ODOT contract 260381 bid tabulation
CLE-SR 125-14.08 (SIDEWALK). Let by Ohio DOT on August 27, 2026, CLE. 5 bids received; low bid $972,510 by Axis Civil Construction LLC, -1.2% against the engineer's estimate of $984,000.
- Owner
- Ohio DOT
- Letting
- 27 AUG 2026
- Pay items
- 79
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Axis Civil Construction LLC | $972,510 | Low | -1.0% |
| 2 | Fillmore Construction | $978,411 | +1.0% | -1.0% |
| 3 | Sunesis Construction Co | $1,073,410 | +10% | +9.0% |
| 4 | Prus Construction Company | $1,162,328 | +20% | +18% |
| 5 | Ford Development Corp | $1,362,959 | +40% | +39% |
Engineer's estimate: $984,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Axis Civil Construction LLC | 2. Fillmore Construction | 3. Sunesis Construction Co | 4. Prus Construction Company | 5. Ford Development Corp |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $15,000 | $2,612.78 | $5,500.00 | $3,000.00 |
| 2 | Pavement removed (202E23000) | SY | 3,113 | $16.20 | $10.00 | $18.61 | $19.50 | $13.00 |
| 3 | Pavement removed (202E23000) | SY | 130 | $18.00 | $15.00 | $23.11 | $40.00 | $13.00 |
| 4 | Walk removed (202E30000) | SF | 300 | $3.20 | $10.00 | $1.35 | $3.85 | $3.00 |
| 5 | Curb removed (202E32000) | FT | 38 | $20.00 | $15.00 | $11.44 | $20.00 | $5.00 |
| 6 | Curb and gutter removed (202E32500) | FT | 589 | $20.00 | $15.00 | $8.12 | $18.00 | $12.00 |
| 7 | Pipe removed, 24" and under (202E35100) | FT | 30 | $30.00 | $30.00 | $19.21 | $50.00 | $22.00 |
| 8 | Guardrail removed (202E38000) | FT | 292 | $7.00 | $10.00 | $5.51 | $2.80 | $2.00 |
| 9 | Manhole removed (202E58000) | EACH | 1 | $750.43 | $750.00 | $976.65 | $3,500.00 | $1,700.00 |
| 10 | Catch basin removed (202E58100) | EACH | 2 | $750.00 | $500.00 | $467.26 | $1,050.00 | $670.00 |
| 11 | Special - pipe cleanout, 24" and under (202E70110) | FT | 57 | $60.00 | $100.00 | $24.08 | $42.00 | $21.00 |
| 12 | Excavation (203E10000) | CY | 1,274 | $35.00 | $30.00 | $65.46 | $35.00 | $11.00 |
| 13 | Embankment (203E20000) | CY | 279 | $35.00 | $50.00 | $20.05 | $32.00 | $150.00 |
| 14 | Subgrade compaction (204E10000) | SY | 705 | $3.00 | $5.00 | $7.50 | $3.25 | $3.00 |
| 15 | Guardrail, type MGS with long posts (606E15100) | FT | 250 | $37.00 | $42.00 | $40.70 | $36.50 | $30.00 |
| 16 | Anchor assembly, MGS type E, (MASH 2016) (606E26150) | EACH | 1 | $2,750.00 | $2,850.00 | $3,025.00 | $3,080.00 | $3,000.00 |
| 17 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,350.00 | $1,500.00 | $1,485.00 | $3,080.00 | $1,500.00 |
| 18 | 5" concrete walk (608E12000) | SF | 14,467 | $9.50 | $10.00 | $9.29 | $10.00 | $20.00 |
| 19 | Curb ramp (608E52000) | SF | 818 | $16.50 | $30.00 | $24.26 | $18.50 | $48.00 |
| 20 | Special - work involving petroleum contaminated soil (690E65016) | TON | 20 | $300.00 | $1,000.00 | $251.98 | $448.00 | $80.00 |
| 21 | Special - mailbox and support system, single (690E98000) | EACH | 6 | $200.00 | $500.00 | $176.31 | $675.00 | $250.00 |
| 22 | Special -consultant for concrete quality control I (690E98400) | LS | 1 | $11,500 | $20,000 | $11,440 | $31,000 | $60,000 |
| 23 | Rock channel protection, type D with filter (601E32300) | CY | 4.45 | $250.00 | $200.00 | $306.64 | $395.00 | $175.00 |
| 24 | Topsoil (659E00300) | CY | 420 | $62.00 | $50.00 | $20.91 | $75.00 | $23.00 |
| 25 | Seeding and mulching, class 1 (659E00500) | SY | 3,780 | $1.30 | $1.45 | $4.59 | $2.40 | $1.50 |
| 26 | Repair seeding and mulching (659E14000) | SY | 140 | $1.30 | $2.20 | $2.20 | $2.40 | $1.00 |
| 27 | Inter-seeding (659E15000) | SY | 140 | $1.30 | $2.20 | $2.20 | $2.40 | $0.50 |
| 28 | Commercial fertilizer (659E20000) | TON | 0.38 | $1,250.00 | $1,400.00 | $760.00 | $850.00 | $500.00 |
| 29 | Lime (659E31000) | ACRE | 0.58 | $150.00 | $450.00 | $50.00 | $55.00 | $70.00 |
| 30 | Water (659E35000) | MGAL | 15.10 | $1.00 | $1.00 | $50.00 | $55.00 | $3.00 |
| 31 | Slope erosion protection (670E00500) | SY | 985 | $2.50 | $2.25 | $3.75 | $4.00 | $2.00 |
| 32 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,000.00 | $5,000.00 | $2,850.00 | $3,000.00 | $3,000.00 |
| 33 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $8,100.00 | $10,000 | $4,750.00 | $14,500 | $5,000.00 |
| 34 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $13,250 | $10,000 | $13,231 | $15,000 | $7,500.00 |
| 35 | Erosion control (832E30000) | EACH | 15,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 36 | 12" conduit, type B (611E04400) | FT | 479 | $75.00 | $100.00 | $96.23 | $110.00 | $175.00 |
| 37 | 12" conduit, type C (611E04600) | FT | 161 | $80.00 | $85.00 | $82.01 | $122.00 | $150.00 |
| 38 | 15" conduit, type B (611E05900) | FT | 80 | $80.00 | $120.00 | $113.57 | $142.00 | $200.00 |
| 39 | 15" conduit, type B (611E05900) | FT | 5 | $250.00 | $120.00 | $271.04 | $450.00 | $200.00 |
| 40 | 15" conduit, type C (611E06100) | FT | 19 | $115.00 | $110.00 | $100.24 | $150.00 | $190.00 |
| 41 | 18" conduit, type B (611E07400) | FT | 20 | $115.00 | $150.00 | $431.22 | $360.00 | $250.00 |
| 42 | Catch basin, no. 3 (611E98150) | EACH | 1 | $5,200.00 | $10,000 | $5,219.25 | $6,500.00 | $7,000.00 |
| 43 | Catch basin, no. 3A (611E98180) | EACH | 9 | $4,200.00 | $7,500.00 | $3,717.78 | $5,200.00 | $5,000.00 |
| 44 | Catch basin, no. 6 (611E98370) | EACH | 1 | $4,200.00 | $10,000 | $2,845.92 | $4,600.00 | $7,000.00 |
| 45 | Manhole, no. 3 (611E99574) | EACH | 1 | $5,500.00 | $7,500.00 | $4,028.86 | $8,200.00 | $10,000 |
| 46 | Manhole reconstructed to grade (611E99660) | EACH | 2 | $2,500.00 | $3,500.00 | $1,386.85 | $5,700.00 | $5,000.00 |
| 47 | Pavement repair, as per plan (253E02001) | CY | 268 | $345.00 | $94.00 | $391.69 | $280.00 | $250.00 |
| 48 | Aggregate base (304E20000) | CY | 100 | $150.00 | $100.00 | $140.79 | $145.00 | $150.00 |
| 49 | Non-tracking tack coat (407E20000) | GAL | 13 | $6.00 | $10.00 | $129.50 | $11.20 | $5.00 |
| 50 | Stabilized crushed aggregate (411E10000) | CY | 142 | $165.00 | $100.00 | $163.70 | $148.00 | $150.00 |
| 51 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 8 | $750.00 | $440.00 | $2,510.88 | $950.00 | $500.00 |
| 52 | Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700) | CY | 17 | $510.00 | $400.00 | $1,848.55 | $590.00 | $400.00 |
| 53 | 7" non-reinforced concrete pavement, class QC 1P (452E11010) | SY | 51 | $135.00 | $100.00 | $106.23 | $120.00 | $225.00 |
| 54 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 402 | $145.00 | $107.00 | $93.86 | $126.00 | $235.00 |
| 55 | Combination curb and gutter, type 2 (609E12000) | FT | 2,310 | $39.00 | $45.00 | $36.00 | $42.70 | $40.00 |
| 56 | Curb, type 6 (609E26000) | FT | 277 | $38.00 | $50.00 | $39.09 | $50.00 | $45.00 |
| 57 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 3 | $15.25 | $12.50 | $16.78 | $22.40 | $12.00 |
| 58 | Ground mounted support, no. 3 post (630E03100) | FT | 222 | $15.50 | $15.00 | $15.50 | $17.35 | $17.00 |
| 59 | Sign post reflector (630E08600) | EACH | 1 | $55.00 | $50.00 | $55.00 | $61.60 | $60.00 |
| 60 | Sign, flat sheet (630E80100) | SF | 73 | $16.00 | $25.00 | $16.00 | $18.00 | $18.00 |
| 61 | Removal of ground mounted sign and disposal (630E84900) | EACH | 6 | $20.00 | $25.00 | $20.00 | $22.40 | $20.00 |
| 62 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $45.00 | $175.00 | $45.00 | $50.40 | $50.00 |
| 63 | Removal of ground mounted post support and disposal (630E86002) | EACH | 10 | $10.00 | $25.00 | $25.00 | $28.00 | $25.00 |
| 64 | Signing, misc.: solar powered rectangular rapid FL (630E97700) | EACH | 6 | $6,165.00 | $8,750.00 | $7,950.00 | $8,900.00 | $8,750.00 |
| 65 | Pedestal foundation (632E64020) | EACH | 6 | $2,325.00 | $1,950.00 | $1,573.87 | $1,500.00 | $1,500.00 |
| 66 | Lane line, 4" (644E00200) | MI | 0.02 | $2,175.00 | $7,500.00 | $7,500.00 | $8,400.00 | $8,250.00 |
| 67 | Center line (644E00300) | MI | 0.04 | $7,910.00 | $30,000 | $30,000 | $33,600 | $33,000 |
| 68 | Stop line (644E00500) | FT | 11 | $9.90 | $8.00 | $8.00 | $8.96 | $9.00 |
| 69 | Crosswalk line, 24" (644E00630) | FT | 294 | $7.90 | $8.00 | $8.00 | $8.96 | $9.00 |
| 70 | Transverse/diagonal line (644E00700) | FT | 46 | $9.90 | $8.00 | $8.00 | $8.96 | $9.00 |
| 71 | School symbol marking, 96" (644E01110) | EACH | 2 | $495.00 | $700.00 | $700.00 | $784.00 | $770.00 |
| 72 | Yield line (644E20800) | FT | 75 | $39.50 | $40.00 | $40.00 | $44.80 | $44.00 |
| 73 | Removal of pavement marking (644E30000) | FT | 234 | $9.75 | $8.71 | $11.00 | $9.75 | $10.00 |
| 74 | Removal of pavement marking (644E30020) | EACH | 2 | $350.00 | $450.00 | $717.75 | $504.00 | $500.00 |
| 75 | Class QC1 concrete, headwall (511E46610) | CY | 1.11 | $3,200.00 | $2,000.00 | $5,953.24 | $5,400.00 | $2,500.00 |
| 76 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $9,500.00 | $8,500.00 | $6,490.28 | $11,500 | $13,000 |
| 77 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $25,000 | $25,289 | $72,000 | $100,000 |
| 78 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $14,000 | $7,500.00 | $14,100 | $15,800 | $20,000 |
| 79 | Mobilization (624E10000) | LS | 1 | $30,000 | $23,000 | $60,627 | $40,000 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.