ODOT contract 260243 bid tabulation
MIA-CR 15-05.57 BH (BRIDGE REPAIR). Let by Ohio DOT on May 7, 2026, MIA. 4 bids received; low bid $2,560,670 by Eagle Bridge Co, -0.2% against the engineer's estimate of $2,565,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 92
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eagle Bridge Co | $2,560,670 | Low | 0.0% |
| 2 | Complete General Construction Company | $2,983,683 | +17% | +16% |
| 3 | Brumbaugh Construction Inc | $3,000,000 | +17% | +17% |
| 4 | Sunesis Construction Co | $3,779,973 | +48% | +47% |
Engineer's estimate: $2,565,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Bridge Co | 2. Complete General Construction Company | 3. Brumbaugh Construction Inc | 4. Sunesis Construction Co |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,500.00 | $8,000.00 | $5,000.00 | $4,143.62 |
| 2 | Pavement removed (202E23000) | SY | 850 | $11.00 | $12.00 | $10.00 | $28.98 |
| 3 | Walk removed (202E30000) | SF | 1,075 | $1.50 | $4.00 | $4.00 | $4.10 |
| 4 | Curb removed (202E32000) | FT | 317 | $5.00 | $10.00 | $15.00 | $5.98 |
| 5 | Guardrail removed (202E38000) | FT | 518 | $3.00 | $2.10 | $10.00 | $6.97 |
| 6 | Fence removed (202E75000) | FT | 57 | $4.00 | $4.00 | $20.00 | $27.83 |
| 7 | Excavation (203E10000) | CY | 239 | $60.00 | $45.00 | $25.00 | $47.03 |
| 8 | Embankment (203E20000) | CY | 8 | $150.00 | $60.00 | $25.00 | $53.18 |
| 9 | Subgrade compaction (204E10000) | SY | 1,290 | $4.50 | $5.00 | $2.00 | $7.20 |
| 10 | Proof rolling (204E45000) | HR | 1 | $125.00 | $250.00 | $200.00 | $476.75 |
| 11 | Guardrail, type MGS with long posts (606E15100) | FT | 363 | $28.00 | $26.60 | $30.00 | $33.00 |
| 12 | Anchor assembly, type E (606E26100) | EACH | 2 | $2,440.00 | $2,585.00 | $2,500.00 | $2,650.00 |
| 13 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 2 | $2,650.00 | $2,545.00 | $2,700.00 | $2,250.00 |
| 14 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 2 | $550.00 | $835.00 | $600.00 | $350.00 |
| 15 | Fence, type CLT (607E23000) | FT | 57 | $75.00 | $56.00 | $70.00 | $80.00 |
| 16 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 69 | $60.00 | $118.00 | $115.00 | $122.64 |
| 17 | Soil analysis test (659E00100) | EACH | 2 | $100.00 | $70.00 | $250.00 | $54.67 |
| 18 | Topsoil (659E00300) | CY | 8 | $35.00 | $80.00 | $90.00 | $144.79 |
| 19 | Seeding and mulching (659E10000) | SY | 71 | $30.00 | $22.00 | $10.00 | $11.84 |
| 20 | Repair seeding and mulching (659E14000) | SY | 4 | $5.00 | $22.00 | $2.00 | $0.28 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.01 | $2,000.00 | $800.00 | $2,500.00 | $346.00 |
| 22 | Lime (659E31000) | ACRE | 0.02 | $1.00 | $5.00 | $1.00 | $52.00 |
| 23 | Water (659E35000) | MGAL | 0.39 | $10.00 | $0.51 | $5.00 | $1.38 |
| 24 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | 6" shallow pipe underdrains (605E11100) | FT | 589 | $13.00 | $38.00 | $20.00 | $18.12 |
| 26 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 20 | $30.00 | $45.00 | $25.00 | $80.44 |
| 27 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $375.00 | $340.00 | $300.00 | $340.95 |
| 28 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 213 | $315.00 | $410.00 | $325.00 | $275.00 |
| 29 | Aggregate base (304E20000) | CY | 190 | $100.00 | $115.00 | $90.00 | $118.33 |
| 30 | Tack coat (407E10000) | GAL | 117 | $1.00 | $5.00 | $10.00 | $2.00 |
| 31 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 37 | $395.00 | $660.00 | $410.00 | $500.00 |
| 32 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 52 | $380.00 | $440.00 | $340.00 | $375.00 |
| 33 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 286 | $39.00 | $67.00 | $80.00 | $83.42 |
| 34 | Curb, type 4-C (609E24510) | FT | 27 | $31.00 | $200.00 | $95.00 | $104.53 |
| 35 | Connection, fused pull apart (625E00450) | EACH | 6 | $97.82 | $210.00 | $200.00 | $155.00 |
| 36 | Connection, unfused pull apart (625E00460) | EACH | 3 | $94.58 | $200.00 | $190.00 | $155.00 |
| 37 | Connection, unfused permanent (625E00480) | EACH | 6 | $48.24 | $175.00 | $170.00 | $155.00 |
| 38 | Light pole, conventional, A12B30 (low-rise) (625E10490) | EACH | 3 | $3,633.60 | $4,900.00 | $2,800.00 | $5,000.00 |
| 39 | Light pole anchor bolts on structure (625E10614) | EACH | 12 | $92.46 | $300.00 | $280.00 | $400.00 |
| 40 | No. 6 AWG 600 volt distribution cable (625E22990) | FT | 1,575 | $1.57 | $4.00 | $3.00 | $8.00 |
| 41 | Conduit, 2", 725.04 (625E25400) | FT | 495 | $13.45 | $40.00 | $20.00 | $25.00 |
| 42 | Luminaire, conventional, solid state (LED), 250 WA (625E26252) | EACH | 3 | $414.00 | $800.00 | $600.00 | $1,200.00 |
| 43 | Trench (625E29000) | FT | 50 | $22.50 | $26.00 | $13.00 | $20.00 |
| 44 | Structure junction box (625E29920) | EACH | 3 | $3,508.62 | $3,500.00 | $3,800.00 | $3,150.00 |
| 45 | Structure grounding system (625E33000) | EACH | 1 | $14,250 | $18,000 | $21,000 | $22,500 |
| 46 | Light pole removed for storage (625E75402) | EACH | 3 | $750.00 | $1,200.00 | $450.00 | $1,200.00 |
| 47 | Luminaire removed for storage (625E75504) | EACH | 3 | $500.00 | $300.00 | $110.00 | $250.00 |
| 48 | Disconnect circuit (625E75800) | EACH | 2 | $1,750.00 | $600.00 | $700.00 | $250.00 |
| 49 | Barrier reflector, type 1 (bidirectional) (626E00102) | EACH | 15 | $12.50 | $14.00 | $15.00 | $9.00 |
| 50 | Ground mounted support, no. 3 post (630E03100) | FT | 4 | $30.00 | $120.00 | $75.00 | $15.50 |
| 51 | Sign, flat sheet (630E80100) | SF | 7 | $16.00 | $35.00 | $25.00 | $16.00 |
| 52 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $25.00 | $15.00 | $25.00 | $20.00 |
| 53 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $20.00 | $20.00 | $30.00 | $25.00 |
| 54 | Edge line, 4" (644E00100) | MI | 0.10 | $9,160.00 | $11,900 | $10,000 | $9,160.00 |
| 55 | Center line (644E00300) | MI | 0.06 | $22,900 | $30,000 | $25,000 | $22,900 |
| 56 | Dotted line, 4" (644E01500) | FT | 85 | $5.00 | $6.50 | $5.00 | $5.00 |
| 57 | Edge line, 4" (646E10000) | MI | 0.18 | $11,403 | $15,000 | $12,000 | $11,403 |
| 58 | Center line (646E10200) | MI | 0.09 | $22,806 | $30,000 | $24,000 | $22,806 |
| 59 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $230,000 | $300,000 | $350,000 | $315,851 |
| 60 | Approach slab removed (202E22900) | SY | 167 | $50.00 | $66.00 | $45.00 | $60.20 |
| 61 | Unclassified excavation, as per plan (503E21101) | CY | 200 | $100.00 | $145.00 | $40.00 | $137.16 |
| 62 | Epoxy coated steel reinforcement (509E10000) | LB | 146,105 | $1.50 | $1.50 | $1.25 | $1.57 |
| 63 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 6,967 | $1.70 | $1.95 | $2.25 | $1.43 |
| 64 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 80 | $20.00 | $30.00 | $15.00 | $23.85 |
| 65 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 585 | $975.00 | $1,200.00 | $1,300.00 | $2,102.84 |
| 66 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 124 | $700.00 | $1,100.00 | $850.00 | $741.88 |
| 67 | Class QC1 concrete with QC/QA, abutment (511E45712) | CY | 5 | $2,000.00 | $12,000 | $2,500.00 | $5,225.63 |
| 68 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,598 | $26.75 | $26.75 | $30.00 | $26.75 |
| 69 | Welded stud shear connectors (513E20000) | EACH | 3,960 | $6.50 | $5.60 | $8.00 | $6.50 |
| 70 | Surface preparation of existing structural steel (514E00050) | SF | 35,110 | $11.00 | $11.00 | $12.00 | $11.37 |
| 71 | Field painting of existing structural steel, prime coat (514E00056) | SF | 35,110 | $4.00 | $4.00 | $3.10 | $4.14 |
| 72 | Field painting structural steel, intermediate coat (514E00060) | SF | 35,110 | $3.00 | $3.00 | $3.10 | $3.10 |
| 73 | Field painting structural steel, finish coat (514E00066) | SF | 35,110 | $2.00 | $2.00 | $3.10 | $2.07 |
| 74 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 16 | $150.00 | $150.00 | $90.00 | $155.06 |
| 75 | Final inspection repair (514E10000) | EACH | 5 | $250.00 | $250.00 | $325.00 | $258.44 |
| 76 | Field painting, misc.: coating of beam ends (514E27702) | EACH | 10 | $3,500.00 | $3,500.00 | $5,500.00 | $3,618.11 |
| 77 | 1" preformed expansion joint filler (516E13600) | SF | 15 | $5.00 | $15.00 | $5.00 | $9.54 |
| 78 | 2" preformed expansion joint filler (516E13900) | SF | 178 | $6.00 | $12.00 | $8.00 | $7.18 |
| 79 | Semi-integral abutment expansion joint seal (516E14020) | FT | 109 | $60.00 | $50.00 | $50.00 | $50.00 |
| 80 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 10 | $2,250.00 | $1,800.00 | $3,000.00 | $2,795.11 |
| 81 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $20,000 | $31,000 | $60,000 | $19,500 |
| 82 | Porous backfill with geotextile fabric (518E21200) | CY | 67 | $150.00 | $125.00 | $100.00 | $138.58 |
| 83 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 32 | $25.00 | $20.00 | $15.00 | $25.93 |
| 84 | Reinforced concrete approach slabs with QC/QA (T=1 (526E10010) | SY | 130 | $325.00 | $480.00 | $400.00 | $386.50 |
| 85 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $43,000 | $19,000 | $50,000 | $19,209 |
| 86 | CPM progress schedule (108E10000) | LS | 1 | $5,000.00 | $2,500.00 | $5,000.00 | $3,120.00 |
| 87 | Maintaining traffic (614E11000) | LS | 1 | $5,000.00 | $14,000 | $5,000.00 | $18,853 |
| 88 | Field office, type B (619E16010) | MNTH | 6 | $3,500.00 | $3,500.00 | $1,200.00 | $4,310.69 |
| 89 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,000 | $22,000 | $35,000 | $39,150 |
| 90 | Mobilization (624E10000) | LS | 1 | $120,000 | $110,000 | $98,674 | $421,352 |
| 100 | Detour signing (614E12420) | LS | 1 | $7,500.00 | $5,500.00 | $5,000.00 | $5,170.00 |
| 101 | Water (616E10000) | MGAL | 0.75 | $5.00 | $125.00 | $10.00 | $272.96 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.