ODOT contract 260381 bid tabulation

CLE-SR 125-14.08 (SIDEWALK). Let by Ohio DOT on August 27, 2026, CLE. 5 bids received; low bid $972,510 by Axis Civil Construction LLC, -1.2% against the engineer's estimate of $984,000.

Owner
Ohio DOT
Letting
27 AUG 2026
Pay items
79
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Axis Civil Construction LLC$972,510Low-1.0%
2Fillmore Construction$978,411+1.0%-1.0%
3Sunesis Construction Co$1,073,410+10%+9.0%
4Prus Construction Company$1,162,328+20%+18%
5Ford Development Corp$1,362,959+40%+39%
ODOT contract 260381: bids by rank

Engineer's estimate: $984,000.

Bid tabulation

LinePay itemUnitQuantity1. Axis Civil Construction LLC2. Fillmore Construction3. Sunesis Construction Co4. Prus Construction Company5. Ford Development Corp
1Clearing and grubbing (201E11000)LS1$5,000.00$15,000$2,612.78$5,500.00$3,000.00
2Pavement removed (202E23000)SY3,113$16.20$10.00$18.61$19.50$13.00
3Pavement removed (202E23000)SY130$18.00$15.00$23.11$40.00$13.00
4Walk removed (202E30000)SF300$3.20$10.00$1.35$3.85$3.00
5Curb removed (202E32000)FT38$20.00$15.00$11.44$20.00$5.00
6Curb and gutter removed (202E32500)FT589$20.00$15.00$8.12$18.00$12.00
7Pipe removed, 24" and under (202E35100)FT30$30.00$30.00$19.21$50.00$22.00
8Guardrail removed (202E38000)FT292$7.00$10.00$5.51$2.80$2.00
9Manhole removed (202E58000)EACH1$750.43$750.00$976.65$3,500.00$1,700.00
10Catch basin removed (202E58100)EACH2$750.00$500.00$467.26$1,050.00$670.00
11Special - pipe cleanout, 24" and under (202E70110)FT57$60.00$100.00$24.08$42.00$21.00
12Excavation (203E10000)CY1,274$35.00$30.00$65.46$35.00$11.00
13Embankment (203E20000)CY279$35.00$50.00$20.05$32.00$150.00
14Subgrade compaction (204E10000)SY705$3.00$5.00$7.50$3.25$3.00
15Guardrail, type MGS with long posts (606E15100)FT250$37.00$42.00$40.70$36.50$30.00
16Anchor assembly, MGS type E, (MASH 2016) (606E26150)EACH1$2,750.00$2,850.00$3,025.00$3,080.00$3,000.00
17Anchor assembly, MGS type T (606E26550)EACH1$1,350.00$1,500.00$1,485.00$3,080.00$1,500.00
185" concrete walk (608E12000)SF14,467$9.50$10.00$9.29$10.00$20.00
19Curb ramp (608E52000)SF818$16.50$30.00$24.26$18.50$48.00
20Special - work involving petroleum contaminated soil (690E65016)TON20$300.00$1,000.00$251.98$448.00$80.00
21Special - mailbox and support system, single (690E98000)EACH6$200.00$500.00$176.31$675.00$250.00
22Special -consultant for concrete quality control I (690E98400)LS1$11,500$20,000$11,440$31,000$60,000
23Rock channel protection, type D with filter (601E32300)CY4.45$250.00$200.00$306.64$395.00$175.00
24Topsoil (659E00300)CY420$62.00$50.00$20.91$75.00$23.00
25Seeding and mulching, class 1 (659E00500)SY3,780$1.30$1.45$4.59$2.40$1.50
26Repair seeding and mulching (659E14000)SY140$1.30$2.20$2.20$2.40$1.00
27Inter-seeding (659E15000)SY140$1.30$2.20$2.20$2.40$0.50
28Commercial fertilizer (659E20000)TON0.38$1,250.00$1,400.00$760.00$850.00$500.00
29Lime (659E31000)ACRE0.58$150.00$450.00$50.00$55.00$70.00
30Water (659E35000)MGAL15.10$1.00$1.00$50.00$55.00$3.00
31Slope erosion protection (670E00500)SY985$2.50$2.25$3.75$4.00$2.00
32Storm water pollution prevention plan (832E15000)LS1$3,000.00$5,000.00$2,850.00$3,000.00$3,000.00
33Storm water pollution prevention inspections (832E15002)LS1$8,100.00$10,000$4,750.00$14,500$5,000.00
34Storm water pollution prevention inspection software (832E15010)LS1$13,250$10,000$13,231$15,000$7,500.00
35Erosion control (832E30000)EACH15,000$1.00$1.00$1.00$1.00$1.00
3612" conduit, type B (611E04400)FT479$75.00$100.00$96.23$110.00$175.00
3712" conduit, type C (611E04600)FT161$80.00$85.00$82.01$122.00$150.00
3815" conduit, type B (611E05900)FT80$80.00$120.00$113.57$142.00$200.00
3915" conduit, type B (611E05900)FT5$250.00$120.00$271.04$450.00$200.00
4015" conduit, type C (611E06100)FT19$115.00$110.00$100.24$150.00$190.00
4118" conduit, type B (611E07400)FT20$115.00$150.00$431.22$360.00$250.00
42Catch basin, no. 3 (611E98150)EACH1$5,200.00$10,000$5,219.25$6,500.00$7,000.00
43Catch basin, no. 3A (611E98180)EACH9$4,200.00$7,500.00$3,717.78$5,200.00$5,000.00
44Catch basin, no. 6 (611E98370)EACH1$4,200.00$10,000$2,845.92$4,600.00$7,000.00
45Manhole, no. 3 (611E99574)EACH1$5,500.00$7,500.00$4,028.86$8,200.00$10,000
46Manhole reconstructed to grade (611E99660)EACH2$2,500.00$3,500.00$1,386.85$5,700.00$5,000.00
47Pavement repair, as per plan (253E02001)CY268$345.00$94.00$391.69$280.00$250.00
48Aggregate base (304E20000)CY100$150.00$100.00$140.79$145.00$150.00
49Non-tracking tack coat (407E20000)GAL13$6.00$10.00$129.50$11.20$5.00
50Stabilized crushed aggregate (411E10000)CY142$165.00$100.00$163.70$148.00$150.00
51Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY8$750.00$440.00$2,510.88$950.00$500.00
52Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700)CY17$510.00$400.00$1,848.55$590.00$400.00
537" non-reinforced concrete pavement, class QC 1P (452E11010)SY51$135.00$100.00$106.23$120.00$225.00
548" non-reinforced concrete pavement, class QC 1P (452E12010)SY402$145.00$107.00$93.86$126.00$235.00
55Combination curb and gutter, type 2 (609E12000)FT2,310$39.00$45.00$36.00$42.70$40.00
56Curb, type 6 (609E26000)FT277$38.00$50.00$39.09$50.00$45.00
57Barrier reflector, type 2, bidirectional (626E00110)EACH3$15.25$12.50$16.78$22.40$12.00
58Ground mounted support, no. 3 post (630E03100)FT222$15.50$15.00$15.50$17.35$17.00
59Sign post reflector (630E08600)EACH1$55.00$50.00$55.00$61.60$60.00
60Sign, flat sheet (630E80100)SF73$16.00$25.00$16.00$18.00$18.00
61Removal of ground mounted sign and disposal (630E84900)EACH6$20.00$25.00$20.00$22.40$20.00
62Removal of ground mounted sign and reerection (630E85100)EACH4$45.00$175.00$45.00$50.40$50.00
63Removal of ground mounted post support and disposal (630E86002)EACH10$10.00$25.00$25.00$28.00$25.00
64Signing, misc.: solar powered rectangular rapid FL (630E97700)EACH6$6,165.00$8,750.00$7,950.00$8,900.00$8,750.00
65Pedestal foundation (632E64020)EACH6$2,325.00$1,950.00$1,573.87$1,500.00$1,500.00
66Lane line, 4" (644E00200)MI0.02$2,175.00$7,500.00$7,500.00$8,400.00$8,250.00
67Center line (644E00300)MI0.04$7,910.00$30,000$30,000$33,600$33,000
68Stop line (644E00500)FT11$9.90$8.00$8.00$8.96$9.00
69Crosswalk line, 24" (644E00630)FT294$7.90$8.00$8.00$8.96$9.00
70Transverse/diagonal line (644E00700)FT46$9.90$8.00$8.00$8.96$9.00
71School symbol marking, 96" (644E01110)EACH2$495.00$700.00$700.00$784.00$770.00
72Yield line (644E20800)FT75$39.50$40.00$40.00$44.80$44.00
73Removal of pavement marking (644E30000)FT234$9.75$8.71$11.00$9.75$10.00
74Removal of pavement marking (644E30020)EACH2$350.00$450.00$717.75$504.00$500.00
75Class QC1 concrete, headwall (511E46610)CY1.11$3,200.00$2,000.00$5,953.24$5,400.00$2,500.00
76Premium for contract performance bond and for payment bond (103E05000)LS1$9,500.00$8,500.00$6,490.28$11,500$13,000
77Maintaining traffic (614E11000)LS1$25,000$25,000$25,289$72,000$100,000
78Construction layout stakes and surveying, as per plan (623E10001)LS1$14,000$7,500.00$14,100$15,800$20,000
79Mobilization (624E10000)LS1$30,000$23,000$60,627$40,000$40,000
ODOT contract 260381: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy