.00 | $70.00 | $150.00 | $172.50 | $100.00 |
| 79 | Final inspection repair (514E10000) | EACH | 9 | $250.00 | $550.00 | $250.00 | $287.50 | $200.00 |
| 80 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 7 | $3,297.40 | $2,250.00 | $2,750.00 | $1,705.00 | $2,250.00 |
| 81 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 7 | $3,870.81 | $2,750.00 | $3,250.00 | $2,400.00 | $2,750.00 |
| 82 | Reset bearing (516E46700) | EACH | 1 | $4,878.40 | $3,500.00 | $5,000.00 | $800.00 | $3,500.00 |
| 83 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $63,627 | $125,000 | $140,000 | $87,785 | $125,000 |
| 84 | Structure drainage, misc.: bridge drainage system (518E63300) | LS | 1 | $14,849 | $50,000 | $55,000 | $13,700 | $50,000 |
| 85 | Structure drainage, misc.: scupper and drainage PI (518E63300) | LS | 1 | $7,574.97 | $12,500 | $12,500 | $6,300.00 | $12,500 |
| 86 | Patching concrete structure, as per plan (519E11101) | SF | 442 | $485.56 | $205.00 | $205.00 | $110.00 | $205.00 |
| 87 | Patching concrete bridge deck - type B (519E12300) | SY | 14 | $2,354.34 | $1,000.00 | $1,100.00 | $800.00 | $1,000.00 |
| 88 | Fence, misc.: fence repair (607E98100) | EACH | 320 | $325.00 | $219.00 | $219.00 | $375.00 | $219.00 |
| 89 | 4" concrete walk, as per plan (608E10001) | SF | 661 | $19.84 | $20.00 | $25.00 | $12.85 | $20.00 |
| 90 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $26,706 | $50,000 | $125,000 | $60,250 | $200,000 |
| 91 | Maintaining traffic (614E11000) | LS | 1 | $455,084 | $1,000,000 | $571,000 | $883,350 | $300,000 |
| 92 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1,000.00 | $14,000 | $15,000 | $11,835 | $10,000 |
| 93 | Mobilization (624E10000) | LS | 1 | $251,626 | $223,000 | $287,500 | $200,000 | $300,000 |
| 100 | Special - asbestos abatement: work involving asbes (690E71000) | LS | 1 | $13,113 | $250.00 | $250.00 | $5,700.00 | $250.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.