ODOT contract 260280 bid tabulation
FRA-US 33-08.75 Culvert Repl. (CULVERT REPLACEMENT). Let by Ohio DOT on May 21, 2026, FRA. 2 bids received; low bid $2,223,194 by Complete General Construction Company, +31% against the engineer's estimate of $1,699,000.
- Owner
- Ohio DOT
- Letting
- 21 MAY 2026
- Pay items
- 72
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Complete General Construction Company | $2,223,194 | Low | +31% |
| 2 | Axis Civil Construction LLC | $2,472,520 | +11% | +46% |
Engineer's estimate: $1,699,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Complete General Construction Company | 2. Axis Civil Construction LLC |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $36,500 | $30,000 |
| 2 | Structure removed (202E11004) | EACH | 1 | $70,000 | $350,000 |
| 3 | Headwall removed (202E20010) | EACH | 2 | $8,000.00 | $1,500.00 |
| 4 | Pavement removed (202E23000) | SY | 884 | $30.00 | $19.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 509 | $30.00 | $33.00 |
| 6 | Guardrail removed (202E38000) | FT | 448 | $2.00 | $5.00 |
| 7 | Excavation (203E10000) | CY | 881 | $17.00 | $32.00 |
| 8 | Embankment (203E20000) | CY | 2,465 | $19.00 | $32.00 |
| 9 | Subgrade compaction (204E10000) | SY | 1,039 | $6.00 | $4.00 |
| 10 | Guardrail, type MGS (606E15050) | FT | 425 | $24.00 | $25.00 |
| 11 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 3 | $2,620.00 | $2,700.00 |
| 12 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $25,500 | $30,000 |
| 13 | Riprap, type D (601E11000) | SY | 21 | $900.00 | $300.00 |
| 14 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 2 | $150.00 | $400.00 |
| 15 | Rock channel protection, type A with aggregate filter (601E32010) | CY | 64 | $295.00 | $135.00 |
| 16 | Soil analysis test (659E00100) | EACH | 2 | $85.00 | $200.00 |
| 17 | Topsoil (659E00300) | CY | 194 | $30.00 | $75.00 |
| 18 | Seeding and mulching, class 5B, as per plan (659E00581) | SY | 690 | $5.34 | $5.50 |
| 19 | Seeding and mulching (659E10000) | SY | 1,056 | $3.80 | $3.00 |
| 20 | Repair seeding and mulching (659E14000) | SY | 87 | $3.00 | $1.90 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.24 | $750.00 | $1,250.00 |
| 22 | Lime (659E31000) | ACRE | 0.36 | $10.00 | $150.00 |
| 23 | Water (659E35000) | MGAL | 10 | $1.00 | $1.00 |
| 24 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 |
| 25 | Concrete masonry (602E20000) | CY | 13.85 | $3,000.00 | $2,000.00 |
| 26 | 6" shallow pipe underdrains (605E11100) | FT | 450 | $20.00 | $25.00 |
| 27 | 6" base pipe underdrains (605E14000) | FT | 450 | $20.00 | $25.00 |
| 28 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 10 | $60.00 | $40.00 |
| 29 | 6" conduit, type B (611E00900) | FT | 42 | $95.00 | $30.00 |
| 30 | 15" conduit, type B, as per plan (611E05901) | FT | 109 | $650.00 | $200.00 |
| 31 | 15" conduit, type C (611E06100) | FT | 105 | $500.00 | $132.00 |
| 32 | 24" conduit, type B, as per plan (611E10401) | FT | 145 | $725.00 | $260.00 |
| 33 | 108" conduit, type A, 706.02 (611E32000) | FT | 208 | $3,000.00 | $4,480.00 |
| 34 | Catch basin, no. 2-2B, as per plan (611E98471) | EACH | 1 | $10,000 | $3,400.00 |
| 35 | Manhole, no. 3 (611E99574) | EACH | 2 | $5,000.00 | $4,400.00 |
| 36 | Manhole, no. 4, as per plan (611E99601) | EACH | 2 | $10,000 | $13,000 |
| 37 | Precast reinforced concrete outlet (611E99710) | EACH | 1 | $500.00 | $450.00 |
| 38 | Pavement planing, asphalt concrete (T = 1.5") (254E01000) | SY | 7,333 | $4.00 | $4.70 |
| 39 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 220 | $202.00 | $230.00 |
| 40 | Aggregate base (304E20000) | CY | 173 | $85.00 | $129.00 |
| 41 | Tack coat (407E10000) | GAL | 627 | $4.50 | $4.50 |
| 42 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 386 | $250.00 | $270.00 |
| 43 | Special - 12" water main dip class 52 push on joints and fittings (638E20174) | FT | 255 | $325.00 | $290.00 |
| 44 | Special - 12" gate valve with valve box (columbus (638E20586) | EACH | 2 | $5,000.00 | $10,000 |
| 45 | Barrier reflector, type 1 (bidirectional) (626E00102) | EACH | 10 | $13.40 | $15.00 |
| 46 | Ground mounted support, no. 2 post (630E02100) | FT | 28 | $20.00 | $25.00 |
| 47 | Sign, flat sheet (630E80100) | SF | 6.50 | $30.00 | $30.00 |
| 48 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $15.00 | $25.00 |
| 49 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $20.00 | $25.00 |
| 50 | Lane line, 6", type 1 (642E00204) | MI | 0.40 | $2,000.00 | $2,000.00 |
| 51 | Center line, type 1 (642E00300) | MI | 0.20 | $2,000.00 | $2,000.00 |
| 52 | Edge line, 6" (644E00104) | MI | 0.16 | $12,000 | $12,000 |
| 53 | Lane line, 6" (644E00204) | MI | 0.06 | $7,000.00 | $7,000.00 |
| 54 | Center line (644E00300) | MI | 0.08 | $24,000 | $24,000 |
| 55 | Channelizing line, 12" (644E00404) | FT | 311 | $1.80 | $1.80 |
| 56 | Stop line (644E00500) | FT | 62 | $8.00 | $8.00 |
| 57 | Transverse/diagonal line (644E00700) | FT | 82 | $8.00 | $8.00 |
| 58 | Chevron marking (644E00720) | FT | 68 | $8.00 | $8.00 |
| 59 | Lane arrow (644E01300) | EACH | 4 | $98.00 | $98.00 |
| 60 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $95.00 | $65.00 |
| 61 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 1 | $2,200.00 | $3,000.00 |
| 62 | Detour signing (614E12420) | LS | 1 | $15,000 | $15,000 |
| 63 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $465.00 | $200.00 |
| 64 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.20 | $9,250.00 | $9,300.00 |
| 65 | Work zone arrow, class I, 740.06, type I (614E30400) | EACH | 12 | $215.00 | $215.00 |
| 66 | Portable barrier, unanchored (622E41100) | FT | 280 | $47.00 | $35.00 |
| 67 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $395,000 | $225,000 |
| 68 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $13,000 | $20,000 |
| 69 | Maintaining traffic (614E11000) | LS | 1 | $40,000 | $35,000 |
| 70 | Field office, type B (619E16010) | MNTH | 6 | $3,350.00 | $2,900.00 |
| 71 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $15,000 | $18,000 |
| 72 | Mobilization (624E10000) | LS | 1 | $111,000 | $80,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 21, 2026. Compiled by Mirage Metrics.